Summary of Telephone Conference Call Held on December 23, 2009, Between the U.S. NRC and Florida Power Corporation, Concerning Applicant'S Response to a RAI Pertaining to the Crystal River Unit 3 Nuclear Generating Plant License Renewal..
ML100320036
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 02/19/2010
From: Robert Kuntz
License Renewal Projects Branch 2
To:
Florida Power Corp
KUNTZ R, NRR/DLR, 415-2989
References
Download: ML100320036 (5)


Text

February 19, 2010 LICENSEE: Florida Power Corporation FACILITY: Crystal River Unit 3 Nuclear Generating Plant

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON DECEMBER 23, 2009, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FLORIDA POWER CORPORATION, CONCERNING APPLICANTS RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Florida Power Corporation (the licensee or the applicant) held a telephone conference call on December 23, 2009 to discuss the licensees response to a request for additional information (RAI) concerning the Crystal River Unit 3 Nuclear Generating Plant (CR-3) license renewal application (LRA). The telephone conference call was useful in clarifying the licensees RAI response.

During the telephone conference call, the staff sought clarification on a response to an RAI provided in a letter dated October 13, 2009 (Agencywide Documents Access and Management Access Accession No. ML092890155). RAI B.2.30-1 requested more information on the inspection frequency of concrete structures inspected under the Structures Monitoring Program.

The staff sought clarification on what structures would be inspected at intervals greater than five years. The applicant stated that as detailed in the RAI response the structures that the inspection schedule is established so that degradation would be detected before the loss of function. The staff may consider issuing an additional RAI requesting the applicant to provide further detail on how the inspection frequency will be determined.

The staff also sought clarification on the applicants aging management of reactor vessel internals. The applicant stated that as per Commitment No. 1 in the LRA they will participate, evaluate and implement the results of the industry programs as applicable and by 24 months prior to entering the period of extended operation they will submit an inspection plan for reactor internals to the NRC for review and approval.

Florida Power Corporation The enclosure provides a listing of the participants.

The applicant had an opportunity to comment on this summary.

/RA/

Robert Kuntz, Senior Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302

Enclosure:

As stated cc w/encl: See next page

Florida Power Corporation The enclosure provides a listing of the participants.

The applicant had an opportunity to comment on this summary.

/RA/

Robert Kuntz, Senior Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302

Enclosure:

As stated cc w/encl: See next page DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource

________

RKuntz DBrittner AJones, OGC LLake, RII MSykes, RII TMorrissey, RII RReyes, RI OFFICE PM:RPB2:DLR LA:RPOB:DLR BC:RPB2:DLR PM:RPB2:DLR NAME RKuntz YEdmonds DWrona RKuntz (Signature)

DATE 02/16/10 02/5/10 02/19/10 02/19/10 OFFICIAL RECORD COPY

TELEPHONE CONFERENCE CALL CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS DECEMBER 23, 2009 PARTICIPANTS AFFILIATIONS Robert Kuntz U.S. Nuclear Regulatory Commission (NRC)

James Medoff NRC Madhumita Sircar NRC Abdul Sheikh NRC Hans Ashar NRC Todd Mintz Center for Nuclear Waste Regulatory Analysis Mike Heath Florida Power Corporation (FPC)

Mike Fletcher FPC Wayne Bichlmeir FPC Chris Malner FPC Jeff Lane FPC Bob Reynolds FPC ENCLOSURE

Crystal River Unit 3 Nuclear Generating Plant cc:

Mr. R. Alexander Glenn Mr. Daniel R. Westcott Associate General Counsel (MAC-BT15A) Supervisor, Licensing & Regulatory Florida Power Corporation Programs P.O. Box 14042 Crystal River Nuclear Plant St. Petersburg, FL 33733-4042 15760 W. Power Line Street Crystal River, FL 34428-6708 Mr. James W. Holt Plant General Manager Senior Resident Inspector Crystal River Nuclear Plant (NA2C) Crystal River Unit 3 15760 W. Power Line Street U.S. Nuclear Regulatory Commission Crystal River, FL 34428-6708 6745 N. Tallahassee Road Crystal River, FL 34428 Mr. William A. Passetti, Chief Department of Health Mr. Jack E. Huegel Bureau of Radiation Control Manager, Nuclear Oversight 2020 Capital Circle, SE, Bin #C21 Crystal River Nuclear Plant (NA2C)

Tallahassee, FL 32399-1741 15760 W. Power Line Street Crystal River, FL 34428-6708 Attorney General Department of Legal Affairs Mr. David T. Conley The Capitol Associate General Counsel II - Legal Dept.

Tallahassee, FL 32304 Progress Energy Service Company, LLC P.O. Box 1551 Mr. Ruben D. Almaguer, Director Raleigh, NC 27602-1551 Division of Emergency Preparedness Department of Community Affairs Mr. Michael P. Heath 2740 Centerview Drive Supervisor, License Renewal Tallahassee, FL 32399-2100 Progress Energy 8470 River Road, 2E Chairman Southport, NC 28461 Board of County Commissioners Citrus County Mr. Mark Rigsby 110 North Apopka Avenue Manager, Support Services - Nuclear Inverness, FL 34450-4245 Crystal River Nuclear Plant (SA2C) 15760 W. Power Line Street Mr. Stephen J. Cahill Crystal River, FL 34428-6708 Engineering Manager Crystal River Nuclear Plant (NA2C) Mr. Robert J. Duncan II 15760 W. Power Line Street Vice President, Nuclear Operations Crystal River, FL 34428-6708 Progress Energy P.O. Box 1551 Raleigh, NC 27602-1551

Crystal River Unit 3 Nuclear Generating Plant cc:

Mr. Brian C. McCabe Manager, Nuclear Regulatory Affairs Progress Energy P.O. Box 1551 Raleigh, NC 27602-1551 Mr. Jon Franke, Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing &

Regulatory Programs 15760 W. Power Line Street Crystal River, FL 34428-6708