ML18004A590: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(3 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 10/10/1986 | | issue date = 10/10/1986 | ||
| title = Package of 29 Postcards Urging NRC to Deny Util Request for Exemption from 10CFR50,App E Requirement Re Full Participation Exercise of Emergency Response Plan Prior to Commercial Operation of Plant | | title = Package of 29 Postcards Urging NRC to Deny Util Request for Exemption from 10CFR50,App E Requirement Re Full Participation Exercise of Emergency Response Plan Prior to Commercial Operation of Plant | ||
| author name = | | author name = Bullock N, Caison W, Cake E, Cashwell P, Courbois C, Davis L, Fuller F, Greenberg G, Greenberg S, Halford M, Halford R, Hobbs A, Jessup J, Kardon R, Palton K, Pettee C, Tuller D, Wall L, Wilson D, Wilson R, Wissner J | ||
| author affiliation = AFFILIATION NOT ASSIGNED | | author affiliation = AFFILIATION NOT ASSIGNED | ||
| addressee name = | | addressee name = Denton H | ||
| addressee affiliation = NRC OFFICE OF NUCLEAR REACTOR REGULATION (NRR) | | addressee affiliation = NRC OFFICE OF NUCLEAR REACTOR REGULATION (NRR) | ||
| docket = 05000400 | | docket = 05000400 | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:RECUI+ORY INFORNATION DIBTRIBUTy<N BYBTEN (RIDE>ACCESBIObl NBR: 8610170251 DOC.DATE: 86/10/10 NOTARIZED: | {{#Wiki_filter:RECUI+ORY INFORNATION DIBTRIBUTy<N BYBTEN (RIDE> | ||
NO DOCKET FACIL: 50-400 Shearon Harris Nuclear Power Planti Unit i.Carolina 05000400 AUTH.NANE AUTHOR AFFILIATION DAVIS>L.AFfiliation Not Assigned MALL>L, B.AFFiliation Not Assigned QREENl3ERQ> | ACCESBIObl NBR: 8610170251 DOC. DATE: 86/10/10 NOTARIZED: NO DOCKET FACIL: 50-400 Shearon Harris Nuclear Power Planti Unit i. Carolina 05000400 AUTH. NANE AUTHOR AFFILIATION DAVIS> L. AFfiliation Not Assigned MALL> L, B. AFFiliation Not Assigned QREENl3ERQ> S. K. Affiliation Not Assigned RECIP. NANE RECIPIENT AFFlLIATIGN DENTON) H. R Office of Nuclear Reactor Regulation~ Director (post 851125 | ||
S.K.Affiliation Not Assigned RECIP.NANE RECIPIENT AFFlLIATIGN DENTON)H.R Office of Nuclear Reactor Regulation~ | |||
Director (post 851125 | |||
==SUBJECT:== | ==SUBJECT:== | ||
Package of 29 postcards urging NRC to deny util request for exemption from 10CFR50i App E requirement re full participation exercise of emergency response plan prior to commerc ial operation of p lant.DIBTRIDUTION CODE: YEOBD COP IEB RECEIVED: LTR cDBENCL 0 BI ZE: | Package of 29 postcards urging NRC to deny util request for exemption from 10CFR50i App E requirement re full participation exercise of emergency response plan prior to commerc ial operation of p lant. | ||
DIBTRIDUTION CODE: YEOBD TITLE: Request For NRR COP IEB RECEIVED: LTR cDBENCL Action (e. | |||
0 BI ZE: | |||
: g. 2. 206 Petitions) 8c Related Correspondenc NOTES: Application for permit renewal Filed. 05000<00 RECIPIENT COP IEB RECIPIENT COPIES ID CODE/NANE LTTR ENCL ID CODE/NAME LTTR ENCL PMR-A PD2 LA PWR-A PD2 PD gUCKLEYp 8 01 INTERNAL: EDO/ACB ELD/HDB1 E ED NRR DIR R | |||
EXTERNAL: LPDR 03 NRC PDR 02 NBIC 05 | |||
I>> | |||
==Dear Mr.'5?Eton:== | ==Dear Mr.'5?Eton:== | ||
II I wish to urge denial of CPSL's r'egest for exemption from the requirement, unlit 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.-Sincerely, p,o))w, Qg Q h'~.8610i7025i Ghi010;<<,PDR | II I wish to urge denial of CPSL's r'egest for exemption from the requirement, unlit 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | ||
,."H.,",.PDA' J A~l>.l l.gP~' | Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | ||
C | -Sincerely, p,o) | ||
)w, Qg Q h | |||
'~.8610i7025i Ghi010 ADOCK;08000400 | |||
; <<,PDR | |||
,."H., ", . PDA' | |||
J A~ | |||
l | |||
>.l l. | |||
gP | |||
~' | |||
C | |||
==Dear Mr.=Denton:== | ==Dear Mr.=Denton:== | ||
I wish to urge denial of CPSL's r&guest for exemption from the requirement, under$.0 CFR 50 Appendix E, that the Company conduct 6 full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before'the plant is permitted to operate at all.Sincerely,~p | I wish to urge denial of CPSL's r&guest for exemption from the requirement, under $ .0 CFR 50 Appendix E, that the Company conduct 6 full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | ||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before'the plant is permitted to operate at all. | |||
Sincerely, | |||
~ ~ | |||
p | |||
Mrs. Lainbert Daiis | |||
'- ~ | |||
a PM 0 | |||
70I Greenwood Road | |||
~> Chapel ~Hill; NC~ 27514~= | |||
)9 )cT 1 | |||
f986 Mr. Harold Denton, Director Office=-of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear" Mr .. Denton:== | |||
I wish to urge denial of CPEL's request for exemption from the reguirement, under ~0 CFR 50, Appendix E, that the~oanpany conduct a ~full Participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
.1986 Mr. Harold Denton, Director Office-'o'f Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555 | |||
==Dear | ==Dear Hr. Denton:== | ||
I wish to urge denial of CPS,L's gdguest for exemption from the requirement, urger 10 CFR 50, Appendix E, that the Company conducb"a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
I wish to urge denial of CPS,L's gdguest for exemption from the requirement, urger 10 CFR 50, Appendix E, that the Company conducb"a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.Sincerely, | -Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | ||
Sincerely, | |||
"'-:c" >Bi a'j~i~ | |||
R /t/88K C , spis, f8 77Fo<A/coo 8@i. | |||
C~pM e]~c. si r)'+ | |||
=V Mr.:Harold Denton, Director Offi'ce'of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear Mr.Denton:== | p% | ||
4 | |||
Mr.Harold Denton, Directorg-'ffice | |||
==Dear Mr. Denton:== | |||
I wish to urge denial of CPS,L's request for exemption from the requirement, undJg 10 CFR 50, Appendix E, that the Company conduct-a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerel | |||
USA . | |||
: 14-i'-I Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Nashington, DC 20555 | |||
==Dear Mr. Denton:== | |||
I wish to urge denial of CPS,L's j p requ'eA for exemption from the requirement, under"10 CPR 50, Appendix E, that the Company. conduct a full participation exercise'f the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely,. | |||
Mr. Harold Denton, of Nuclear Reaction Regulatiop Directorg-'ffice Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear Mr.,== | ==Dear Mr.,== | ||
Denton: | Denton: ~ | ||
: j. vjyh to urge denial of CPSLP's request for | |||
~I., Mr.Harold Benton, Director ('ffice of Nuclear | ,exemption from the requirement, under 10 CPR 50, | ||
: Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear pover plant | |||
~ within one year before beginning commercial operation of the plant or before operating at greater than f've percent of rated pover. | |||
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
~ I., | |||
Mr. Harold Benton, Director of Nuclear React'ion Regulatiop ('ffice Nuclear Regulatory Commission Hashington, DC 20555 | |||
==Dear Hr. Denton:== | |||
I wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, E believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
X | |||
~~ oct USA I98 M~~Harold Denton, Director Of'&ice. of Nuclear Reaction Regulatio Nuclear Regulatory Commission Washington, DC 20555 | |||
r4 J'pa g ~ ~ * &<1 a | |||
==Dear Hr. Denton:== | |||
I wish to urge denial of CPS,L's request for exemption from the requirement,--under 10 CFR 50; Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
4 | |||
==Dear. Mr. Denton:== | |||
wish to urge denial of CPS,L's request for exemption from the requirement, undeg 10 CFR 50, Appendix E, tha t thd company conduc t' full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.. | |||
g~~ ~~g I | |||
Sincerely, | |||
Q8e ~mc Paauqpig '~ | |||
PNI | |||
/0 ~A'A OCT'986 Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear. Mr. Denton:== | |||
E wish to urge denial of CPS,L's request for exemption from the requirement, undegz)0 CFR 50, Appendix E, that the Company conduct'Q full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at al Sincerely, | |||
Cev~~4 | |||
+J +. Ca~mn 4~< | |||
Qqpgpg Qg// ~, | |||
z~j'Q I0 ocT Iree | |||
-~sr ~rg(~end Mr. Harold Denton, .D'irector Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear Mr". Denton:== | |||
I wish to urge denial of CPS,L's request for exemption from the requirement, der 10 CFR 50, Appendix E, that the Company conduct~a=full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, 1 believe this exercise should be conducted before the plant is peg itted to operate at all. | |||
Sincerely, | |||
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear Mr. Denton:== | |||
- I wish to urge denial of CPSL's request for exemption from the requirement, ufi'der" 10 CFR 50, | |||
,Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Since e | |||
C. | |||
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear | ==Dear Mr. Dent;,== | ||
I wish to urge denial of | on: | ||
I wish to urge denial of CPSL's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response | |||
.Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
Mr. Harold Denton, Director Office of Nuclear Reaction Regulation Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear. | ==Dear Hr. Den7on:== | ||
I wish to urge denial of CPS,L's request'tz for exemption from the requirement, under )0 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
cP. PL- (m ge8 ~~ir e~w>q-t 6- g~ < (PM. + | |||
K 0) | |||
Qy~ g'.C g.95 cO IO OCT 1986 C | |||
Mr. Harold Denton,."Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
4kcaas Dqyr Mr; Denton: | |||
~ <<<<I <<4 I'ish to urge denial op CPS,L's request for exemption from the requ'irement, under&0 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
G~ ig m<PMg<~ | |||
0) | |||
IO OCT 1986 rises ~~ | |||
Mr. Harold Denton~,~Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
0, C | |||
==Dear Mr."Denton:== | ==Dear Mr."Denton:== | ||
wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct.a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct.a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power..Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.Sincerely, P~~~)T<PT 7~P/pe | .Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | ||
Sincerely, | |||
'hii P~ ~~ | |||
)T<PT 7~ | |||
, USA P /pe Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear Mr.Denton:== | ==Dear Mr. Denton:== | ||
.I wish to urge denial of CPSL's request for exemption from the requirement, un'd6 10 CFR 50, Appendix E, that the Company conduct a full~participation. | |||
exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power..Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.Sincerely, | .I wish to urge denial of CPSL's request for exemption from the requirement, un'd6 10 CFR 50, Appendix E, that the Company conduct a full | ||
~@8 PM CA IO OCT 1986 Mr.Harold Denton, Director Office of Nuclear Reaction Regulatio Nuclear Regulatory Commission Washington, DC 20555 | ~ | ||
participation. exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
~@8 PM CA IO OCT 1986 Mr. Harold Denton, Director Office of Nuclear Reaction Regulatio Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear Mr.,== | ==Dear Mr.,== | ||
Denton: Z wish to urge denial of CPS,L's request for exemption from the requirement, undead | Denton: | ||
g8~/Ckapa)R.l/I9aS | Z wish to urge denial of CPS,L's request 10 for exemption from the requirement, undead CFR 50, Appendix E, that the Company conduct a full paarticipation exercise-of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | ||
-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
.C4 g8 lips | |||
~/ | |||
Ckapa) R.l/ I9aS Mr. Harold Denton, 'Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Hashington, DC 20555 li~liljlii))filial)l~s)ilI)(Ilail | |||
Dear Hr. Denton.>> | |||
L's request for exemption fj;6$the requirement, under" 10 CFR 50, Appendix E, tTiat the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to-operate at all.Sincerely, | I wish to urge denial of CPS,L's request for exemption fj;6$ the requirement, under" 10 CFR 50, Appendix E, tTiat the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | ||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to | |||
- operate at all. | |||
Sincerely, | |||
4c pk rv rl( ('r lac. | |||
la ')cv | |||
/946 | |||
~ q~ i r g wxaxr~( | |||
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555 | |||
DC 20555 | |||
==Dear Mr Denton | ==Dear Mr. Denton:== | ||
==Dear Mr.Denton:== | I wish to urge denial'f CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one ye'ar before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | ||
I wish to urge denial of CPBL's re/gest for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.Sincerely, 4'y-4~ | Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | ||
Mr.Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< | Sincerely, C | ||
DC 20555 Denton: I wish to urge denial of CPE,L's request for exemption from the requirement, unddg 10 CFR 50, Appendix E, that the Company conducWa full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.Sincerely, c c~A6~~, lO OCr | |||
,c~ e~ | |||
CPM i +~ | |||
lV 0) | |||
IO OCT I9SS Mr. Harold Denton,~Director Office of Nuclear 'Reaction Regulatiop = | |||
Nuclear Regulatory Commission Washington, DC 20555 | |||
,%ear Mr. Denton: | |||
I wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
.'--"., a~ I~s )=4v ya. g. pk( | |||
( Q Zoo | |||
'u gH. y >pigs < | |||
cg Phh IG OcT | |||
~986 Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555 | |||
Dear Mr Denton. | |||
I wish to urge denial of CPS,L's reqyqst for exemption from the requirement, unde~5 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergencg Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555 | |||
S J | |||
==Dear Mr. Denton:== | |||
I wish to urge denial of CPBL's re/gest for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, 4'y-4 ~ | |||
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555 | |||
Denton: | |||
I wish to urge denial of CPE,L's request for exemption from the requirement, unddg 10 CFR 50, Appendix E, that the Company conducWa full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
c c~A6~~ | |||
&gal~ , | |||
lO OCr lg8g Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear Mr:== | ==Dear Mr:== | ||
.'enton: | .'enton: | ||
I wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the OPmpany conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater-than five percent of rated power.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.Sincerely, Mr.Harold Denton, Director Office'=of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 l~C D'ear Mr;Denton: I wish to urge denial of CPS,LL/grequest for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.Sincerely, Hr.Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | I wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the OPmpany conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater-than five percent of rated power. | ||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
Mr. Harold Denton, Director Office'=of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
l | |||
~C D'ear Mr; Denton: | |||
I wish to urge denial of CPS,LL/grequest for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
Hr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear:== | ==Dear:== | ||
:Hr.<<Benton: | :Hr.<<Benton: | ||
I wish to urge denial of CPS,L's request for exemption from the requirement~Zpn'der 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.-Because of the need for changes in the evacua-tion plan, l believe this exercise should be conducted before the plant is permitted to operate at all.Sincerely, Mr.Harold Denton,,-Director Office of Nuclear-Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | I wish to urge denial of CPS,L's request for exemption from the requirement~Zpn'der 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | ||
-Because of the need for changes in the evacua-tion plan, l believe this exercise should be conducted before the plant is permitted to operate at all. | |||
Sincerely, | |||
Mr. Harold Denton,,- Director Office of Nuclear-Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555 | |||
==Dear Mr. Denton:== | |||
x I wish to urge denial of CPS,L's request for exemption from the re quirkgent, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power. | |||
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to r | |||
operate at all. | |||
Sincerely, | |||
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555}} | |||
Latest revision as of 20:33, 3 February 2020
ML18004A590 | |
Person / Time | |
---|---|
Site: | Harris |
Issue date: | 10/10/1986 |
From: | Bullock N, Caison W, Cake E, Cashwell P, Courbois C, Davis L, Fuller F, Greenberg G, Greenberg S, Halford M, Halford R, Hobbs A, Jessup J, Kardon R, Palton K, Pettee C, Tuller D, Wall L, Denise Wilson, Wilson R, Wissner J AFFILIATION NOT ASSIGNED |
To: | Harold Denton Office of Nuclear Reactor Regulation |
References | |
NUDOCS 8610170251 | |
Download: ML18004A590 (60) | |
Text
RECUI+ORY INFORNATION DIBTRIBUTy<N BYBTEN (RIDE>
ACCESBIObl NBR: 8610170251 DOC. DATE: 86/10/10 NOTARIZED: NO DOCKET FACIL: 50-400 Shearon Harris Nuclear Power Planti Unit i. Carolina 05000400 AUTH. NANE AUTHOR AFFILIATION DAVIS> L. AFfiliation Not Assigned MALL> L, B. AFFiliation Not Assigned QREENl3ERQ> S. K. Affiliation Not Assigned RECIP. NANE RECIPIENT AFFlLIATIGN DENTON) H. R Office of Nuclear Reactor Regulation~ Director (post 851125
SUBJECT:
Package of 29 postcards urging NRC to deny util request for exemption from 10CFR50i App E requirement re full participation exercise of emergency response plan prior to commerc ial operation of p lant.
DIBTRIDUTION CODE: YEOBD TITLE: Request For NRR COP IEB RECEIVED: LTR cDBENCL Action (e.
0 BI ZE:
- g. 2. 206 Petitions) 8c Related Correspondenc NOTES: Application for permit renewal Filed. 05000<00 RECIPIENT COP IEB RECIPIENT COPIES ID CODE/NANE LTTR ENCL ID CODE/NAME LTTR ENCL PMR-A PD2 LA PWR-A PD2 PD gUCKLEYp 8 01 INTERNAL: EDO/ACB ELD/HDB1 E ED NRR DIR R
EXTERNAL: LPDR 03 NRC PDR 02 NBIC 05
I>>
Dear Mr.'5?Eton:
II I wish to urge denial of CPSL's r'egest for exemption from the requirement, unlit 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
-Sincerely, p,o)
)w, Qg Q h
'~.8610i7025i Ghi010 ADOCK;08000400
- <<,PDR
,."H., ", . PDA'
J A~
l
>.l l.
gP
~'
C
Dear Mr.=Denton:
I wish to urge denial of CPSL's r&guest for exemption from the requirement, under $ .0 CFR 50 Appendix E, that the Company conduct 6 full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before'the plant is permitted to operate at all.
Sincerely,
~ ~
p
Mrs. Lainbert Daiis
'- ~
a PM 0
70I Greenwood Road
~> Chapel ~Hill; NC~ 27514~=
)9 )cT 1
f986 Mr. Harold Denton, Director Office=-of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear" Mr .. Denton:
I wish to urge denial of CPEL's request for exemption from the reguirement, under ~0 CFR 50, Appendix E, that the~oanpany conduct a ~full Participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
.1986 Mr. Harold Denton, Director Office-'o'f Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555
Dear Hr. Denton:
I wish to urge denial of CPS,L's gdguest for exemption from the requirement, urger 10 CFR 50, Appendix E, that the Company conducb"a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
"'-:c" >Bi a'j~i~
R /t/88K C , spis, f8 77Fo<A/coo 8@i.
C~pM e]~c. si r)'+
=V Mr.:Harold Denton, Director Offi'ce'of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
p%
4
Dear Mr. Denton:
I wish to urge denial of CPS,L's request for exemption from the requirement, undJg 10 CFR 50, Appendix E, that the Company conduct-a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerel
USA .
- 14-i'-I Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Nashington, DC 20555
Dear Mr. Denton:
I wish to urge denial of CPS,L's j p requ'eA for exemption from the requirement, under"10 CPR 50, Appendix E, that the Company. conduct a full participation exercise'f the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,.
Mr. Harold Denton, of Nuclear Reaction Regulatiop Directorg-'ffice Nuclear Regulatory Commission Washington, DC 20555
Dear Mr.,
Denton: ~
- j. vjyh to urge denial of CPSLP's request for
,exemption from the requirement, under 10 CPR 50,
- Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear pover plant
~ within one year before beginning commercial operation of the plant or before operating at greater than f've percent of rated pover.
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
~ I.,
Mr. Harold Benton, Director of Nuclear React'ion Regulatiop ('ffice Nuclear Regulatory Commission Hashington, DC 20555
Dear Hr. Denton:
I wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, E believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
X
~~ oct USA I98 M~~Harold Denton, Director Of'&ice. of Nuclear Reaction Regulatio Nuclear Regulatory Commission Washington, DC 20555
r4 J'pa g ~ ~ * &<1 a
Dear Hr. Denton:
I wish to urge denial of CPS,L's request for exemption from the requirement,--under 10 CFR 50; Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
4
Dear. Mr. Denton:
wish to urge denial of CPS,L's request for exemption from the requirement, undeg 10 CFR 50, Appendix E, tha t thd company conduc t' full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all..
g~~ ~~g I
Sincerely,
Q8e ~mc Paauqpig '~
PNI
/0 ~A'A OCT'986 Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear. Mr. Denton:
E wish to urge denial of CPS,L's request for exemption from the requirement, undegz)0 CFR 50, Appendix E, that the Company conduct'Q full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at al Sincerely,
Cev~~4
+J +. Ca~mn 4~<
Qqpgpg Qg// ~,
z~j'Q I0 ocT Iree
-~sr ~rg(~end Mr. Harold Denton, .D'irector Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear Mr". Denton:
I wish to urge denial of CPS,L's request for exemption from the requirement, der 10 CFR 50, Appendix E, that the Company conduct~a=full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, 1 believe this exercise should be conducted before the plant is peg itted to operate at all.
Sincerely,
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Denton:
- I wish to urge denial of CPSL's request for exemption from the requirement, ufi'der" 10 CFR 50,
,Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Since e
C.
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Dent;,
on:
I wish to urge denial of CPSL's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response
.Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
Mr. Harold Denton, Director Office of Nuclear Reaction Regulation Nuclear Regulatory Commission Washington, DC 20555
Dear Hr. Den7on:
I wish to urge denial of CPS,L's request'tz for exemption from the requirement, under )0 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
cP. PL- (m ge8 ~~ir e~w>q-t 6- g~ < (PM. +
K 0)
Qy~ g'.C g.95 cO IO OCT 1986 C
Mr. Harold Denton,."Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
4kcaas Dqyr Mr; Denton:
~ <<<<I <<4 I'ish to urge denial op CPS,L's request for exemption from the requ'irement, under&0 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
G~ ig m<PMg<~
0)
IO OCT 1986 rises ~~
Mr. Harold Denton~,~Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
0, C
Dear Mr."Denton:
wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct.a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
'hii P~ ~~
)T<PT 7~
, USA P /pe Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Denton:
.I wish to urge denial of CPSL's request for exemption from the requirement, un'd6 10 CFR 50, Appendix E, that the Company conduct a full
~
participation. exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
~@8 PM CA IO OCT 1986 Mr. Harold Denton, Director Office of Nuclear Reaction Regulatio Nuclear Regulatory Commission Washington, DC 20555
Dear Mr.,
Denton:
Z wish to urge denial of CPS,L's request 10 for exemption from the requirement, undead CFR 50, Appendix E, that the Company conduct a full paarticipation exercise-of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
.C4 g8 lips
~/
Ckapa) R.l/ I9aS Mr. Harold Denton, 'Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Hashington, DC 20555 li~liljlii))filial)l~s)ilI)(Ilail
Dear Hr. Denton.>>
I wish to urge denial of CPS,L's request for exemption fj;6$ the requirement, under" 10 CFR 50, Appendix E, tTiat the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to
- operate at all.
Sincerely,
4c pk rv rl( ('r lac.
la ')cv
/946
~ q~ i r g wxaxr~(
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555
Dear Mr. Denton:
I wish to urge denial'f CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one ye'ar before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely, C
,c~ e~
CPM i +~
lV 0)
IO OCT I9SS Mr. Harold Denton,~Director Office of Nuclear 'Reaction Regulatiop =
Nuclear Regulatory Commission Washington, DC 20555
,%ear Mr. Denton:
I wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
.'--"., a~ I~s )=4v ya. g. pk(
( Q Zoo
'u gH. y >pigs <
cg Phh IG OcT
~986 Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555
Dear Mr Denton.
I wish to urge denial of CPS,L's reqyqst for exemption from the requirement, unde~5 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergencg Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
.Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555
S J
Dear Mr. Denton:
I wish to urge denial of CPBL's re/gest for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely, 4'y-4 ~
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington< DC 20555
Denton:
I wish to urge denial of CPE,L's request for exemption from the requirement, unddg 10 CFR 50, Appendix E, that the Company conducWa full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
c c~A6~~
&gal~ ,
lO OCr lg8g Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear Mr:
.'enton:
I wish to urge denial of CPS,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that the OPmpany conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater-than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
Mr. Harold Denton, Director Office'=of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
l
~C D'ear Mr; Denton:
I wish to urge denial of CPS,LL/grequest for exemption from the requirement, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
-Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
Hr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear:
- Hr.<<Benton:
I wish to urge denial of CPS,L's request for exemption from the requirement~Zpn'der 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
-Because of the need for changes in the evacua-tion plan, l believe this exercise should be conducted before the plant is permitted to operate at all.
Sincerely,
Mr. Harold Denton,,- Director Office of Nuclear-Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Denton:
x I wish to urge denial of CPS,L's request for exemption from the re quirkgent, under 10 CFR 50, Appendix E, that the Company conduct a full participation exercise of the Emergency Response plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.
Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to r
operate at all.
Sincerely,
Mr. Harold Denton, Director Office of Nuclear Reaction Regulatiop Nuclear Regulatory Commission Washington, DC 20555