Memo - Completion of ROP Baseline Inspections for Extended Shutdown of Crystal River in Calendar Yr. 2010
ML102170331
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 08/05/2010
From: Wert L
Division Reactor Projects II
To: Frederick Brown
Division of Inspection and Regional Support
References
Download: ML102170331 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 August 5, 2010 MEMORANDRUM TO: Frederick D. Brown, Director Division of Inspection and Regional Support Office of Nuclear Reactor Regulation FROM: Leonard D. Wert, Jr., Director /RA/

Division of Reactor Projects

SUBJECT:

COMPLETION OF REACTOR OVERSIGHT PROGRAM (ROP)

BASELINE INSPECTIONS FOR THE EXTENDED SHUTDOWN OF CRYSTAL RIVER UNIT 3 IN THE CALENDAR YEAR 2010.

Crystal River Unit 3 was shutdown on September 26, 2009, for a scheduled steam generator (SG) replacement refueling outage (R16). SG replacement activities were completed in January 2010. However, the unit remained shut down and defueled in order to repair damage to the containment found during creation of the temporary containment opening. Containment repairs are currently scheduled to be completed in the third quarter of 2010, but the repair schedule has experienced significant delays in the past six months, and may experience additional delays in the future. As a result, due to the extended No Mode condition, with all fuel off loaded to the spent fuel pool, there will be a limited number of available samples and opportunities to apply several ROP baseline inspection procedures (IP) in calendar year 2010. However, Region II has determined that the objectives of the ROP baseline inspection program will be met for Crystal River Unit 3 in 2010.

In accordance with Manual Chapter 2515, Approval by the Director, Division of Inspection &

Regional Support (DIRS), NRR, is required when the inspection requirements in an inspectable area cannot be met. Manual Chapter 2515 also states, The sample size may be reduced to a number below the minimum value in situations where there are an insufficient number of samples with appropriate risk significance available for inspection (e.g., a reduction of sample size to zero, if necessary, when no samples exist).

The enclosed table specifies the inspection procedures for which the minimum number of inspection samples, will very likely not be completed in CY 2010 because of a reduced number of risk significant samples and/or there were no opportunities to apply the procedure. The remainder of the ROP baseline inspections is expected to be fully completed. Additionally, during CY 2010, team inspections have been completed in Operator Licensing (IP 71111.11B),

Problem Identification and Resolution (IP 71152B), and Component Design Bases Inspection (IP 71111.21). Also, a Special Inspection is in progress to review the causes and corrective actions related to structural flaws in the containment building. Finally, the Steam Generator Replacement Inspection (IP 50001), which includes inspection of repairs to the temporary containment opening is ongoing.

CONTACT: Daniel W. Rich RII/DRP 404-997-4721

F. Brown 2 The substantial effort devoted to these inspections and resultant thorough review of various aspects of the licensees engineering, training, maintenance, and corrective actions programs provides confidence that the intent of the ROP baseline has been completed. This confidence, and the allowance by Manual Chapter 2515 to reduce baseline inspection sample sizes below the minimum when required, leads Region II to conclude that the objectives of the 2010 ROP Baseline Inspection Program will be met for Crystal River Unit 3.

Should you have any questions please contact Dan Rich, Chief, Reactor Projects Branch 3, at 404-997-4721.

Enclosure:

(As stated) cc w/encl.

Luis A. Reyes, Regional Administrator Victor M. McCree, Deputy Regional Administrator Kriss M. Kennedy, Director, DRS Harold O. Christensen, Deputy Director, DRS Leonard D. Wert, Jr., Director, DRP Joel T. Munday, Deputy Director, DRP Farideh E. Saba, Crystal River 3, Senior Project Manager, NRR Nathan Sanfilippo, Executive Technical Assistant, EDO

___ML102170331___________ X SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP RII:DRS RII:DRP SIGNATURE PCH1 TXM1 DWR1 HOC LXW1 NAME PHiggins TMorrissey DRich HChristensen LWert DATE 07/19/2010 07/14/2010 07/28/2010 0728/2010 08/05/2010 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO TABLE 1 CRYSTAL RIVER UNIT 3---1 UNIT SITE Inspection Procedure Samples Complete No. Title/ (Revision Date) Min. Sample Frequency (Range) Req=d Min. Q1 Q2 Q3 Q4 Total The minimum 7111112Q Maint Rule Implementation Maint Eff. Issues = 8-10/yr Req Min = 8/yr; sample size was 2 2 (11/16/2009) (a)(3) evaluation can count as one sample not available during the inspection cycle The opportunity to 7111113 Maint. Risk Asmts & Work Eval apply the procedure Maint. Activities 24/yr Req Min = 14/yr 0 0 (11/16/2009) was not available during the inspection cycle The minimum Operability Evaluations Reviews 21/yr Req. Min - 15 yr 2 1 sample size was 7111115 (11/16/2009) not available during the inspection cycle For temporary 7111118 Plant Modifications Temporary 3 Minimum 0 0 mods only, the (10/31/2008) Mods 5/yr opportunity to apply 1 1 the procedure was Permanent Req. Min = 1/yr not available during Mods - Occurred (1-2/yr) the inspection cycle For the RCS leak

  • 7111122 Surveillance Testing Tests -(18-26/yr)2 rate sample only, (02/27/2008) IST (1/Q) Req Min = 18/yr the opportunity to CIV (1-2/Cycle) See note on IST / 4* 5* apply the procedure RCS Leak (1-3/yr) contmt isol valve was not available during the inspection cycle
  • No RCS leakrate samples will be completed. All IST and CIV samples will be completed.

Inspection Procedure Samples Complete No. Title/ (Revision Date) Min. Sample Frequency (Range) Req=d Min. Q1 Q2 Q3 Q4 Total 71151 Performance Indicator Verification Verifies - 11/yr (DRP Assigned)

(06/28/2007) 1st scram, scram with complications, Several PIs will not unplanned power changes (3) have a full years 11 3* 2*

2nd RCS leakage and Activity (2) date available to 3rd SSFF (1) review 4th MSPI (5)

For the OWA 71152 PI&R (ID & Resolution of Problems) Focused Reviews 7/yr3, one OWA 4 1 2 sample only, the (01/10/2008) opportunity to apply the procedure was not available during the inspection cycle 2 semiannual trend 2 1

  • RCS leakage or activity, unplanned scrams, unplanned power changes will not have a full years data available to review.

2 IP 71111.22 requires 18-26 samples/year. Quarterly sample to include 1 Inservice Test activity. Once per refueling cycle select 1-2 containment isolation valves in the sample.

3 IP 71152 is now the Resident portion of this procedure. IP 71152B has become the team portion of this procedure.

2