Summary of Meeting with Crystal River Nuclear Plant to Discuss Overall Crystal River 3 Plant Status
ML032760051
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 10/02/2003
From: Joel Munday
NRC/RGN-II/DRP/RPB3
To: Young D
Florida Power Corp
Shared Package
ML032760047 List:
References
Download: ML032760051 (4)


Text

October 2, 2003 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing &

Regulatory Programs 15760 West Power Line Street Crystal River, FL 34428-6708

SUBJECT:

PUBLIC MEETING

SUMMARY

- CATEGORY ONE PLANT STATUS MEETING CRYSTAL RIVER NUCLEAR PLANT, DOCKET NO. 50-302

Dear Mr. Young:

This refers to the meeting conducted at your request at the Region II Office in Atlanta, Georgia on September 19, 2003. The purpose of the meeting was to discuss overall Crystal River 3 plant status. Enclosed are a list of attendees and the presentation handout.

The discussions focused on the following topics: Plant Performance and Outage Status, Major Projects and Initiatives, Security Update and Order Response Status, and Future Initiatives.

The meeting was informative and did not result in any specific action items or decisions.

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 562-4560.

Sincerely,

/RA/

Joel T. Munday, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket No. 50-302 License No. DPR-72

Enclosures:

1. List of Attendees
2. Handout - Crystal River Unit 3 Update cc w/encls: (See page 2)

FPC 2 cc w/encls:

Daniel L. Roderick Chairman Director Site Operations Board of County Commissioners Crystal River Nuclear Plant (NA2C) Citrus County Electronic Mail Distribution 110 N. Apopka Avenue Inverness, FL 36250 Jon A. Franke Plant General Manager Jim Mallay Crystal River Nuclear Plant (NA2C) Framatome Technologies Electronic Mail Distribution Electronic Mail Distribution Richard L. Warden Distribution w/encls: (See page 3)

Manager Nuclear Assessment Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution Donald L. Taylor Manager Support Services Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, FL 34428-6708 R. Alexander Glenn Associate General Counsel (MAC - BT15A)

Florida Power Corporation Electronic Mail Distribution Steven R. Carr Associate General Counsel - Legal Dept.

Progress Energy Service Company, LLC Electronic Mail Distribution Attorney General Department of Legal Affairs The Capitol Tallahassee, FL 32304 William A. Passetti Bureau of Radiation Control Department of Health Electronic Mail Distribution Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs Electronic Mail Distribution

FPC 3 Distribution w/encls:

B. Mozafari, NRR RIDSNRRDIPMLIPB PUBLIC OFFICE DRP/RII SIGNATURE sn NAME SNinh:vyg DATE 10/2/2003 E-MAIL COPY? YES NO PUBLIC DOCUMENT YES NO OFFICIAL RECORD COPY DOCUMENT NAME: C:\ORPCheckout\FileNET\ML032760051.wpd

LIST OF ATTENDEES Nuclear Regulatory Commission L. Reyes, Regional Administrator, Region II (RII)

V. McCree, Director, Division of Reactor Projects (DRP), RII C. Casto, Director, Division of Reactor Safety (DRS), RII M. Lesser, Chief, Engineering Branch 2, DRS, RII S. Ninh, Senior Project Engineer, DRP, RII Progress Energy/Florida Power Corporation D. Young, Site Vice President, Crystal River (CR3)

J. Franke, Plant General Manager, CR3 J. Terry, Engineering Manager, CR3 D. Taylor, Site Support Manager, CR3 S. Young, Security Superintendent, CR3 R. Bright, Licensing Engineer, CR3 Enclosure 1