Package of Three Comments Urging Denial of Util Request for Exemption from Requirement Under 10CFR50,App E That Full Participation Exercise of Emergency Response Plan Be Conducted within 1 Yr Prior to Commercial Operation
ML18004A573
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 10/01/1986
From: Bishop G, Latta A, Mazzitelli J
AFFILIATION NOT ASSIGNED
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8610100205
Download: ML18004A573 (9)


Text

REGULA Y INFORNATION DISTR IBUTI YSTEl'1 (R IDB)

ACCESSION NBR: 8610100205 DOC. DATE: 86/10/01 NOTARIZED:

NO DOCKET 0 FAG IL:50-400 Shearon Harris Nuclear Power Plant.

Uni't 1> Carolina 05000400 AUTH. NANE AUTHOR AFFILIATION BISHOP> Q. K.

AffiliationNot Assigned LATTA>A.

AffiliationNot Assigned NAZZITELLI>J.

Affiliation Not Assigned REClP. NANE RECIPIENT AFFILIATION DENTON> H.

Office of Nuclear Reactor Regulation.

Direc tor (post 851125

SUBJECT:

Package of three comments uringin denial of util request for exemption from requirement under 10CFR50> App E that full participation exercise of emergency response plan be conducted ei thin 1 gr prior to commercial operation.

DISTRIBUTION CODE:

YE03D COPIES RECEIVED: LTR ENCL BI ZE:

TITLE: Request for NRR Action (e. g.

2. 206 Petitions) 8c Related Correspondenc NOTES: Applicati on for permit reneua 1 fi 1 ed.

05000400 RECIPIENT ID CODE/NAl'1E PNR-A PD2 LA QUCKLEY. 8 01 COPIES LTTR ENCL RECIPIENT ID CODE/NAI'fE PWR-A PD2 PD COPIEB LTTR ENCL INTERNAL: EDO/ACB REQ FILE EXTERNAL:

LPDR NSIC 04 03 05 ELD/HDB1 NRR DIR NRC PDR 02 TOTAL NU<BER OF COPIEB REQUIRED:

LTTR 11 ENCL

,p 4

hh M

4 I

M

'l 4'kl

'1 ~ l 44

~

~

k Vr q

I h }

( r I }rt'),itr,,tl)'

s'r '}:j>>

C I

M hv IV 4

r Ilrlt

Dear Mr. Denton:

I wish to urge denial of CPS,L's request for exemption from the requirement~der 10 CPR 50, Appendix E, that the Company cog~et a full participation exercise of the Emergency

Response

Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rat'ed power.

Because of the need for changes in the evacua-tion plan, I believe this exercise shoul'd be conducted before the plant is permitted to operate at all.

Sincerely, i001 8~>o 9OCW O~

poR ppp5 8b OogOO pop A

H

Dear Mr. Denton:

l wish to urge, denial of CPBL's request for exemption from the requirement, under 10 CFR 50, Appendix E, that QAe Company conduct a full participation exercise of the Emergency

Response

Plan for its Shearon Harris nuclear power plant within one year before-beginning commercial

'peration of the plant or before operating at greater than five percent of rated power.

Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.

Sincerely,

~ear Mr. Denton:

~

It'WED IW t

~

~rT>>

~V 4>>

I wish to urge denial of CPS,L's request for exemption from the requirement, unde@ l0 CPR 50, Appendix E, that the Company conducts full participation exercise of the Emergency

Response

Plan for its Shearon Harris nucleai power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.

Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.

Sincerel

( (~0~

~C C

Dear Mr.'enton:

I wish to urge denial of CPSL's request for exemption from the requirement~der 10 CFR 50, Appendix E, that the Company cqrgQuct a full participation exercise of the Emergency

Response

Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.

Because of the need for changes in the evacua-tion plan, I believe this exercise shoul'd be

~ conducted before the plant is permitted to operate at all.

Sincerely,

)$

0 iD ppOS 8" ppaO0 OO1 8bio1 g5 PSO pgp--

PDg g 9O H

Dear Mr. Denton:

I wish to urge denial of CPE,L's request for exemption from the requirement, under 10 CFR 50, Appendix E, that Q6e Company conduct a full participation exercise of the Emergency

Response

Plan for its Shearon Harris nuclear power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.

Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.

Sincerely,

ear Mr. Denton:

i()l'le I~

m )PMq<~

0%

I OCr l906 l wish to urge denial of CPS,L's request for exemption from the requirement, und~@.10 CFR 50, Appen'dix E, that the Company conduct@ full partici*pation exercise of the Emergency

Response

Plan for its Shearon Harris nuclear -'power plant within one year before beginning commercial operation of the plant or before operating at greater than five percent of rated power.

Because of the need for changes in the evacua-tion plan, I believe this exercise should be conducted before the plant is permitted to operate at all.

Sincerel

0