IR 05000482/2024001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000482/2024001
ML24107A888
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 04/17/2024
From: Greg Werner
NRC/RGN-IV/DORS/PBB
To: Reasoner C
Wolf Creek
References
IR 2024001
Download: ML24107A888 (33)


Text

April 17, 2024

SUBJECT:

WOLF CREEK GENERATING STATION - INTEGRATED INSPECTION REPORT 05000482/2024001

Dear Cleve Reasoner:

On March 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Wolf Creek Generating Station. On April 4, 2024, the NRC inspectors discussed the results of this inspection with R. Bayer, General Manager, Plant Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Both of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Wolf Creek Generating Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Wolf Creek Generating Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Gregory E. Werner, Chief Reactor Projects Branch B Division of Operating Reactor Safety Docket No. 05000482 License No. NPF-42

Enclosure:

As stated

Inspection Report

Docket Number:

05000482

License Number:

NPF-42

Report Number:

05000482/2024001

Enterprise Identifier:

I-2024-001-0010

Licensee:

Wolf Creek Nuclear Operating Corp.

Facility:

Wolf Creek Generating Station

Location:

Burlington, KS

Inspection Dates:

January 1 to March 31, 2024

Inspectors:

C. Henderson, Senior Resident Inspector

R. Kopriva, Senior Project Engineer

J. Melfi, Project Engineer

D. Proulx, Senior Project Engineer

Approved By:

Gregory E. Werner, Chief

Reactor Projects Branch B

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Wolf Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Maintain Surveillance Testing Procedure in Accordance with the Fire Protection Program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000482/2024001-01 Open/Closed None (NPP)71111.24 The inspectors identified a Green finding and associated non-cited violation of Technical Specification 5.4.1.d, for the licensees failure to maintain a fire protection program procedure.

Specifically, the licensee failed to maintain procedure STN RP-002H, Essential Service Water Train B to Component Cooling Water Heat Exchanger B Isolation Switch, revision 2, to perform the required 18-month post-fire safe shutdown normal/bypass (isolation) switch surveillance testing for train B essential service water from component cooling water heat exchanger isolation valve, EFHV0060.

Failure to Perform Post-Maintenance Testing Following Maintenance and Installation of the Bypass Reactor Trip Breaker Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000482/2024001-02 Open/Closed

[H.5] - Work Management 71111.24 The inspectors identified a Green finding and associated non-cited violation of Technical Specification 5.4.1.a for the licensee failure to perform appropriate post-maintenance testing following reactor trip breaker maintenance and installation to verify full technical specification operability.

Additional Tracking Items

None.

PLANT STATUS

Wolf Creek Generating Station began the inspection period at full power. On March 24, 2024, the unit commenced power coast down. On March 28, 2024, the unit was shut down to begin refueling outage (RF)

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1)winter weather advisory with wind gusts of approximately 45 mph and extreme cold weather temperatures on January 16, 2024

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)operator action to isolate a faulted steam generator on February 8, 2024 (2)reactor protection system and anticipated transient without scram actions on February 15, 2024 (3)turbine-driven auxiliary feedwater pump and motor-driven auxiliary feedwater pump A to steam generator D on February 28, 2024 (4)train B class 1E recirculation system for planned maintenance of train A class 1E air conditioning system on March 12, 2024

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the 480 volt AC distribution system on March 14, 2024.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)missed 18-month fire protection surveillance for the isolation/bypass switch for train B essential service water from component cooling water heat exchanger isolation valve, fire area C-27, on January 16, 2024 (2)diesel-driven fire pump area, fire area circulating water screen house, on January 31, 2024 (3)auxiliary building, 2026-foot elevation, fire area A-16, on February 2, 2024 (4)auxiliary feedwater valve compartment number one, fire area A-29, on February 9, 2024 (5)auxiliary panel shutdown room, fire area A-28, on February 14, 2024 (6)reactor protection system motor generator set room, fire area A-27, on February 28, 2024

Fire Brigade Drill Performance Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill turbine building north 2032-foot elevation, 480 volt motor control center PG-015 on February 14, 2024.
(2) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill auxiliary building elevation 2026-foot, south electrical penetration room 480 volt load center XPG22 on March 8, 2024.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections for a feedwater line break inside containment, main steam enclosure, and turbine building on February 15, 2024.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during end of core life moderator temperature coefficient measurement and plant shut down for RF 26 on March 28, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated just-in-time training for plant shutdown for RF 26 on March 18, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)480 volt distribution system maintenance and testing on February 21, 2024 (2)reactor protection system and anticipated transient without scram actions maintenance and testing on February 28, 2024

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)class 1E motor-operated valve thermal overload maintenance and testing on March 4, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (9 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)train A safety injection equipment outage January 11, 2024 (2)emergency diesel generator B and train B essential service water equipment outage on January 23, 2024 (3)train B motor-driven feedwater equipment outage on January 29, 2024 (4)circulating water bay C diving activities and unavailability for the diesel and motor-driven fire protection pumps on January 31, 2024 (5)train A essential service water system equipment outage and emergency diesel generator A in maintenance lockout on February 6, 2024 (6)emergency work activities of unplanned nitrogen and instrument air leak for steam generator A atmospheric relief valve and turbine-driven auxiliary feedwater flow control valve accumulator on March 10, 2024 (7)train A class 1E air conditioning system and residual heat removal equipment outage on March 13, 2024 (8)emergent work activities for troubleshooting of a step change in nitrogen leakage for the steam generator D atmospheric relief valve and turbine-driven auxiliary feedwater flow control valve accumulator on March 14, 2024 (9)emergent work activities for emergency diesel generator B failure to manual start on March 29, 2024.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)chemical and volume control valve to safety injection pump A valve, EMHV8924, closed with safety injection pump A unavailable and 100 percent emergency core cooling system flow equivalent from both trains operability determination on January 17, 2024 (2)train B class 1E air conditioning system, SGK05B, tripped on high pressure discharge past operability determination on January 22, 2024 (3)feedwater line D flow accelerated corrosion design pressure requirement operability determination on February 6, 2024 (4)failure to isolate a faulted steam generator with a single failure of the remotely operated valve operability determination on February 27, 2024 (5)emergency diesel generator B governor control load decrease while increasing load during surveillance testing operability determination on February 27, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1)large break loss of coolant accident dose analysis re-evaluation on February 6, 2024 (2)steam generator A atmospheric relief valve gauge block removal on March 13, 2024

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial)

The inspectors evaluated RF 26 activities from March 28 - 31, 2024. The inspectors completed inspection procedure sections 03.01.a and 03.01.b.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (8 Samples)

(1)containment cooler D 480 volt breaker fast and slow speed mechanical interlock replacement post-maintenance testing on January 3, 2024 (2)train A containment spray system room cooler belt replacement on January 25, 2024 (3)train A swing inverter, NN15, post-maintenance testing on January 25, 2024 (4)train B essential service water travelling screen post-maintenance testing on January 25, 2024 (5)emergency diesel generator B post-maintenance testing on February 20, 2024 (6)turbine-driven auxiliary feedwater equipment outage post-maintenance testing on February 21, 2024 (7)train B essential service water travel screen motor-operated valve, EFHV0092, corrective and preventative maintenance post-maintenance testing on February 29, 2024 (8)emergent repairs for steam generator A atmospheric relief valve on March 13, 2024

Surveillance Testing (IP Section 03.01) (3 Samples)

(1)train B essential service water motor-operated valve fire protection isolation switch surveillance testing on January 5, 2024 (2)inservice testing requirements for auxiliary feedwater discharge isolation valves ALV032, ALV047, ALV044, ALV035, ALV056, ALV066, ALV071, and ALV061 on February 9, 2024 (3)reactor trip and bypass breaker response time testing and maintenance on February 27, 2024

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1)turbine-driven auxiliary feedwater discharge to steam generator air operated valve, ALHV0006, on February 27, 2024

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1)simulated reactor coolant pump A shaft shear and failure of automatic reactor trip and manual trip from the control room on January 31,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) January 1, 2023, through December 31, 2023 IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)
(1) January 1, 2023, through December 31, 2023

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

(1) January 1, 2023, through December 31, 2023

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)failure to perform essential service water motor-operated valve 18-month isolation/bypass surveillance extent of condition (2)failure to perform adequate reactor trip breaker work planning, and post-maintenance testing

INSPECTION RESULTS

Failure to Maintain Surveillance Testing Procedure in Accordance with the Fire Protection Program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000482/2024001-01 Open/Closed None (NPP)71111.24 The inspectors identified a Green finding and associated non-cited violation of Technical Specification 5.4.1.d, for the licensees failure to maintain a fire protection program procedure. Specifically, the licensee failed to maintain procedure STN RP-002H, Essential Service Water Train B to Component Cooling Water Heat Exchanger B Isolation Switch, revision 2, to perform the required 18-month post-fire safe shutdown normal/bypass (isolation) switch surveillance testing for train B essential service water from component cooling water heat exchanger isolation valve, EFHV0060.

Description:

The inspectors reviewed the licensees Updated Safety Analysis Report (USAR),off normal procedures, and surveillance procedures for the normal/bypass (isolation) switches for the train B essential service water system motor-operated valves that are credited for post-fire safe shutdown to determine the required surveillance testing. Specifically, the inspectors reviewed three off normal procedures including: procedure OFN RP-017, Control Room Evacuation, revision 56; procedure AP 10-100, Fire Protection Program, revision 26; and procedure STN RP-002H, Essential Service Water Train B to Component Cooling Water Heat Exchanger B Isolation Switch, revision 2, and identified the following:

  • Procedure AP 10-100, step 6.3.12.3, stated, in part that all STN RP-002 series of procedures are performed at least once per 18-months to verify the operability of normal/bypass (isolation) switches credited for post-fire safe shutdown that are used to bypass circuits that could be affected by a fire.
  • Off normal procedure OFN RP-017 was used to determine the operability of credited post-fire safe shutdown B essential service water motor-operated valves that are operated by normal/bypass (isolation) switches located at the 480 volt motor control centers, which included train B essential service water from component cooling water heat exchanger motor-operated isolation valve, EFHV0060. The required position of EFHV0060 for post-fire safe shutdown was maintain/close to ensure adequate essential service water flow to all train B components required for post-fire safe shutdown.
  • Procedure STN RP-002H was utilized to verify the operability of train B essential service water to and from the component cooling water heat exchanger B. However, EFHV0060 isolation switch, that was used to bypass circuits that could be affected by a fire in the control room, was not being testing every 18 months.

From the above, the inspectors determined that the licensee failed to perform the 18-month surveillance testing to verify the operability of the normal/bypass (isolation) switch credited for postfire safe shutdown for valve EFHV0060 in accordance with procedure AP 10-100, step 6.3.12.3. The inspectors informed the licensee of the issue. The licensee then entered it into their corrective action program as condition report 10029354. The licensee confirmed valve EFHV0060 normal/bypass (isolation) switch was not being testing every 18 months and was last tested March 2014. Valve EFHV0060 normal/bypass (isolation) switch was installed in 2013 at its 480 volt motor control center in accordance with change package 13898, and the licensee failed to identify that procedure STN PR-002H was required to be updated to ensure valve EFHV0060 normal/bypass (isolation) switch was tested every 18 months.

Corrective Action: The licensee performed an extent of condition review, established an hourly fire watch for the control room, and revised procedure STN RP-002H to perform 18-month surveillance testing for valve EFHV0060 normal/bypass (isolation) switch during RF 26.

Corrective Action Reference: Condition reports 10029354 and 10031492

Performance Assessment:

Performance Deficiency: The licensees failure to maintain procedure STN RP-002H to perform required fire protection program 18-month isolation/bypass surveillance testing for valve EFHV0060 normal/bypass (isolation) switch, was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the procedural quality attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the licensees failure to maintain procedural guidance to perform required 18-month isolation/bypass surveillance testing for valve EFHV0060 normal/bypass (isolation) switch prevented the licensee from verifying the valve was capable of being/maintained closed from the motor control center in a case of a fire in the control room.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix F, Fire Protection Significance Determination Process. The inspectors assigned the finding a fire category 1.4.7, because the finding involved post-fire safe shutdown. The inspectors determined that the finding had very low safety significance (Green) because the finding did not adversely affect the ability to reach and maintain hot shutdown/hot standby or safe and stable conditions using the credited safe shutdown success path.

Cross-cutting Aspect: Not present performance. Specifically, the performance deficiency occurred in 2013 when the licensee modified the motor control center for EFHV0060 to provide the isolation/bypass circuit to allow for local operation and failed to update procedure STN RP-002H.

Enforcement:

Violation: Technical Specification 5.4.1.d requires that written procedures shall be established, implemented, and maintained covering fire protection program implementation.

Procedure STN RP-002H, Essential Service Water Train B to Component Cooling Water Heat Exchanger B Isolation Switch, revision 2, verified the operability of train B essential service water motor-operated valves for the component cooling water heat exchanger B isolation switch used to bypass circuits that could be affected by a fire.

Contrary to the above, from March 2014 to January 2024, the licensee failed to maintain a procedure covering the fire protection program implementation. Specifically, the licensee failed to maintain procedure STN RP-002H to perform the required 18-month isolation/bypass switch surveillance testing for train B essential service water from component cooling water heat exchanger isolation valve, EFHV0060.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with section2.3.2 of the Enforcement Policy.

Failure to Perform Post-Maintenance Testing Following Maintenance and Installation of the Bypass Reactor Trip Breaker Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000482/2024001-02 Open/Closed

[H.5] - Work Management 71111.24 The inspectors identified a Green finding and associated non-cited violation of Technical Specification 5.4.1.a for the licensee failure to perform appropriate post-maintenance testing following reactor trip breaker maintenance and installation to verify full technical specification operability.

Description:

On August 18, 2020, while the plant was in Mode 1, in accordance with work order (WO) 18-444075-000, the licensee installed a vendor overhauled reactor trip breaker as train B reactor trip bypass breaker (BYB), and during RF 24 (March 25 - May 9, 2021) the breaker was moved to train A reactor trip breaker (RTA) in accordance with WO 20-459184-000. Following being placed in the RTA position, on April 28, 2021, the breaker failed surveillance procedure STS IC-215, Trip Actuating Device Operational Test, Trip and Bypass Breaker UV/Shunt Trip, Turbine Trip on Reactor Trip and P4, revision 17. Specifically, the reactor trip breaker failed to generate the turbine trip signal associated with the P-4 interlock upon a reactor trip, because the interlock was not wired into the circuit when the breaker was overhauled. Additionally, surveillance procedure STS IC-215 can only be performed in Modes 4, 5, 6, and defueled. The licensee corrected this deficiency during RF 24 and initiated condition reports (CR) 10004991 and 10005013 and performed a past operability review and equipment performance evaluation.

The inspectors reviewed WO 18-444075-000, WO 20-259184-000, CR 10004991, CR 10005013, the past operability and equipment performance evaluation, technical specifications and identified the following:

(1) trip the main turbine - Modes 1 and 2,
(2) isolate main feedwater with coincident low reactor coolant average temperature - Modes 1 and 2,
(3) allows manual block of the automatic re-actuation of safety injection after a manual reset of safety injection - Modes 1, 2, and 3,
(4) prevents opening of the main feedwater isolation valves if closed on safety injection and steam generator water level high-high - Modes 1, 2, and 3.
  • The equipment performance evaluation and the past operability determined the turbine trip did not function because two wires connecting the trip contact, as seen on drawing M-766-01045, to the test points and TB4 terminals 1 and 4, as seen on drawing M-766-1043, were not installed during the breakers overhaul performed by a vendor. This issue was identified during the performance of surveillance procedure STS IC-215 The function of the trip contact was to produce a turbine trip signal from the P-4 interlock upon a reactor trip breaker opening. Additionally, between August 18, 2020, and RF 24, BYB was racked to connect for testing of RTB on October 10, 2020, and February 4, 2021, for approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of the 48-hour completion time for LCO 3.3.2 condition F in support of train B reactor trip breaker quarterly testing.

During these periods, if a reactor trip occurred by BYB, no turbine trip signal would have been generated from the P-4 interlock, however, RTA was fully capable of generating the required turbine trip, so no complete loss of safety function occurred.

The equipment performance evaluation and past operability documented in CRs 10004991 and 10005013 did not review the maintenance practice of installing and performing maintenance on reactor trip breakers in Mode 1, nor did it contain corrective actions associated with the maintenance practice.

  • The installation WO 18-445075-000 stated to perform maintenance on the spare reactor trip breaker in accordance with maintenance procedure MPE M766Q-03, Reactor Trip Switchgear Breaker, revision 24, and perform as found and as left testing in accordance with surveillance procedure STS IC-746, Reactor Trip and Bypass Breaker Response Time Testing, revision 2C. The purpose of surveillance procedure STS IC-746 was to perform response time testing on train A and B reactor trip breakers and bypass reactor trip breakers which does not test all the technical specification design functions, including the reactor trip P-4 interlocks.

The inspectors concluded the licensee did not properly pre-plan maintenance and installation of overhauled reactor trip breakers in Mode 1 to ensure adequate post-maintenance testing was performed to demonstrate full technical specification operability.

Corrective Actions: The licensee initiated actions to review what modes of operation are appropriate for performing maintenance, installation, and testing of reactor trip breakers.

Corrective Action References: Condition reports 10031001 and 10031493

Performance Assessment:

Performance Deficiency: The licensees failure to perform appropriate post-maintenance testing following reactor trip breaker maintenance and installation to verify full technical specification operability was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the equipment performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, failure to perform the appropriate post-maintenance testing prevented the licensee from identifying the train B bypass reactor trip breaker P-4 interlock was inoperable.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding was determined to be of very low safety significance (Green) because it

(1) was not a deficiency affecting design or qualification of a mitigating system,
(2) does not represent a loss of the probability risk analysis (PRA) function of a single train technical specification system for greater than allowed outage time,
(3) does not represent a loss of PRA function of one train of a multi-train technical specification for greater than its allowed outage time, (4)does not represent a loss of the PRA function of two separate technical specification systems for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />,
(5) does not represent a loss of PRA system and/or function as defined by the plant risk information e-book or licensees PRA for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and
(6) does not result in the loss of a high safety-significant, nontechnical specification train for greater than 3 days.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. Specifically, inappropriately planning the installation of vendor overhauled reactor trip breakers in Mode 1 prevented the licensee from performing adequate post-maintenance testing to verify proper operation of the reactor trip breaker in the bypass location to ensure it was fully operable.

Enforcement:

Violation: Technical Specification 5.4.1.a, requires, in part, that written procedures be established, implemented, and maintained covering applicable procedures recommended in appendix A to Regulatory Guide 1.33, Quality Assurance Program Requirements, revision 2, dated February 1978. Regulatory Guide 1.33, appendix A, section 9.a, requires, in part, maintenance that can affect the performance of safety-related equipment should be properly pre-planned and performed in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances. Work order 18-445075-000 pre-planned the maintenance and installation of reactor trip bypass breaker B.

Contrary to the above, between August 2020 to March 2021, the licensee failed to properly pre-plan and perform maintenance that affected safety-related equipment. Specifically, WO 18-445075-000 failed to provide appropriate instructions for safety-related bypass reactor trip breaker post-maintenance testing following maintenance and installation to verify the breaker was fully operable, by testing the technical specification required P-4 interlock.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 4, 2024, the inspectors presented the integrated inspection results to R. Bayer, General Manager, Plant Operations, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

Condition Reports

10029393, 10029523, 10029546

71111.01

Drawings

M-12BN01

Piping and Instrumentation Diagram Borated Refueling

Water Storage Tank

71111.01

Drawings

M-12EC02

Piping and Instrumentation Diagram Fuel Pool Cooling and

Clean-Up System

71111.01

Procedures

AI 14-006

Severe Weather

71111.01

Procedures

ALR 00-055F

FRZ Prot Trouble

71111.01

Procedures

STS CH-021

Spent Fuel Pool Boron Concentration Determination

9A

71111.01

Procedures

SYS EC-121

Recirc of the RWST Through the Fuel Pool Cleanup System

71111.01

Procedures

SYS EF-205

ESW/CIRC Water Cold Weather Operations

71111.01

Work Orders

WO 39464

71111.04

Calculations

XX-E-004

AC Motor Operated Valve Minimum Terminal Voltage

71111.04

Calculations

XX-E-009

System NB, NG, PG Undervoltage/Degraded Voltage Relay

Setpoints

71111.04

Corrective Action

Documents

Condition Reports

10009424, 10028903, 10028925

71111.04

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10030450

71111.04

Drawings

E-018-0852

MMC Cubicles SZ 5 2SP-1WD Schematic

W12

71111.04

Drawings

E-018-0853

Wiring Diagram 2SP IWD (Size 5)

W12

71111.04

Drawings

E-11NG01

Low Voltage System Class 1E 480V Single Line Meter and

Relay Diagram

71111.04

Drawings

E-11NG02

Low Voltage System Class 1E 480 V. Single Line Meter and

Relay Diagram

71111.04

Drawings

E-11NG20

Low Voltage System Class 1E Motor Control Center

Summary

318

71111.04

Drawings

E-13EF09A

Schematic Diagram ESW To/From Containment Air Coolers

Isolation Valve

71111.04

Drawings

E-13GN02A

Schematic Diagrams Containment Cooler B and D

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Drawings

E-13NG01A

Low Voltage System Class 1E 480 V Three Line Meter and

Relay Diagram

71111.04

Drawings

E-1F9915

Design Basis Document for OFN RP-017, Control Room

Evacuation

71111.04

Drawings

KD-7496

One Line Diagram

71111.04

Drawings

M-12AB01

Piping and Instrumentation Diagram Main Steam System

71111.04

Drawings

M-12AB02

Piping and Instrumentation Diagram Main Steam System

71111.04

Drawings

M-12AE02

Piping and Instrumentation Diagram Feedwater System

71111.04

Drawings

M-12AL

Piping and Instrumentation Diagram Auxiliary Feedwater

System

71111.04

Drawings

M-12AL01

Piping and Instrumentation Diagram Auxiliary Feedwater

System

71111.04

Drawings

M-12BM01

Piping and Instrumentation Diagram Steam Generator

Blowdown Sys.

71111.04

Miscellaneous

WCRE-34

Fourth 10-Year Interval Inservice Testing Basis Document

71111.04

Procedures

AI 21-016

Operator Time Critical Actions Validation

71111.04

Procedures

ALR 00-025E

NG02 Bus Trouble

71111.04

Procedures

AP 21-004

Operator Response Time Program

5A

71111.04

Procedures

BD-EMG E-0

Reactor Trip or Safety Injection

71111.04

Procedures

BD-EMG E-2

Faulted Steam Generator Isolation

71111.04

Procedures

CKL AL-120

Auxiliary Feedwater Normal Lineup

44A

71111.04

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.04

Procedures

EMG E-2

Faulted Steam Generator Isolation

24A

71111.04

Procedures

EMG FR-S1

Response to Nuclear Power Generation/ATWS

71111.04

Procedures

OFN RP-17

Control Room Evacuation

71111.04

Procedures

STN RP-002G

ESW Train B to CTMT Air Cooler ISO Switch

71111.04

Procedures

SYS GK-201

Mitigating Actions for Inoperable SGK05 Train

21D

71111.04

Procedures

SYS NG-332

Deenergized NG02 NG04 and NG06E

29A

71111.04

Work Orders

WO 15194, 21-475048-000, 21-475048-001

71111.05

Calculations

XX-X-004

Combustible Fire Loading for Each in the Various Fire Areas

at WCNOC

71111.05

Corrective Action

Documents

Condition Reports

10009424, 10029354

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05

Corrective Action

Documents

Resulting from

Inspection

Condition Reports

10030120, 10030121

71111.05

Drawings

E-11NG20

Low Voltage System Class 1E Motor Control Center

Summary

318

71111.05

Drawings

M-12EF02

Piping and Instrumentation Diagram Essential Service Water

System

71111.05

Miscellaneous

E-1F9905

Fire Hazard Analysis

71111.05

Miscellaneous

E-1F9910

Post Fire Safe Shutdown Area Analysis

71111.05

Miscellaneous

PT12386

Post Fire Safe Shutdown Issue

71111.05

Miscellaneous

WCRE-35

Boundary Matrix

71111.05

Procedures

ALR KC-888

Fire Protection Panel KC-008 Alarm Response

71111.05

Procedures

AP 10-100

Fire Protection Program

71111.05

Procedures

AP 10-101

Control of Transient Ignition Sources

71111.05

Procedures

AP 10-102

Control of Combustible Materials

71111.05

Procedures

AP 10-103

Fire Protection Impairment Control

71111.05

Procedures

AP 10-104

Breach Authorization

71111.05

Procedures

AP 10-105

Fire Protection Training and Drills

24B

71111.05

Procedures

AP 10-106

Fire Preplan

71111.05

Procedures

AP 26C-004

Operability Determination and Functionality Assessments

71111.05

Procedures

OFN KC-016

Fire Responses

71111.06

Calculations

XX-M-069

FAC Program Minimum Wall Thickness Calculation for

Large Bore Piping and Components

71111.06

Corrective Action

Documents

Condition Reports

10019400, 10020468, 10021613, 10021652, 10027094,

10028389, 10029850

71111.06

Drawings

M-12AE01

Piping and Instrumentation Diagram Feedwater System

71111.06

Drawings

M-12AE02

Piping and Instrumentation Diagram Feedwater System

71111.06

Drawings

M-12AL01

Piping and Instrumentation Diagram Auxiliary Feedwater

System

71111.06

Drawings

M-13AE05

Piping Isometric Main Feedwater Reactor and Auxiliary

Building

71111.06

Miscellaneous

MS-02

Pipe Class Sheets

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.06

Procedures

EMG E-2

Faulted Steam Generator Isolation

24A

71111.11Q

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.11Q

Procedures

EMG ES-02

Reactor Trip Response

71111.11Q

Procedures

GEN 00-004

Power Operation

2

71111.11Q

Procedures

GEN 00-005

Minimum Load to Hot Standby

71111.11Q

Procedures

STS RE-006

EOL Core MTC Measurement

71111.12

Calculations

XX-E-004

AC Motor Operated Valve Minimum Terminal Voltage

71111.12

Calculations

XX-E-042

Class 1E 480V AC and 208/120V AC System Coordination

71111.12

Corrective Action

Documents

Condition Reports

73120, 73421, 81790, 10004991, 10005001, 10005013,

10007665, 10013896, 10014094, 10018253, 10019416,

10020251, 10020290, 10023534, 10023559, 10024112,

10024908, 10026422, 10026451, 10026459, 10026498,

10027058, 10027518, 10027877, 10028066, 10028432,

10028903, 10028925, 10029210, 10029729, 10029830,

10029484

71111.12

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10030449

71111.12

Drawings

E-025-00007

sheet 201

ESW Screen B Spray EFHV0092

W14

71111.12

Drawings

E-11NG20

Low Voltage System Class 1E Motor Control Center

Summary

318

71111.12

Drawings

E-13NG02

Schematic Diagram Containment Cooler Fans A and C

71111.12

Drawings

M-12AB01

Piping and Instrumentation Diagram Main Steam System

71111.12

Drawings

M-766-01043

05W

71111.12

Engineering

Changes

CP 14923

Restore Regulatory Compliance for Ten 480V MOVs

71111.12

Miscellaneous

2013-049

USAR Change Request

2/12/2013

71111.12

Miscellaneous

E-018A-00007

Instruction Manual for Molded Case Circuit Breaker

W15

71111.12

Miscellaneous

QL-AB

System AB Main Steam System

71111.12

Miscellaneous

WCLR-33

Electrical Cable Connections Not Subject to 10 CFR 50.49

Environmental Qualification Requirements B2.1.36

NUREG-1801 Program XLE6 Aging Management Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.12

Miscellaneous

WCNOC-76

Medium Low Voltage AC and Low Voltage DC Overcurrent

Protection Coordination for Wolf Creek Generating Station

71111.12

Miscellaneous

WCQPM

Wolf Creek Quality Program Manual

71111.12

Procedures

AI 16B-002

Preventive Maintenance Change Process

71111.12

Procedures

AP 16B-003

Planning and Scheduling Preventive Maintenance

8B

71111.12

Procedures

AP 16E-002

Post Maintenance Testing Development

21B

71111.12

Procedures

AP 24D0-003

Receipt Inspection

71111.12

Procedures

I-ENG-005

Infrared Thermography

71111.12

Procedures

MGE EOOP-11

Molded Case Circuit Breaker and Ground Fault Sensor

Testing

71111.12

Procedures

STS IC-211A

Actuation Logic Test Train A Solid State Protection System

37A

71111.12

Procedures

STS IC-211B

Actuation Logic Test Train B Solid State Protection System

38A

71111.12

Procedures

STS IC-215

TADOT of Manual Reactor Trip, Trip and Bypass Breaker

UV/Shunt Trip, Turbine Trip on Reactor Trip and P4

71111.12

Procedures

STS MT-024A

Functional Test of 480 and 120 Volt Molded Case Circuit

Breakers

16A

71111.12

Work Orders

WO 2580, 14-385283-000, 14-385283-001, 15-406874-000,

18-439151-000, 18-445075-000, 19-452140-026,

20-458342-000, 20-460120-000, 20-460914-000,

2-480055-000, 22-477183-000, 22-477957-001,

23-486740-000, 23-486740-001, 23-488067-000

71111.13

Corrective Action

Documents

Condition Reports

10029736, 10030624, 10030630, 10030631, 10030667,

10030732, 10030733, 10030734, 10030736, 10030739,

10031127

71111.13

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10029882

71111.13

Drawings

M-12AB01

Piping and Instrumentation Diagram Main Steam System

71111.13

Drawings

M-12AL01

Piping and Instrumentation Diagram Auxiliary Feedwater

System

71111.13

Drawings

M-12BG03

Piping and Instrumentation Diagram Chemical and Volume

Control System

71111.13

Drawings

M-12EM01

Piping and Instrumentation Diagram High Pressure Coolant

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Injection System

71111.13

Drawings

M-12FC02

Piping and Instrumentation Diagram Auxiliary Turbines

Auxiliary Feedwater Pump Turbine

71111.13

Drawings

M-12KA05

Piping and Instrumentation Diagram Compressed Air

System

71111.13

Miscellaneous

E-1F9910

Post-Fire Safe Shutdown Area Analysis

71111.13

Procedures

AI 16C-006

Troubleshooting

2A

71111.13

Procedures

AI 22C-013

Protected Equipment Program

71111.13

Procedures

AI 22C-014

TSEO Management

7A

71111.13

Procedures

AP 22C-003

On-Line Nuclear Safety and Generation Risk Assessment

71111.13

Procedures

EMG ES-12

Transfer to Cold Leg Recirculation

71111.13

Procedures

OFN RP-017

Control Room Evacuation

71111.13

Procedures

STS KA-010

N2 Accumulator Inservice Check Valve Test

71111.13

Procedures

SYS EM-003

Operation of EM HV-8924

71111.13

Procedures

SYS KJ-200

Inoperable Emergency Diesel

71111.13

Procedures

SYS NB-202

Transferring NB02 Power Sources

71111.13

Work Orders

WO 50424, 50426, 50948

71111.15

Calculations

AN-05-016

Wolf Creek MSLB Containment Pressure and Temperature

Response Analyses with GOTHIC for the MSIV/MFIV

Replacement Project

71111.15

Calculations

SA-91-016

ECCS Design Basis Injection Flowrates Re-analysis in

Supporting of the WCGS Power Re-Rate Project

71111.15

Calculations

XX-M-069

FAC Program Minimum Wall Thickness Calculation for

Large Bore Piping and Components

71111.15

Corrective Action

Documents

Condition Reports

99-3942, 10019400, 10021613, 10028389, 10028779,

10029850, 10030351

71111.15

Drawings

M-12BG03

Piping and Instrumentation Diagram Chemical and Volume

71111.15

Drawings

M-12EM01

Piping and Instrumentation Diagram High Pressure Coolant

Injection System

71111.15

Drawings

M-622.1A-00001

SGK05A and SGK05B Air Conditioner Refrigeration

Schematic

W13

71111.15

Engineering

Changes

DCP 09488

Governor Replacement of Emergency Diesel Generators

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Miscellaneous

M-018B-00009

Woodward Governor Failure Analysis and Test Report

Review

W01

71111.15

Miscellaneous

M-10AE

Feedwater System

71111.15

Miscellaneous

MS-02

Pipe Class Sheets

71111.15

Procedures

AP 26C-004

Operability Determinations and Functionality Assessments

71111.15

Procedures

DB-EMG E-0

Reactor Trip or Safety Injection

71111.15

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.15

Procedures

EMG E-2

Faulted Steam Generator Isolation

24A

71111.15

Procedures

EMG E-3

Steam Generator Tube Rupture

71111.15

Procedures

EMG ES-12

Transfer to Cold Leg Recirculation

71111.15

Procedures

MPE GK-004

GK Unit Preparation for Work

71111.15

Procedures

STS KJ-005B

Manual/Auto Start, Sync and Loading of EDG NE02

71111.15

Procedures

SYS EM-003

Operation of EM HV-8924

71111.15

Work Orders

WO 285, 33185, 48154, 22-482755-000

71111.18

Calculations

BN-20

RWST Volumes and Level Set Points

71111.18

Calculations

BN-M-013

Time Available for Injection, ECCS, and Containment Spray

Pumps Transfer and Evaluation of Air Entrainment at Empty

Alarm

71111.18

Calculations

EJ-30

RHR Pumps A and B NPSH

71111.18

Calculations

EN-33

Containment Spray Pump NPSH

71111.18

Calculations

FL-18

Containment Flood Levels for LOCA and MSLB

71111.18

Calculations

WES-009-CALC-

001

Wolf Creek/Callaway Post-LOCA Containment Water Level

Calculation

71111.18

Corrective Action

Documents

Condition Reports

21822, 137915, 142204, 10014808, 10015112, 10015262,

10017090, 10017620, 10019464, 10019626, 10030624,

10030630, 10030361, 10030650, 10030662, 10030663,

10030664,

71111.18

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10029963

71111.18

Engineering

Changes

DECP 020631

System Descriptions M-10BN and M-10EN Update

71111.18

Engineering

DRE 20456

AV1 Positioner Gauge Block Removal

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Changes

71111.18

Miscellaneous

DB-EMG ES-12

Transfer to Cold Leg Recirculation

71111.18

Miscellaneous

SQTS-01-GSQTP

Seismic Functional Procedure

71111.18

Procedures

ALR 00-047C

RWST LOLO2

71111.18

Procedures

AP 05-021

Direct Replacement Equivalency

6A

71111.18

Procedures

AP 26C-004

Operability Determination and Functionality Assessments

71111.18

Procedures

DB-EMG ES-03

SI Termination

71111.18

Procedures

EGM ES-03

SI Termination

71111.18

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.18

Procedures

EMG ES-12

Transfer to Cold Leg Recirculation

71111.20

Corrective Action

Documents

Condition Report

10030086, 10030789, 10031067

71111.20

Miscellaneous

Interoffice

Correspondence

Refuel 26 Risk Assessment Team Report - Schedule Rev.

C 1/12/2024

2/22/2024

71111.20

Procedures

AP 22B-001

Outage Risk Management

71111.20

Procedures

GEN 00-006

Hot Standby to Cold Shutdown

106

71111.20

Procedures

STS BB-011

Reactor Coolant System and Pressurizer Heatup/Cooldown

Surveillance

71111.20

Procedures

STS IC-901

Channel Operational Test Reactor Coolant Cold

Overpressure Protection Instrumentation

23A

71111.20

Procedures

SYS NB-202

Transferring NB02 Power Sources

71111.20

Work Orders

WO 53004, 20-466498-000, 21-474062-000, 23-487901-000

71111.24

Calculations

XX-M-080

Wolf Creek Generating Station Pump Room Heat-Up

Analysis

71111.24

Corrective Action

Documents

Condition Reports

20559, 10001214, 10004589, 10005013, 10007337,

10019205, 10024045, 10024821, 10028295, 10028635,

10028649, 10029512, 10029662, 10029726, 10029748,

10030191, 10030273, 10030274, 10030624, 10030630,

10030361

71111.24

Corrective Action

Documents

Resulting from

Inspection

Condition Reports

10029354, 10029485, 10029495, 100300455, 10031001,

10031492, 10031493

71111.24

Drawings

E-13EF09A

Schematic Diagram ESW To/From Containment Air Coolers

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Isolation Valve

71111.24

Drawings

E-13NN01

Class 1E Instrument AC Schematic

71111.24

Drawings

M-12AB01

Piping and Instrumentation Diagram Main Steam System

71111.24

Drawings

M-12AL01

Piping and Instrumentation Diagram Auxiliary Feedwater

System

71111.24

Drawings

M-12EF01

Piping and Instrumentation Diagram Essential SVC Water

System

71111.24

Drawings

M-12EF02

Piping and Instrumentation Diagram Essential Service Water

System

71111.24

Drawings

M-12KA05

Piping and Instrumentation Diagram Compressed Air

System

71111.24

Miscellaneous

E-1F9915

Design Basis Document for OFN RP-017, Control Room

Evacuation

71111.24

Miscellaneous

WCRE-34

Fourth 10-Year Interval Inservice Testing Bases Document

71111.24

Procedures

AP 10-100

Fire Protection Program

71111.24

Procedures

AP 16E-002

Post Maintenance Testing Development

21B

71111.24

Procedures

AP 26C-004

Operability Determination and Functionality Assessments

71111.24

Procedures

AP 26C-004

Operability Determination and Functionality Assessments

26C

71111.24

Procedures

AP 29B-002

ASME Code Testing of Pumps and Valves

2A

71111.24

Procedures

AP 29B-003

Surveillance Testing

71111.24

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.24

Procedures

EMG E-2

Faulted Steam

24A

71111.24

Procedures

EMG E-3

Steam Generator Tube Rupture

71111.24

Procedures

MPE 766Q-008

Cleaning and Inspection of Class 1E Inverters

71111.24

Procedures

MPE RC-001

Room Cooler Maintenance

71111.24

Procedures

OFN RP-017

Control Room Evacuation

71111.24

Procedures

STN AL-201

Auxiliary Feedwater System Valve Test

71111.24

Procedures

STN RP-001E

ESW to SW SYS VLV ISO Switch

3A

71111.24

Procedures

STN RP-001F

ESW to UHS VLV ISO Switch

2A

71111.24

Procedures

STN RP-002G

ESW TRN B to CTMT Air Coolers ISO Switch

71111.24

Procedures

STN RP-002H

ESW TRN B to CCW HX B ISO Switch

71111.24

Procedures

STN RP-011E

ESW to SW SYS VLV ISO Switch 10 YR

71111.24

Procedures

STN RP-011F

ESW to UHS VLV ISO Switch 10 YR

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.24

Procedures

STN RP-012H

ESW To/From CCW HX B ISO Switches 10 year

71111.24

Procedures

STN TCA-001

Manual Time Critical Action Timing

71111.24

Procedures

STS AB-201D

Atmospheric Relief Valve Inservice Valve Test

71111.24

Procedures

STS AL-103

TDAFW Pump Inservice Pump Test

71111.24

Procedures

STS AL-201C

Turbine Driven Auxiliary Feedwater System Inservice Valve

Test

71111.24

Procedures

STS EF-100B

ESW System Inservice B and ESW Check Valve B Test

51A

71111.24

Procedures

STS GN-001

CTMT Cooling Fan Operability Test

71111.24

Procedures

STS IC-746

Reactor Trip and Bypass Breaker Response Time Testing

2C

71111.24

Procedures

STS KA-010

N2 Accumulator Inservice Check Valve Test

71111.24

Procedures

STS PE-007

Periodic Verification of Motor Operated Valves

5A

71111.24

Procedures

SYS KJ-124

Post Maintenance Run of Emergency Diesel Generator B

71111.24

Procedures

SYS NN-131

Energizing NN Buses

71111.24

Procedures

SYS NN-200A

Transferring NN01 and NN03 Buses Between Power

Sources

71111.24

Work Orders

WO 15194, 15202, 15925, 16321, 16774, 16776, 16778, 16790,

16794, 16800, 16880, 16886, 17423, 17435, 17442, 17549,

17553, 26620, 27203, 29104, 30569, 32367, 32797, 32392,

38854, 44708, 45373, 50424, 50426, 50431, 17-430071-

003, 18-444963-000, 18-444964-000, 18-445168-000,

18-445169-000, 19-448878-000, 19-488879-000,

19-448880-000, 19-448882-000, 22-480055-000,

23-146046-000, 23-485690-000, 23-486898-000,

23-486898-001, 23-489131-005

71152A

Corrective Action

Documents

Condition Reports

14364, 45434, 50217, 1996-0015, 1995-3074, 10029354,

10004991, 10004995, 10005013, 10017445

71152A

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10030907

71152A

Drawings

M-766-01043

W05

71152A

Drawings

M-766-01045

W04

71152A

Miscellaneous

EPR NS30650022

06/05/2009

71152A

Miscellaneous

WCQPM

Wolf Creek Quality Program Manual

13, 14

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71152A

Procedures

AP 24-002

Requisition and Procurement Process

30E

71152A

Procedures

AP 24D-003

Receipt Inspection

71152A

Procedures

OFN RP-013

Control Room Not Habitable

71152A

Procedures

OFN RP-017

Control Room Evacuation

71152A

Procedures

STN RP 002D

BIT Inlet VLV B ISO Switch

71152A

Procedures

STN RP-001C

VCT Outlet Isolation VLV ISO Switch

71152A

Procedures

STN RP-001D

CCP B Suct from RWST VLV ISO Switch

2B

71152A

Procedures

STN RP-001N

SGL15B Control RM ISO Switch

71152A

Procedures

STN RP-002C

RWST to RHR B Suction ISO Switch

71152A

Procedures

STN RP-002F

CCP B Recirc VLV ISO Switch

71152A

Procedures

STN RP-002I

CCW TRN B SPLY/Return VLV ISO Switch

71152A

Procedures

STN RP-011C

VCT Outlet Isolation VLV ISO Switch 10 YR

71152A

Procedures

STN RP-011D

CCP B Suct from RWST VLV ISO Switch 10 YR

71152A

Procedures

STN RP-011N

SGL15B Control RM ISO Switch 10 YR

71152A

Procedures

STN RP-012C

RWST to RHR Pump B Suction ISO Switch 10 YR

71152A

Procedures

STN RP-012D

BIT Inlet VLV B ISO Switch 10 YR

71152A

Procedures

STN RP-012F

CCP B Recirc VLV ISO Switch 10 YR

71152A

Procedures

STN RP-012I

CCW TRN B SPLY/Return VLV ISO Switch 10 YR

71152A

Procedures

STS IC-211B

Actuation Logic Test Train B Solid Sate Protection System

38A

71152A

Procedures

STS IC-215

TADOT of Manual Reactor Trip, Trip and Bypass Breaker

UV/Shunt Trip, Turbine Trip on Reactor Trip and P4

71152A

Procedures

STS IC-610B

Slave Relay Test K610 Train B Safety Injection

71152A

Work Orders

WO

13-378440-000, 15-406873-002, 21-469167-000,

21-472626-000, 21-474139-000, 22-483407-000,

2-477183-000