Summary of Meeting with Duke Energy to Discuss Decommissioning Submittals for Crystal River Unit 3 Nuclear Generating Plant
ML13253A216
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 09/12/2013
From: Gratton C
Plant Licensing Branch II
To:
Gratton C
Shared Package
ML13253A214 List:
References
TAC MF2635
Download: ML13253A216 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 12, 2013 LICENSEE: Duke Energy Florida, Inc.

FACILITY: Crystal River Unit 3 Nuclear Generating Plant

SUBJECT:

SUMMARY

OF AUGUST 29, 2013, MEETING WITH DUKE ENERGY TO DISCUSS DECOMMISSIONING SUBMITTALS FOR CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT (TAC NO. MF2635)

On August 29,2013, the Nuclear Regulatory Commission (NRC) staff conducted a Category 1 public meeting with Duke Energy Florida, Inc., representing Florida Power Corporation (the licensee), at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland (see notice at Agencywide Documents Access and Management System (ADAMS)

Accession No. ML13225A199). The meeting provided an opportunity for the licensee to discuss its plans for submittals to support the decommissioning of its Crystal River Unit 3 Nuclear Generating Plant. The licensee's presentation material may be accessed in ADAMS at Accession No. ML13238A307. The list of meeting attendees is enclosed.

The licensee covered the status of decommissioning activities to date, and discussed its planned permanently defueled (PD) accident analysis upon which upcoming submittals would be based. The licensee expects to submit a PD emergency plan, PD technical specifications, and PD security plan. The license also mentioned its proposed schedule for the submission of its Post Shutdown Decommissioning Activities Report.

The NRC staff asked questions throughout the presentation, and gave the following feedback:

  • For instances where the emergency plan staffing is proposed to be amended, the licensee should provide detailed analysis of the requested change with the application.

Additionally, if the licensee is not seeking an exemption from performing an on-shift staffing analysis, then the staffing analysis is to be included in the amended emergency plan.

  • For any proposed changes related to the timing of emergency classification and notification of offsite agencies, a detailed technical analysis should be provided as well as any past precedents.
  • The licensee asked about the predictability of NRC review durations. The NRC staff stated that it is our goal to review all licensing applications in a timely manner consistent with our obligations to the public, however, as stated in a letter to operating plant licensees dated June 13, 2013 (ADAMS Accession No. ML13151A377), the staff continues to assess and redefine priorities as a result of the recommendations resulting from the Fukushima Lessons Learned Task Force. As a result, some licensing action schedules may be impacted. To foster a common awareness of project schedule expectations, we will continue to maintain routine communications with licensees through the NRC project managers.

- 2 Members of the public were present at the meeting and also participated via the conference line. No Public Meeting Feedback forms were received.

Please direct any inquiries to me at 301-415-1055, or christopher.gratton@nrc.gov.

~~

Christopher Gratton, Senior Project Manager Plant Licensing Branch /1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-302

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv

PUBLIC MEETING WITH DUKE ENERGY CRYSTAL RIVER UNIT 3 PRE-APPLICATION MEETING ON DECOMMISSIONING LICENSING SUBMITTALS AUGUST 29, 2013 LIST OF ATTENDEES NRC C. Gratton A. Gendelman C. Schulten B. Mizuno R. Grover A. Nerret D. Broaddus S. Galbreath T. Tate G. Casto J. White K. Williams D. Duvigneaud Duke Energy D. Westcott B. Wunderly J. Elnitsky T. Hobbs P. Dixon Transnuclear, Inc.

K. Tavassoli Enclosure

Package ML13253A214 Meeting Notice: ML13225A199 Summary: ML13253A216 NRC-001 I LPLII-2JP_M_ _-+I_LP_L_II_-2~_/L_A_ _ _---tI-=LP_Ll_I-2_I_BC_{A_}

I

1 OFFICE NAME DATE I CGratton
09/11/13 i BClayton i 09/11/13 DBroaddus 09/12/13

___-r-I -=LP-:::-L_"_-2_/P_M_--11 I CGratton i 09/12/13

~