W3P84-3303, Forwards Application to Amend CPPR-103,extending Const Completion Date to 850228.Addl Time Needed to Address & Close Out Outstanding Issues to Accommodate Unanticipated Issues or Events

From kanterella
Jump to navigation Jump to search
Forwards Application to Amend CPPR-103,extending Const Completion Date to 850228.Addl Time Needed to Address & Close Out Outstanding Issues to Accommodate Unanticipated Issues or Events
ML20099L286
Person / Time
Site: Waterford Entergy icon.png
Issue date: 11/28/1984
From: Leddick R
LOUISIANA POWER & LIGHT CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML20099L288 List:
References
W3P84-3303, NUDOCS 8412010075
Download: ML20099L286 (2)


Text

1 O-louisiana 44a ce-oNoe er..1 . m ooxeoos P O W E R & L i G H T! NEW CAMANS LOUISIANA 701744000 9 (504)360-2345 UTauTIES SYST(M November 28, 1984 ROTH S. LEDDICK Senior Vice President Nuclear Operations W3P84-3303 3-A1.01.04 Q-3-A28.ll A4.05 l

1 Mr. Darrell. G. Eisenhut, Director Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555

SUBJECT:

Louisiana Power & Light Company Waterford SES Unit 3 Docket No. 50-382 Amended Request for Extension of Construction Permit REFERENC"S: 1) Letter from R.S. Leddick to D.C. Eisenhut (W3P83-3264), dated September 29, 1983

2) Letter from R.S. Leddick to D.G. Eisenhut (W3P84-2184), dated August 15, 1984
3) Letter from D.G. Eisenhut to J.M. Cain, dated June 13, 1984

Dear Mr. Eisenhut:

In the above Reference 1 and pursuant to 10 CFR 50.55(b), Louisiana Power &

Light (LP&L) requested that the Commission extend the construction completion date for Waterford SES Unit No. 3 set forth in the Construction Permit, CPPR-103, to September 30, 1984.

In the above Reference 2 LP&L amended Reference 1 by requesting a construction completion extension until December 31, 1984. LP&L hereby submits a second amendment to Re ~erence 1 by requesting a construction completion date extension until February 28, 1985.

LP&L continues to believe that design, construction and testing of Waterford 3 have essentially been completed in accordance with the Final Safety Analysis Report and other licensing documents and that the unit is ready to load fuel. Additional time required to respond to NRC issues (Reference 3) was the basis for the previous extension request. LP&L has since addressed the issue in Reference 3, and the documentation of the NRC staff review to support issuance of an operating license is pending.

8412010075 841128 l

{DRADOCK 05000382 h00 PDR f1 l

r W3P84-3303 Mr. D.G. Eisenhut

- Page 2

' Completion of the: staff efforts and resolution of other outstanding issues are expected to' support issuance.ofsan operating license shortly, possibly prior to the expiration date of December 31, 1984. The request for a two month extension is requested to provide sufficient margin beyond the time required to address and close' out. the outstanding issues to accommodate .

unanticipated issues or' events.

V truly yours, p R. S. Leddick RSL/RWP/ch cc: E.L. Blake, W.M. Stevenson, J.H. Wilson, G.L. Constable, D.M. Crutchfield, R.D. Martin I