|
---|
Category:Inspection Plan
MONTHYEARML24018A1382024-01-18018 January 2024 Inservice Inspection Request for Information IR 05000482/20230052023-08-23023 August 2023 Updated Inspection Plan for Wolf Creek Nuclear Operating Corporation, Unit 1 (Report 05000482/2023005) - Mid-Cycle Letter 2023 IR 05000482/20220062023-03-0101 March 2023 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2022006) ML22321A2662022-11-16016 November 2022 January 2023 Emergency Preparedness Program Inspection - Request for Information IR 05000482/20220052022-08-23023 August 2022 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2022005) ML22215A2742022-08-0202 August 2022 Inservice Inspection Request for Information ML22249A2552022-06-29029 June 2022 Request for Information for an NRC Post-Approval Site Inspection for License Renewal 05000482/2022012 ML22130A7662022-05-10010 May 2022 Notification of Inspection (NRC Inspection Report 05000482/2022003) and Request for Information ML22123A2702022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 IR 05000482/20224012022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 IR 05000482/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000482/2021006) ML22025A3612022-01-21021 January 2022 PI&R RFI Final ML22019A0932022-01-19019 January 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000482/2022002) and Request for Information ML21322A2952021-11-19019 November 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000482/2022001 and Request for Information ML21237A5212021-09-0101 September 2021 Wc Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21132A1032021-05-12012 May 2021 Document Request List, Paperwork Reduction Act Statement ML21123A0412021-05-0505 May 2021 Notification of NRC Design Bases Assurance Inspection (Teams) (05000482/2021010) and Initial Request for Information IR 05000482/20190062021-03-0303 March 2021 Annual Assessment Letter (Report 05000482/2019006) ML21061A3412021-02-25025 February 2021 Request for Information: Wolf Creek Nuclear Station, Dated February 11, 2021, Inspection Report 05000482/2021002 Occupational Radiation Safety Inspection-1, 2, PI ML21026A1982021-01-26026 January 2021 Inservice Inspection Request for Information ML20104C1472020-04-13013 April 2020 Notification of Inspection (NRC Inspection Report 05000482/2020003) and Request for Information ML20099G9422020-04-0808 April 2020 Notification of NRC Biennial Problem Identification and Resolution Inspection (05000482/2020010) and Initial Request for Information ML20055E1132020-03-0303 March 2020 WC2019006 Annual Assessment Letter ML20024D7072020-01-24024 January 2020 Notification of NRC Design Bases Assurance Inspection (Programs) (05000482/2020011) and Initial Request for Information IR 05000482/20190052019-08-30030 August 2019 Updated Inspection Plan for Wolf Creek Generating Station, Report 05000482/2019005 ML19158A0782019-06-0505 June 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2019003) and Request for Information IR 05000482/20180062019-03-0404 March 2019 Annual Assessment Letter for Wolf Creek Report 05000482/2018006) ML19043A9462019-02-12012 February 2019 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000482/2019002) and Request for Information IR 05000482/20180052018-08-31031 August 2018 Updated Inspection Plan for Wolf Creek Generating Station, Unit 1, (Inspection Report 05000482/2018005) IR 05000482/20170062018-03-0101 March 2018 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006) ML17311A5182017-11-0101 November 2017 Notification of NRC Inspection of Implementation of Mitigation Strategies Assessment Plans (05000482/2018008) and Request for Information IR 05000482/20170052017-08-28028 August 2017 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2017005) IR 05000482/20160062017-03-0101 March 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016006) IR 05000482/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016005) ML16237A0732016-08-31031 August 2016 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016005) IR 05000482/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Wolf Creek Generating Station (NRC Physical Security Inspection Reports Number 05000482/2016401) ML16085A0532016-03-25025 March 2016 Operating Corp - Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2016002) and Request for Information IR 05000482/20150062016-03-0202 March 2016 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2015006) IR 05000482/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2015005) ML15015A1712015-01-0808 January 2015 Focused Baseline Inspection at the Wolf Creek Site for a Major Essential Service Water Modification IR 05000482/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Wolf Creek Generating Station (NRC Physical Security Inspection Report Number 05000482/2014402) IR 05000482/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2014006) ML14231A0682014-08-19019 August 2014 Notification of Inspection (NRC Inspection Report 05000482-14-005) and Request for Information ML14063A6282014-03-0404 March 2014 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2013001) ML13246A2992013-09-0303 September 2013 Midcycle Assessment Letter 2013 IR 05000482/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - Wolf Creek Generating Station (05000482/2012006) IR 05000482/20120012012-03-0505 March 2012 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482-12-001) ML1124403182011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - Wolf Creek Generating Station ML1106300832011-03-0404 March 2011 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482-11-001) ML1024403512010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Wolf Creek Generating Station 2024-01-18
[Table view] Category:Letter
MONTHYEARML24025A0992024-01-25025 January 2024 Withdrawal of Request for Exemption from Specific 10 CFR Part 73 Requirements ML24018A0792024-01-22022 January 2024 Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed Nshcd and Opportunity for a Hearing (EPID L-2024-LLA-0007) (Letter) ML24018A1382024-01-18018 January 2024 Inservice Inspection Request for Information ML24018A2482024-01-18018 January 2024 License Amendment Request to Modify the Implementation Date of License Amendment No. 238 IR 05000482/20230042024-01-11011 January 2024 Integrated Inspection Report 05000482/2023004 ML23356A0722024-01-0404 January 2024 Supplemental Information Needed for Acceptance of Requested Licensing Actions Exemption from Specific 10 CFR Part 73N Requirements (EPID L-2023-LLE-0048) (Redacted Version) WO 23-0002, Operating Corp., Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-0082023-12-26026 December 2023 Operating Corp., Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-008 ML23348A3662023-12-18018 December 2023 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000482 2024012) and Request for Information ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23299A2662023-11-29029 November 2023 Issuance of Amendment No. 238 Modified Implementation Date of License Amendment No. 237 ML23331A4972023-11-27027 November 2023 Supplement to License Amendment Request to Modify the 90-Day Implementation of License Amendment No. 237 ML23325A2112023-11-20020 November 2023 Submittal of Request for Exemption from Specific Provisions in 10 CFR 73.55 ML23320A2772023-11-16016 November 2023 License Amendment Request to Revise Ventilation Filter Testing Program Criteria in Technical Specification 5.5.11.b and Administrative Correction of Absorber in Technical Specification 5.5.11 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23305A3472023-11-0101 November 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML23292A3592023-10-19019 October 2023 License Amendment Request to Modify the 90-Day Implementation of License Amendment No. 237 ML23292A3572023-10-19019 October 2023 Operating Corporation, Request for Correction in Response to Issuance of Amendment No. 237 and Corresponding Safety Evaluation ML23277A2772023-10-11011 October 2023 Regulatory Audit Summary Concerning Review of Request Number CI3R-01 for Proposed Alternative Inspection Frequency for Containment Unbonded Post Tensioning System Components ML23284A2392023-10-11011 October 2023 NRC Initial Operator Licensing Examination Approval 05000482/2023301 ML23276B4552023-10-0303 October 2023 Technical Specification 5.6.8 Post Accident Monitoring (PAM) Report ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L ML23256A2062023-09-14014 September 2023 Withdrawal of Requested Licensing Action Exemption from Specific 10 CFR Part 73 Requirements ML23165A2502023-08-31031 August 2023 Issuance of Amendment No. 237 Request for Deviation from Fire Protection Requirements ML23243A0002023-08-31031 August 2023 Wolf Generating Station - Withdrawal of Request for Exemption from Specific 10 CFR Part 73 Requirements IR 05000482/20230052023-08-23023 August 2023 Updated Inspection Plan for Wolf Creek Nuclear Operating Corporation, Unit 1 (Report 05000482/2023005) - Mid-Cycle Letter 2023 ML23232A0012023-08-19019 August 2023 Revision of One Procedure That Implements the Radiological Emergency Response Plan (Rerp). Includes EPP 06-009, Rev. 13 ML23221A3932023-08-0909 August 2023 Submittal of Request for Exemption from Specific 10 CFR Part 73 Requirements ML23220A4222023-08-0808 August 2023 Supplement to License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ML23201A1212023-08-0707 August 2023 Issuance of Amendment No. 236 Revision to Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML23130A2902023-07-26026 July 2023 Issuance of Amendment No. 235 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections IR 05000482/20230022023-07-11011 July 2023 Integrated Inspection Report 05000482/2023002 ML23167A0042023-06-26026 June 2023 Audit Plan to Support Review of Request for Alternative Containment Inservice Inspection Frequency IR 05000482/20234012023-06-21021 June 2023 Security Baseline Inspection Report 05000482/2023401 ML23171B1312023-06-20020 June 2023 Additional Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML23151A4162023-05-31031 May 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) ET 23-0006, CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components2023-05-17017 May 2023 CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components WO 23-0014, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-17017 May 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23132A1532023-05-12012 May 2023 Transmittal of 2022 Annual Financial Reports WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) ML23135A1172023-05-0808 May 2023 Redacted Version of Revision 36 to Updated Safety Analysis Report ML23117A2112023-04-27027 April 2023 Annual Exposure Report (2022) ML23117A1342023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report Report 46 2024-01-04
[Table view] |
Text
March 2, 2022
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2021006)
Dear Mr. Reasoner The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Wolf Creek Generating Station, reviewing performance indicators (PIs),
inspection results, and enforcement actions from January 1, 2021 through December 31, 2021.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
The NRC determined the performance at the Wolf Creek Generating Station during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e.,
Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2023.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities to return to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and as discussed in our November 2, 2021 memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302),
C. Reasoner 2 it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission. For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
On July 18, 2019, the NRC issued a Confirmatory Order (EA-18-165) documenting the commitments made as part of a settlement agreement between Wolf Creek and the NRC. The settlement agreement relates to the apparent violation of NRC requirements as discussed in our letter dated April 2, 2019 (ADAMS Accession Number ML19092A335). That letter provided you with the results of an investigation conducted by the NRC's Office of Investigations at the Wolf Creek Generating Station to determine whether a maintenance worker and a supervisor willfully documented inaccurate information in a required record regarding the cleaning and inspection of control rod drive mechanisms on October 31, 2016. Therefore, the NRC plans to conduct Inspection Procedure 92702, Follow Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirmatory Orders to follow up on your actions to address these commitments. The schedule for this inspection will be decided at a later date since the Confirmatory Order contains actions that are due in 2023.
Inspection procedure (IP) 71111.21N.03 is included in the inspection plan as a placeholder for your next design basis assurance inspection (Programs), which will be focused on commercial grade dedication. The inspection procedure will be developed and made publicly available before these inspections begin.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200-1141 with any questions you have regarding this letter.
Sincerely,
/RA/
Gregory E. Werner, Chief Project Branch B Docket No. 05000482 Division of Operating Reactor Safety License No. NPF-42 Enclosure:
Inspection Plan
ML22045A978 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: JFM1 Yes No Publicly Available Sensitive NRC-002 OFFICE PE:DORS/B C:DORS/B NAME JMelfi GWerner SIGNATURE /RA/ /RA/
DATE 02/18/2022 02/22/2022
Site Inspection Activity Plan 07200079 - Wolf Creek 01/01/2022 - 12/31/2023 Unit Start End Activity CAC Title Staff Count Wolf Creek ISFSI First Loading Inspection 2 1 1/7/2022 3/31/2022 IP 60855 001001 Operation Of An ISFSI 1 1/7/2022 3/31/2022 IP 60856 001003 Review of 10 CFR 72.212(b) Evaluations Prepared on 2/22/2022 1:49:38 PM 1 of 3
Site Inspection Activity Plan Wolf Creek 01/01/2022 - 12/31/2023 Unit Start End Activity CAC Title Staff Count Heat Exchanger/Sink Performance Inspection - 07T - Wolf Creek 2 1 3/7/2022 3/11/2022 IP 71111.07T 000700 Heat Exchanger/Sink Performance Wolf Creek Biennial PI&R 4 1 3/14/2022 3/18/2022 IP 71152B 000747 Problem Identification and Resolution 1 3/28/2022 4/1/2022 IP 71152B 000747 Problem Identification and Resolution 10 CFR 50.59 Inspection - 17T - Wolf Creek 3 1 4/11/2022 4/15/2022 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments Security Access Control .02 1 1 4/18/2022 4/22/2022 IP 71130.02 000734 Access Control 1 4/18/2022 4/22/2022 IP 71130.09 001656 Security Plan Changes 1 4/18/2022 4/22/2022 IP 71151 001338 Performance Indicator Verification WC Target Set Inspection 2 1 5/30/2022 6/3/2022 IP 71130.14 000743 Review of Power Reactor Target Sets Security Protective Strategy .05 2 1 6/20/2022 6/24/2022 IP 71130.05 000737 Protective Strategy Evaluation WC 2022 BRQ 3 1 6/26/2022 7/2/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP 5,8 - WC 2 1 7/18/2022 7/22/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 7/18/2022 7/22/2022 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Security Training/Equip Maint .07 and .04 2 1 7/18/2022 7/22/2022 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 7/18/2022 7/22/2022 IP 71130.07 000739 Security Training MC&A - WC 1 1 7/18/2022 7/22/2022 IP 71130.11 000742 Material Control and Accounting (MC&A)
Cyber Security Inspection - WC 4 1 8/1/2022 8/5/2022 IP 71130.10 000741 Cybersecurity 2022 EP Exercise & PI Inspection - WC 4 1 8/29/2022 9/2/2022 IP 71114.01 000716 Exercise Evaluation 1 8/29/2022 9/2/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 8/29/2022 9/2/2022 IP 71151 001397 Performance Indicator Verification Prepared on 2/22/2022 1:49:38 PM 2 of 3
Site Inspection Activity Plan Inservice Inspection RF25 - WC 1 1 9/29/2022 10/14/2022 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 1,3,PI - WC 2 1 10/3/2022 10/7/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 10/3/2022 10/7/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Design Bases Assurance Inspection (Program) - 21N - Wolf Creek 3 1 1/1/2023 6/30/2023 IP 71111.21N.03 Design Bases Assurance Inspections (Programs) 2023 (Commercial Grade Dedication)
EP 2023 Program Inspection - WC 1 1 1/9/2023 1/13/2023 IP 71114.02 000717 Alert and Notification System Testing 1 1/9/2023 1/13/2023 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 1/9/2023 1/13/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 1/9/2023 1/13/2023 IP 71114.05 000720 Maintenance of Emergency Preparedness Security Access Authorization .01 and Access Control .02 + PIV + Plan Change .09 2 1 1/23/2023 1/27/2023 IP 71130.01 000733 Access Authorization 1 1/23/2023 1/27/2023 IP 71130.02 000734 Access Control 1 1/23/2023 1/27/2023 IP 71130.09 001656 Security Plan Changes 1 1/23/2023 1/27/2023 IP 71151 001338 Performance Indicator Verification RP 6,7 - 2 1 5/15/2023 5/19/2023 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 5/15/2023 5/19/2023 IP 71124.07 000731 Radiological Environmental Monitoring Program Security FFD .08 1 1 5/22/2023 5/26/2023 IP 71130.08 000740 Fitness For Duty Program EP 2023 Exercise Scenario In-Office Rvw 71114.08 - WC 4 1 9/1/2023 10/14/2023 IP 71114.08 000723 Exercise Evaluation Scenario Review RP 1,4,PI - 2 1 9/11/2023 9/15/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 9/11/2023 9/15/2023 IP 71124.04 000728 Occupational Dose Assessment EP 2023 Biennial Exercise & PI Inspection - WC 4 1 11/13/2023 11/17/2023 IP 71114.01 000716 Exercise Evaluation 1 11/13/2023 11/17/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 11/13/2023 11/17/2023 IP 71151 001397 Performance Indicator Verification Prepared on 2/22/2022 1:49:38 PM 3 of 3