ML21060B020

From kanterella
Jump to navigation Jump to search
Memo to File: Final Environmental Assessment and Finding of No Significant Impact for Initial and Updated Decommissioning Funding Plans for Crystal River ISFSI
ML21060B020
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/31/2021
From: Yen-Ju Chen
Storage and Transportation Licensing Branch
To:
JChen - NMSS/DFM/STL - 301.415.1018
Shared Package
ML21060B019 List:
References
Download: ML21060B020 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 31, 2021 MEMORANDUM TO: File FROM:

Yen-Ju Chen, Senior Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards

SUBJECT:

FINAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT FOR THE DUKE ENERGY FLORIDA, LLCS INITIAL DECOMMISSIONING FUNDING PLAN SUBMITTED IN ACCORDANCE WITH 10 CFR 72.30 FOR CRYSTAL RIVER INDEPENDENT SPENT FUEL STORAGE INSTALLATION The subject document related to the Crystal River Unit 3 Nuclear Generating Plant Independent Spent Fuel Storage Installation decommissioning funding plan submission for 2017 was approved this date and is attached for record purposes.

Docket No.: 72-1035 License No.: SFGL-64

Enclosure:

Final Environmental Assessment and Finding of No Significant Impacts for the Duke Energy Florida, LLCs Initial Decommissioning Funding Plans Submitted in Accordance with 10 CFR 72.30(b) for Crystal River Unit 3 Nuclear Plant Independent Spent Fuel Storage Installation (ADAMS Accession No. ML21060B021)

Yen-Ju Chen Digitally signed by Yen-Ju Chen Date: 2021.03.31 10:47:09 -04'00'

ML21060B019 (Pkg)

ML21060B020 (Memo)

ML21060B021 (Encl)

  • concurrence via email OFFICE DFM DFM OGC/NLO DFM NAME YChen*

WWheatley*

NMertz*

BWhite* for JMcKirgan DATE 3/2/2021 3/4/2021 3/16/2021 3/31/2021