Summary of Public Regulatory Conference Meeting with Progress Energy Regarding Risk Significance of the Inspection Finding Documented in Inspection Report No. 05000302/2005007 for Crystal River Unit 3
ML052210242
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 08/04/2005
From: Payne D
NRC/RGN-II
To: Young D
Progress Energy Florida
References
IR-05-007
Download: ML052210242 (4)


Text

August 4, 2005

SUBJECT:

PUBLIC MEETING SUMMARY - CATEGORY ONE REGULATORY CONFERENCE MEETING-CRYSTAL RIVER NUCLEAR PLANT, DOCKET NO. 50-302

Dear Mr. Young:

This refers to the meeting conducted at your request at the Region II Office in Atlanta, Georgia on July 22, 2005. The purpose of the Regulatory Conference was to discuss the risk significance of the inspection finding documented in Inspection Report No. 05000302/2005007.

This finding involved unprotected post-fire safes shutdown cables and related non-feasible local manual operator action, and was preliminarily characterized as greater than very low safety significance (Green) finding. Enclosed are a list of attendees and the presentation handout.

Your staff presented an overview of recent NRC Triennial Fire Protection Inspection findings at your facility, root causes, and corrective actions. Additionally, your staff provided information regarding the plant response to a postulated fire scenario and a Probabilistic Safety Assessment. The meeting was informative and did not result in any decisions. However, you agreed to provide NRC with additional information and assessment regarding this issue. NRC will review the information and will inform you with results of our assessment.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 562-4669.

Sincerely,

/RA/

D. Charles Payne, Chief Engineering Branch 2 Division of Reactor Safety Docket No.: 50-302 License No.: DPR-7

FPC

Enclosures:

1. List of Attendees 2. Handout - Crystal River Unit 3 cc w/encls:

Daniel L. Roderick Director Site Operations Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution Jon A. Franke Plant General Manager Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution Terry D. Hobbs Manager Nuclear Assessment Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution Michael J. Annacone Engineering Manager Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution R. Alexander Glenn Associate General Counsel (MAC - BT15A)

Florida Power Corporation Electronic Mail Distribution Steven R. Carr Associate General Counsel - Legal Dept.

Progress Energy Service Company, LLC Electronic Mail Distribution Attorney General Department of Legal Affairs The Capitol Tallahassee, FL 32304 William A. Passetti Bureau of Radiation Control Department of Health Electronic Mail Distribution Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs Electronic Mail Distribution Chairman Board of County Commissioners Citrus County 110 N. Apopka Avenue Inverness, FL 36250 Jim Mallay Framatome Technologies Electronic Mail Distribution

_________________________

OFFICE RII:DRS SIGNATURE R.Rodriguez NAME

/RA//

DATE 8/4/2005 8/ /2005 8/ /2005 8/ /2005 8/ /2005 8/ /2005 8/ /2005 E-MAIL COPY?

YES YES NO YES NO YES NO YES NO YES NO YES NO

End LIST OF ATTENDEES Nuclear Regulatory Commission V. McCree, Director, Division of Reactor Safety (DRS), Region II (RII)

J. Munday, Chief, Reactor Project Branch 3, Division of Reactor Projects (DRP), RII C. Payne, Chief, Engineering Branch 2 (EB2), DRS, RII W. Rogers, Senior Reactor Analyst, EB 2, DRS, RII R. Rodiguez, Reactor Inspector, EB 2, DRS, RII C. Evan, Regional Counsel/Enforcement Officer, Enforcement and Investigations Coordination Staff (EICS), RII S. Sparks, Senior Enforcement Specialist, EICS, RII R. Schin, Senior Reactor Inspector, EB2, DRS, RII **

M. Maymi, Reactor Inspector, Maintenance Branch, DRS, RII D. Mas-Penaranda, Reactor Inspector, Engineering Branch 1, DRS, RII G. Cameron, Fire Protection Co-Op, EB2, DRS, RII T. Harrison, Fire Protection Co-Op, EB2, DRS, RII E. Brown, Project Manager, Office of Nuclear Reactor Regulation (NRR), Headquarters (HQ) *

D. Starkey, Enforcement Specialist, Office of Enforcement, HQ *

R. Galluci, Fire Protection Engineer, NRR, HQ *

A. Klein, Fire Protection Engineer, NRR, HQ *

P. Koltay, Program Manager, NRR, HQ *

C. Cahill, Risk Analyst, NRR, HQ **

Video conference

Telephone conference Progress Energy/Florida Power Corporation D. Young, Site Vice President, Crystal River (CR3)

M. Annacone, Engineering Manager, CR3 D. Porter, Superintendent, Shift Operations, CR3 S. Karkofski, Electrical Design Engineering Supervisor, CR3 D. Miskiewicz, Lead PSA Engineer, CR3 S. Powell, Licensing Supervisor, CR3 Members of Public Y.Kim, NRC visitor from Korean Bob Dukes, Nisys Corporation