Forwards Safety Evaluation Partially Accepting Util 831114 & 850612 Responses to Generic Ltr 83-28,Item 4.5.3 Re on-line Testing of Reactor Trip Sys
ML20244C839
Person / Time
Site: Oyster Creek
Issue date: 06/12/1989
From: Dromerick A
Office of Nuclear Reactor Regulation
To: Fitzpatrick E
GENERAL PUBLIC UTILITIES CORP.
Shared Package
ML20244C843 List:
References
GL-83-28, TAC-54008, NUDOCS 8906150163
Download: ML20244C839 (2)


Text

-- - __

a t ' June 12,1989

o. x Docket No. 50-219- DISTRIBUTION yksscastmto# - EJordan.

Mr. E. E. Fitzpatrick , NRC & Local PDRs' BGrimes Vice: President and Director Plant File ACRS(10)

Oyster Creek Nuclear Generating Station SVarga DR Lasher Post Office Box 388 BBoger Forked River, Nev: Jersey . 08731 SNorris?

ADromerick

Dear Mr. Fitzpatrick:

OGC

SUBJECT:

SAFETY EVALUATION FOR GENERIC LETTER 83-28, ITEM 4.5.2 FOR:THE OYSTERCREEKNUCLEARGENERATINGSTATION(TACNO.54008)

GPU Nuclear. Corporation (GPUN/ licensee) was required by Generic Letter 83-28 Item 4.5.2 to confirm that the Oyster Creek Nuclear Generating-Station is.

, designed to permit periodic on-line. testing of the Reactor Trip System and, if not, to justify.not making modifications to permit such testing. In letters dated November 14, 1983 and June 12, 1985, you stated that the plant is

' designed to permit the required on-line testing of the Reactor Trip System.

You further stated that this testing will include independent verification of the operability of the shunt and undervoltage trip features.

Our review of this information as documented in our contractor's report, EGC.

NTA 7470, finds it partially acceptable for resolving this issue. The enclosed Safety Evaluation documents our concurrence with the contractor's findings and documents our review of additional information submitted by you on May 15, 1989 which satisfied the outstanding concern in our contractor's report. Therefore, we consider Item 4.5.2 of Generic Letter 83-28 to be resolved.

Sincerely,

/s/

Alexander W. Dromerick, Project Manager Project Directorate'I-4.

Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

Enclosure:

As. stated cc w/ enclosure:

.See next page

-[ TAC NO. 54008]

P 4 PD: 4

. S(dPrisL :PD wI-4 rick:cb JStol

[(/89 4/89 g/pB9 I 16 i

l 8906150163 890612 PDR ADOCK 05000219 P PDC

( '.

\

! I '

.Mr. E. E. Fitzpatrick Oyster Creek Nuclear Oyster Creek Nuclear Generating Station Generating Station cc:

Ernest L. Blake, Jr. Resident Inspector Shaw, Pittman, Potts and Trowbridge c/o U.S. NRC 2300 N Street, NW Post Office Box 445 Washington, D.C. 20037 Forked River, New Jersey 08731 l

J.B. Liberman, Esquire Commissioner Bishop, Libertaan, Cook, et al. New Jersey Department of Energy 1155 Avenue of the Americas 101 Commerce Street New York, New York 10036 Newark, New Jersey 07102 Jennifer Moon, Acting Chief j

Regional Administrator, Region I New Jersey Department of Environmental U.S. Nuclear Regulatory Conrnission Protection 475 Allendale Road Bureau of Nuclear Engineering King of Prussia, Pennsylvania 19406 CN 415 Trenton, New Jersey 08625 BWR Licensing Manager GPU Nuclear Corporation i Upper Pond Road Parsippany, New Jersey 07054 Deputy Attorney General State of New Jersey Department of Law and Public Safety 36 West State Street - CN 112 Trenton, New Jersey 08625 Mayor Lacey Township 818 West Lacey Road Forked River, New Jersey 08731 Licensing Manager Oyster Creek Nuclear Generating Station Mail Stop: Site Emergency Bldg.

P. O. Box 388 Forked River, New Jersey 08731

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _