W3P87-1231, Discusses Progress in Installation of Training Simulator. Packing of Simulator for Shipment Delayed Until 870414 Due to Vendor,Singer Co,Problems.Completion,Installation & Reverification Testing Planned by 870514

From kanterella
(Redirected from ML20210C076)
Jump to navigation Jump to search
Discusses Progress in Installation of Training Simulator. Packing of Simulator for Shipment Delayed Until 870414 Due to Vendor,Singer Co,Problems.Completion,Installation & Reverification Testing Planned by 870514
ML20210C076
Person / Time
Site: Waterford Entergy icon.png
Issue date: 04/30/1987
From: Cook K
LOUISIANA POWER & LIGHT CO., NEW ORLEANS PUBLIC SERVICE CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
W3P87-1231, NUDOCS 8705060076
Download: ML20210C076 (3)


Text

c P LOutSIANA POWER E LIGHT COMPANY

  • Post Office Box 60340

ram;;

NEW ORLEANS PUBLIC SERVICE INC. e Post Office Box 60340 e New Orleans, Louisiana 70160 April 30, 1987 W3P87-1231 A4.10 QA U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555

SUBJECT:

Waterford 3 SES Docket No. 50-382 Waterford 3 Nuclear Power Plant Simulator Progress Summary Update and Ready-For-Training Date Schedule

REFERENCES:

1) Letter W3PE7-0720, K. W. Cook to U. S. Nuclear Regulatory Commission, dated February 28, 1987
2) Letter W3P83-2261,.F. J. Drummond to G. W. Knighton, dated July 1, 1983

Dear Sir:

The Louisiana Power & Light Company (LP&L), in reference 1, provided a brief summary completion status on the Waterford 3 Training Simulator to the U. S. Nuclear Regulatory Commission (NRC). Also indicated in reference 1 was a projected date of March 13, 1987 to start packing the simulator for shipment.

Subsequent to the Reference 1 schedule projections, the simulator vendor (Link Simulation Systems Division of the Singer Company

[ Link]) was not able to complete simulator discrepancy corrections and computer programs re-work resulting from factory acceptance testing as quickly as projected; and the March 13, start-packing projected date for the simulator was not achieved.

However, through the constant attention of both LP&L and Link personnel and executive management, additional technical and manpower resources were applied to minimize further slippage in '

the schedule; and as a result, packing of the simulator for shipment started on April 14, 1987.

8705060076 B70430 DR ADDcK 05000 82 ,

f0)

'I "AN EQUAL OPPORTUNITY EMPLOYER"

I U.S. Nuclear _ Regulatory Commission.

W3P87-1231 Page 2 On April 28, 1987,_the first partial _ shipment of the simulator.

computers and control panels was received at the LP&L Energy Education Center, with the balance of the simulator components expected by May 1, 1987. ~nstallation of'the simulator components received in the initial shipment is in progress.as of this date. The present projected schedule for the simulator is.for all simulator _ components to be completed, installed and

. reverification testing started by May 14, 1987.

LP&L would like to emphasize that the completion of the simulator.

.in a' timely manner continues to be a high priority undeavor for LP&L and one which will continue to receive the complete initiative and support of LP&L personnel and' executive' management.

If you require any additional information or have any questions, please contact E. J. Senac at (504) 587-6475 or.myself at (504) 595-2805.

Yours very truly,

(

/hb%b /A K. W. Cook.

Nuclear Safety _and Regulatory Affairs Manager.