W3P87-1231, Discusses Progress in Installation of Training Simulator. Packing of Simulator for Shipment Delayed Until 870414 Due to Vendor,Singer Co,Problems.Completion,Installation & Reverification Testing Planned by 870514

From kanterella
(Redirected from W3P87-1231)
Jump to navigation Jump to search
Discusses Progress in Installation of Training Simulator. Packing of Simulator for Shipment Delayed Until 870414 Due to Vendor,Singer Co,Problems.Completion,Installation & Reverification Testing Planned by 870514
ML20210C076
Person / Time
Site: Waterford Entergy icon.png
Issue date: 04/30/1987
From: Cook K
LOUISIANA POWER & LIGHT CO., NEW ORLEANS PUBLIC SERVICE CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
W3P87-1231, NUDOCS 8705060076
Download: ML20210C076 (3)


Text

c P LOutSIANA POWER E LIGHT COMPANY

  • Post Office Box 60340

ram;;

NEW ORLEANS PUBLIC SERVICE INC. e Post Office Box 60340 e New Orleans, Louisiana 70160 April 30, 1987 W3P87-1231 A4.10 QA U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555

SUBJECT:

Waterford 3 SES Docket No. 50-382 Waterford 3 Nuclear Power Plant Simulator Progress Summary Update and Ready-For-Training Date Schedule

REFERENCES:

1) Letter W3PE7-0720, K. W. Cook to U. S. Nuclear Regulatory Commission, dated February 28, 1987
2) Letter W3P83-2261,.F. J. Drummond to G. W. Knighton, dated July 1, 1983

Dear Sir:

The Louisiana Power & Light Company (LP&L), in reference 1, provided a brief summary completion status on the Waterford 3 Training Simulator to the U. S. Nuclear Regulatory Commission (NRC). Also indicated in reference 1 was a projected date of March 13, 1987 to start packing the simulator for shipment.

Subsequent to the Reference 1 schedule projections, the simulator vendor (Link Simulation Systems Division of the Singer Company

[ Link]) was not able to complete simulator discrepancy corrections and computer programs re-work resulting from factory acceptance testing as quickly as projected; and the March 13, start-packing projected date for the simulator was not achieved.

However, through the constant attention of both LP&L and Link personnel and executive management, additional technical and manpower resources were applied to minimize further slippage in '

the schedule; and as a result, packing of the simulator for shipment started on April 14, 1987.

8705060076 B70430 DR ADDcK 05000 82 ,

f0)

'I "AN EQUAL OPPORTUNITY EMPLOYER"

I U.S. Nuclear _ Regulatory Commission.

W3P87-1231 Page 2 On April 28, 1987,_the first partial _ shipment of the simulator.

computers and control panels was received at the LP&L Energy Education Center, with the balance of the simulator components expected by May 1, 1987. ~nstallation of'the simulator components received in the initial shipment is in progress.as of this date. The present projected schedule for the simulator is.for all simulator _ components to be completed, installed and

. reverification testing started by May 14, 1987.

LP&L would like to emphasize that the completion of the simulator.

.in a' timely manner continues to be a high priority undeavor for LP&L and one which will continue to receive the complete initiative and support of LP&L personnel and' executive' management.

If you require any additional information or have any questions, please contact E. J. Senac at (504) 587-6475 or.myself at (504) 595-2805.

Yours very truly,

(

/hb%b /A K. W. Cook.

Nuclear Safety _and Regulatory Affairs Manager.

KWC/GMW/dmd cc: E.L. Blake, W.M. Stevenson, J.A. Calvo, J.H. Wilson, R.D. Martin, NRC Resident Inspector's Office (W-3).

= ,

o W3P87-1231 Page 3 bec: R.P. Barkhurst, F.J. Drummond, T.F. Gerrets, S.A. Alleman, N.S. Carns, J.R. McGaha, R.F. Burski, E.J. Senac, G.E. Wuller, R.J. Murillo, G.E. Wilson, J.B. Houghtaling, M.P. Horrell, W.A. Cross, T.A. Jones, C.J. Toth, Project Files, Administrative Support, Licensing Library i