MONTHYEARIR 05000482/20254012025-01-22022 January 2025 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000482/2025401 ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information ML24060A1192024-02-29029 February 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000277/20230062024-02-28028 February 2024 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2023006 and 05000278/2023006) IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24018A1382024-01-18018 January 2024 Inservice Inspection Request for Information IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) IR 05000482/20230052023-08-23023 August 2023 Updated Inspection Plan for Wolf Creek Nuclear Operating Corporation, Unit 1 (Report 05000482/2023005) - Mid-Cycle Letter 2023 IR 05000277/20220062023-03-0101 March 2023 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2022006 and 05000278/2022006) IR 05000482/20220062023-03-0101 March 2023 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2022006) ML23019A0752023-01-19019 January 2023 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000277/2023011 and 05000278/2023011 ML22321A2662022-11-16016 November 2022 January 2023 Emergency Preparedness Program Inspection - Request for Information IR 05000277/20220052022-08-31031 August 2022 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2022005 and 05000278/2022005) IR 05000482/20220052022-08-23023 August 2022 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2022005) ML22215A2742022-08-0202 August 2022 Inservice Inspection Request for Information ML22249A2552022-06-29029 June 2022 Request for Information for an NRC Post-Approval Site Inspection for License Renewal 05000482/2022012 ML22130A7662022-05-10010 May 2022 Notification of Inspection (NRC Inspection Report 05000482/2022003) and Request for Information ML22123A2702022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 IR 05000482/20224012022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 IR 05000277/20210062022-03-0202 March 2022 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2021006 and 05000278/2021006) IR 05000482/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000482/2021006) ML22025A3612022-01-21021 January 2022 PI&R RFI Final ML22019A0932022-01-19019 January 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000482/2022002) and Request for Information ML21322A2952021-11-19019 November 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000482/2022001 and Request for Information ML21237A5212021-09-0101 September 2021 Wc Mid-Cycle Inspection Plan Transmittal Letter 2021 IR 05000277/20210052021-09-0101 September 2021 Updated Inspection Plan for the Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2021005 and 05000278/2021005) ML21132A1032021-05-12012 May 2021 Document Request List, Paperwork Reduction Act Statement ML21123A0412021-05-0505 May 2021 Notification of NRC Design Bases Assurance Inspection (Teams) (05000482/2021010) and Initial Request for Information IR 05000482/20190062021-03-0303 March 2021 Annual Assessment Letter (Report 05000482/2019006) IR 05000277/20200062021-03-0303 March 2021 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2020006 and 05000278/2020006) ML21061A3412021-02-25025 February 2021 Request for Information: Wolf Creek Nuclear Station, Dated February 11, 2021, Inspection Report 05000482/2021002 Occupational Radiation Safety Inspection-1, 2, PI ML21091A1782021-02-0202 February 2021 Ti 2515/194 Inspection Documentation Request ML21026A1982021-01-26026 January 2021 Inservice Inspection Request for Information ML20296A3342020-10-21021 October 2020 ISI Remote Inspection - Supplemental Request for Information IR 05000277/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Reports 05000277/2020005 and 05000278/2020005) ML20119A8852020-04-28028 April 2020 Long-Term Steam Dryer Inspection Plan at EPU Conditions ML20104C1472020-04-13013 April 2020 Notification of Inspection (NRC Inspection Report 05000482/2020003) and Request for Information ML20099G9422020-04-0808 April 2020 Notification of NRC Biennial Problem Identification and Resolution Inspection (05000482/2020010) and Initial Request for Information IR 05000277/20190062020-03-0303 March 2020 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2019006 and 05000278/2019006) ML20055E1132020-03-0303 March 2020 WC2019006 Annual Assessment Letter ML20024D7072020-01-24024 January 2020 Notification of NRC Design Bases Assurance Inspection (Programs) (05000482/2020011) and Initial Request for Information IR 05000482/20190052019-08-30030 August 2019 Updated Inspection Plan for Wolf Creek Generating Station, Report 05000482/2019005 IR 05000277/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000277/2019005 and 05000278/2019005) ML19158A0782019-06-0505 June 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2019003) and Request for Information ML19119A1202019-04-29029 April 2019 Long-Term Steam Dryer Inspection Plan at EPU Conditions IR 05000482/20180062019-03-0404 March 2019 Annual Assessment Letter for Wolf Creek Report 05000482/2018006) 2025-01-22
[Table view] Category:Letter
MONTHYEARML25031A0592025-01-31031 January 2025 Annual Commitment Revision Report for the Period 01/01/24 Through 12/31/24 IR 05000482/20243012025-01-30030 January 2025 Notification of NRC Initial Operator Licensing Examination 05000482/2024301 ML25023A0442025-01-24024 January 2025 Acknowledgement of Response to U.S. Nuclear Regulatory Commission Inspection Report 05000482/2024003 and Disputed Non Cited Violation ML25024A1482025-01-24024 January 2025 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 IR 05000482/20254012025-01-22022 January 2025 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000482/2025401 RS-25-001, Subsequent License Renewal Environmental Review, Response to NRC Requests for Confirmation of Information (Rcis) and Request for Additional Information (RAI)2025-01-21021 January 2025 Subsequent License Renewal Environmental Review, Response to NRC Requests for Confirmation of Information (Rcis) and Request for Additional Information (RAI) ML24353A1372025-01-15015 January 2025 Proprietary Determination Constellation Energy Generation, LLC 2024 Deferred Premiums ML25010A3692025-01-14014 January 2025 Regulatory Audit in Support of Review of License Amendment and Exemption Requests for Risk-Informed Resolution to GSI-191 ML25013A0642025-01-13013 January 2025 Requalification Program Inspection ML25010A1502025-01-10010 January 2025 Notification of Commercial Grade Dedication Inspection (05000277/2025011 and 05000278/2025011) and Request for Information IR 05000171/20230012025-01-0707 January 2025 Constellation Energy Generation, LLC, Peach Bottom Atomic Power Station Unit 1 - NRC Inspection Report No. 05000171/2023001 ML25006A0942025-01-0606 January 2025 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24366A1612024-12-31031 December 2024 Operating Corporations (Wcnocs) Contest Response to Non-Cited Violation 2024003-01 - NRC Inspection Report 05000482/2024003 ML24324A3312024-12-23023 December 2024 Exemption from the Requirements of 10 CFR Part 50, Sections 50.82(a)(8)(1)(A) and 50.75(h)(1)(iv) (EPID L-2024-LLE-0018) (Ltr) ML24344A2742024-12-19019 December 2024 Alternative Request to Use American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case OMN-32 ML24339B7292024-12-18018 December 2024 Amd - Constellation - Adoption of TSTF-591 IR 05000482/20240142024-12-17017 December 2024 Comprehensive Engineering Team Inspection Report 05000482/2024014 ML24352A4382024-12-17017 December 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-505-A, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Commissioners ML24352A0322024-12-17017 December 2024 Notification of Post Approval Site Inspection for License Renewal and Request for Information ML24317A2472024-12-16016 December 2024 Environmental Assessment and Finding of No Significant Impact Related to Exemption from the Requirements of 10 CFR Part 50 (Letter) ML24344A1102024-12-13013 December 2024 Suppl Env Audit Summary Letter ML24347A0122024-12-12012 December 2024 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) 05000482/LER-2024-002-01, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-12-11011 December 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve IR 05000482/20244022024-12-0505 December 2024 Security Baseline Inspection Report 05000482/2024402 ML24337A0132024-12-0202 December 2024 Cycle 27 Core Operating Limits Report, Revision 1 ML24337A1232024-12-0202 December 2024 License Amendment Request to Modify the Implementation Date of License Amendment No. 239 ML24332A1262024-11-27027 November 2024 Notice of Intent to Contest Non-Cited Violation (NCV) 05000482/2024003-01, and Request for Additional Time to Provide Wolf Creek Nuclear Operating Corporation’S (WCNOC) NCV Response ML24331A2592024-11-27027 November 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML24331A2792024-11-26026 November 2024 Supplement to Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition - Revise LaSalle, Units 1 and 2 Technical Specificati ML24327A1642024-11-22022 November 2024 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Peach Bottom SLR and Concurrence with Not Likely to Adversely Affect Finding for Northern long-eared and Tricolored Bats ML24327A1652024-11-22022 November 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Peach Bottom SLR ML24319A0752024-11-14014 November 2024 Additional Information Report for the Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Environmental Review ML24313A1012024-11-13013 November 2024 SLRA Supplemental Environmental Audit Plan ML24310A2832024-11-0404 November 2024 Issuance of the Core Operating Limits Report for Reload 25, Cycle 26 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 IR 05000482/20240032024-11-0101 November 2024 Integrated Inspection Report 05000482/2024003 ML24306A2192024-11-0101 November 2024 Results of the Steam Generator Tube Inservice Inspection During the 26th Refueling Outage to Reflect TSTF-577 Reporting Requirements ML24295A3792024-11-0101 November 2024 Integrated Inspection Report 05000482/2024003 IR 05000482/20244202024-10-31031 October 2024 Security Baseline Inspection Report 05000482/2024420 05000482/LER-2024-001-01, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-10-22022 October 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing ML24296B1902024-10-22022 October 2024 10 CFR 50.55a Requests for the Fifth Ten-Year Interval Inservice Testing Program 05000482/LER-2024-002, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-10-21021 October 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve IR 05000277/20244012024-10-17017 October 2024 Security Baseline Inspection Report 05000277/2024401 and 05000278/2024401 (Cover Letter Only) RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information ML24281A1012024-10-0707 October 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing 2025-01-07
[Table view] |
Text
August 14, 2024
SUBJECT:
UPDATED INSPECTION PLAN FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2024005)
Dear Cleve Reasoner:
The enclosed inspection plan lists the inspections scheduled through June 30, 2026, for Wolf Creek Generating Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
The NRC has completed the onsite portion of Inspection Procedure 92702, Follow-Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, and Orders, during the third quarter of 2024. This inspection was associated with Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-008 (ML19092A335). The results of this inspection will be communicated in the NRC Integrated Inspection Report 05000482/2024003. The NRC will conduct Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal, scheduled for January 2025.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system ADAMS, which is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact David Proulx at (817) 200-1561 with any questions you have regarding this letter.
Sincerely, Gregory E. Werner, Chief Projects Branch B Division of Operating Reactor Safety Docket Nos. 05000482; 07200079 License No. NPF-42 Enclosure:
Inspection Plan cc w/ encl: Distribution via LISTSERV Signed by Werner, Gregory on 08/14/24
ML24227B004 SUNSI Review By: PON ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive Keyword:
NRC-002 OFFICE SPE: DORS/B BC: DORS/B NAME DProulx GWerner SIGNATURE
/RA/
/RA/
DATE 08/01/2024 08/14/2024
Site Inspection Activity Plan Wolf Creek 07/01/2024 - 06/30/2026 Unit Start End Activity CAC Title Staff Count WC IP 92702, Follow-up on Traditional Enforcement Actions - Confirmatory Order
1 7/15/2024 7/26/2024 IP 92702 CONF 001697 Enforcement Related Order Follow-Up-Only RP 5,8
1 7/22/2024 7/26/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
7/22/2024 7/26/2024 IP 71124.05 000729 Radiation Monitoring Instrumentation
7/22/2024 7/26/2024 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation WC 2024 PI&R Inspection
1 7/22/2024 7/26/2024 IP 71152B 000747 Problem Identification and Resolution EP Program & PI Inspection (2024) - WC
1 8/5/2024 8/9/2024 IP 71114.02 000717 Alert and Notification System Testing
8/5/2024 8/9/2024 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System
8/5/2024 8/9/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
8/5/2024 8/9/2024 IP 71114.05 000720 Maintenance of Emergency Preparedness
8/5/2024 8/9/2024 IP 71151 001397 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - WC
1 8/26/2024 8/30/2024 IP 71130.03 000735 Contingency Response - Force-On-Force Testing
9/16/2024 9/20/2024 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Comprehensive Engineering Team Inspection - Wolf Creek
1 10/21/2024 10/25/2024 IP 71111.21M 000713 Comprehensive Engineering Team Inspection
11/4/2024 11/8/2024 IP 71111.21M 000713 Comprehensive Engineering Team Inspection Security Access Control (.02), Security Plan Changes (.09), Security PIV (71151)
1 11/18/2024 11/22/2024 IP 71130.02 000734 Access Control
11/18/2024 11/22/2024 IP 71130.09 001656 Security Plan Changes
11/18/2024 11/22/2024 IP 71151 001338 Performance Indicator Verification License Renewal 71003 - WC (Phase 2)
1 1/20/2025 1/24/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal
2/3/2025 2/7/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal MC&A - WC
1 2/24/2025 2/28/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)
Commercial Grade Dedication Inspection - Wolf Creek
1 3/24/2025 3/28/2025 IP 71111.21N.03 001808 Commercial Grade Dedication
4/7/2025 4/11/2025 IP 71111.21N.03 001808 Commercial Grade Dedication Prepared on 8/13/2024 1:48:31 PM 1 of 3
Site Inspection Activity Plan Security Access Control (71130.02), Security Plan Changes (71130.09), Security PIV (71151)
1 3/31/2025 4/4/2025 IP 71130.02 000734 Access Control
3/31/2025 4/4/2025 IP 71130.09 001656 Security Plan Changes
3/31/2025 4/4/2025 IP 71151 001338 Performance Indicator Verification Cyber Security Inspection - WC
1 5/12/2025 5/16/2025 IP 71130.10 000741 Cybersecurity EP 2025 Biennial Exercise & PI Inspection - WC
1 6/2/2025 6/6/2025 IP 71114.01 000716 Exercise Evaluation
6/2/2025 6/6/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
6/2/2025 6/6/2025 IP 71151 001397 Performance Indicator Verification Security Protective Strategy (71130.05) and Target Sets (71130.14)
1 6/23/2025 6/27/2025 IP 71130.05 000737 Protective Strategy Evaluation
6/23/2025 6/27/2025 IP 71130.14 000743 Review of Power Reactor Target Sets WC 2025 INITIAL EXAM
1 7/6/2025 7/12/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
8/17/2025 8/23/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
Inservice Inspection-WC
1 10/6/2025 10/17/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 1,4,PI - WC
1 10/13/2025 10/17/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
10/13/2025 10/17/2025 IP 71124.04 000728 Occupational Dose Assessment
10/13/2025 10/17/2025 IP 71151 000746 Performance Indicator Verification Age-Related Degradation Inspection - Wolf Creek
1 3/30/2026 4/3/2026 IP 71111.21N.04 001832 Age-Related Degradation
4/13/2026 4/17/2026 IP 71111.21N.04 001832 Age-Related Degradation RP 1,4,PI - WC
1 4/13/2026 4/17/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
4/13/2026 4/17/2026 IP 71124.04 000728 Occupational Dose Assessment
4/13/2026 4/17/2026 IP 71151 000746 Performance Indicator Verification RP 5,6,7,8 - WC
1 6/8/2026 6/12/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation
6/8/2026 6/12/2026 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment
6/8/2026 6/12/2026 IP 71124.07 000731 Radiological Environmental Monitoring Program
6/8/2026 6/12/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation WC 2026 BRQ
Prepared on 8/13/2024 1:48:31 PM 2 of 3
Site Inspection Activity Plan
6/21/2026 6/27/2026 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance License Renewal-WC 71003 (Phase 3)
1 6/22/2026 6/26/2026 IP 71003 000687 Post-Approval Site Inspection for License Renewal Prepared on 8/13/2024 1:48:31 PM 3 of 3