MONTHYEARML12305A2752012-11-0101 November 2012 11/1/12 Meeting Presentation - Regarding GSI-191 Strainer Fiber Bypass Test Plan on November 1, 2012 for Crystal River 3 Generating Plant Project stage: Request ML12307A1282012-11-20020 November 2012 11/1/12 Summary of Meeting with Duke Energy Concerning Generic Letter 2004-02 and NRC Staff Review of Draft Proposed Strainer Fiber Bypass Plan for Crystal River Unit 3 Generating Plant Project stage: Draft Approval 2012-11-01
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML19323F8262019-11-20020 November 2019 NEIMA Meeting Summary ML14034A0262014-04-0303 April 2014 1/16/2014 Summary of Meeting in Crystal River, Fl, to Discuss and Accept Public Comments Related to the Crystal River, Unit 3 Nuclear Generating Station Post-Shutdown Decommissioning Activities Report ML13253A2162013-09-12012 September 2013 Summary of Meeting with Duke Energy to Discuss Decommissioning Submittals for Crystal River Unit 3 Nuclear Generating Plant ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13134A1732013-05-13013 May 2013 Public Meeting Summary - Category 3 - Annual Assessment Meeting - Crystal River Unit 3 Nuclear Plant ML12307A1282012-11-20020 November 2012 11/1/12 Summary of Meeting with Duke Energy Concerning Generic Letter 2004-02 and NRC Staff Review of Draft Proposed Strainer Fiber Bypass Plan for Crystal River Unit 3 Generating Plant ML12184A1382012-07-0202 July 2012 Public Meeting Summary of Category 3 - Annual Assessment Meeting Crystal River 2011 Annual Assessment Meeting Summary ML11314A2552011-11-10010 November 2011 Summary of Pubic Meeting with Crystal River Nuclear Plant Docket No. 50-302 ML11187A1902011-07-18018 July 2011 Summary of Public Meetings Conducted to Discuss the Dseis Related to the Review of the Crystal River 3 Nuclear Generating Plant License Renewal Application ML1116400552011-06-13013 June 2011 Summary of Category 3 Public Meeting, Annual Assessment for Crystal River Nuclear Plant ML11123A0472011-05-12012 May 2011 April 21, 2011, Summary of Public Meeting with Progress Energy on Their Final Pre-Application for Extended Power Uprate ML11116A0202011-05-12012 May 2011 April 12, 2011, Summary of Pre-Application Meeting with Carolina Power & Light Company and Florida Power Corporation, on Brunswick, Units 1 & 2, Crystal River, Unit 3, and H. B. Robinson, Unit 2 ML1034806342010-12-16016 December 2010 Summary of Meeting with Florida Power Corporation Regarding Crystal River'S Proposed License Amendment Request to Support the Independent Spent Fuel Storage Facility Project ML1027100652010-10-19019 October 2010 09/27/10 Summary of Telephone Conference Call Held Between NRC and Florida Power Corp., Concerning Draft Request for Information Related to Crystal River, Unit 3, License Renewal Application ML1025903962010-09-15015 September 2010 Summary of Public Meeting - Special Inspection Results Crystal River Nuclear Plant ML1023804682010-08-26026 August 2010 08/18/10 Summary of Meeting NRC Initial Exam Writer'S Workshop ML1022802912010-08-25025 August 2010 July 15, 2010, Summary of Conference Call with Florida Power Corporation on Nrc'S Preliminary Review of Florida Power Corporation'S 10 CFR 50.59 Evaluation ML1020903352010-08-17017 August 2010 Summary of June 30, 2010, Meeting with Progress Energy, on Containment Investigation and Repair Activities at Crystal River, Unit 3 ML1016803832010-06-25025 June 2010 Summary of Public Meeting with Progress Energy to Discuss Their Proposed Digital Modifications in Support of Fast Cooldown System for Extended Power Uprate ML1013200292010-05-12012 May 2010 Public Meeting Summary - Category 3 Open House Annual Performance Assessment Mtg. - Crystal River ML1000900502010-03-0101 March 2010 Summary of Telephone Conference Call Held on November 11, 2009, Between the U.S. NRC and Florida Power Corporation, Concerning a Draft RAI and the Applicant'S Response to a RAI Pertaining to the Crystal River Unit 3 Nuclear Generating Plant ML1003200362010-02-19019 February 2010 Summary of Telephone Conference Call Held on December 23, 2009, Between the U.S. NRC and Florida Power Corporation, Concerning Applicant'S Response to a RAI Pertaining to the Crystal River Unit 3 Nuclear Generating Plant License Renewal.. ML1001415932010-02-16016 February 2010 Summary of Tele Conference Call Held on 12/1/09, Btw the USNRC and Florida Power Corp, Concerning Licensee Response to a RAI Pertaining to the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application ML1000703172010-02-0202 February 2010 Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Florida Power Corporation, Concerning the Applicant'S Response to a Request for Additional Information Pertaining to the Crystal River, Unit 3 ML0934513952010-01-0404 January 2010 Summary of Telephone Conference Call on 10/29/09, Between the USNRC and Florida Power Corporation, Concerning Licensee Response to a Request for Information Related to the Crystal River Unit 3 Nuclear Generating Plant License Renewal Applic ML0933602292009-12-0404 December 2009 Summary of Meeting with Progress Energy on Crystal River Unit 3 Containment Building Concrete Delamination ML0932900342009-12-0303 December 2009 10/28/09 Summary of Telephone Conference Call Held, Between NRC and Florida Power Corp., Concerning License Response to a Request for Additional Information Related Pertaining to Crystal River ,Unit 3 License Renewal Application ML1020402762009-10-0808 October 2009 Email from Khanna, Meena to Grobe, Jack; Hiland, Patrick; Skeen, David; Subject: Summary of Meeting with Chairman Jaczko - Crystal River 3 Containment Delamination Issue ML1020402722009-10-0808 October 2009 Meeting Summary of Meeting with Chairman Jaczko on Delamination of Containment Domes ML0923803922009-08-26026 August 2009 08/11-12/2009-Summary of Meeting Re 2009 Us NRC Initial Exam Development Workshop ML0923100052009-08-19019 August 2009 Public Meeting Summary - License Renewal Inspection Results Crystal River Nuclear Plant ML0914903142009-05-29029 May 2009 Carolina Power and Light, May 22, 2009, Public Meeting Summary Regarding Brunswick Steam Electric Plant Performance and Organizational Alignment within the Company ML0913201652009-05-12012 May 2009 Summary of Category 3 Public/Open House Meeting with Crystal River to Discuss Annual Assessment ML0830800032008-10-31031 October 2008 Summary of Public Meeting with Carolina Power and Light and Florida Power Corporation Regarding Organizational Alignment within the Company ML0805001632008-02-15015 February 2008 Summary of September 14, 2007, Meeting with Progress Energy Florida, Inc, to Discuss Power Uprates at Crystal River Unit 3 ML0720005322007-07-20020 July 2007 04/23/2007 Summary of Meeting with Florida Power Corporation Regarding Planned Changes to Crystal River Nuclear Plant, Unit 3 Discuss the Licensee'S Plans for Power Uprates and Their Integration with License Renewal, Steam Generator Replace ML0711601882007-04-25025 April 2007 04/18/2007 Meeting Summary Category One Annual Assessment Meeting ML0621305672006-08-0101 August 2006 Summary of 07/19 - 07/20/2006 Meeting - 2006 Initial Exam Development Workshop ML0613501262006-05-30030 May 2006 Summary of Conference Calls with Florida Power Corporation Regarding the Fall 2005 Steam Generator Inspection IR 05000302/20050072005-08-0404 August 2005 Summary of Public Regulatory Conference Meeting with Progress Energy Regarding Risk Significance of the Inspection Finding Documented in Inspection Report No. 05000302/2005007 for Crystal River Unit 3 ML0505402162005-03-0303 March 2005 Summary of Meeting with Progress Energy (Brunswick, Harris, Robinson & Crystal River) Regarding Fire Protection Initiatives ML0502101312005-01-17017 January 2005 11/09-10/2004 Summary of Meeting with B&W Owners Group Re Replacement for BAW-2374, Revision 1, Evaluation of OTSG Thermal Loads During Hot Leg LOCA ML0421600772004-08-0202 August 2004 Summary of 07/28/2004 Public Meeting with NRC to Discuss Performance of Progress Energy Nuclear Facilities ML0404802242004-02-17017 February 2004 Letter, Summary of Conference Call, with Florida Power Corp Fall 2003 Steam Generator Inspection ML0403404782004-02-0303 February 2004 Meeting Summary with Progress Energy and NRC to Discuss Fire Protection Initiatives ML0327600512003-10-0202 October 2003 Summary of Meeting with Crystal River Nuclear Plant to Discuss Overall Crystal River 3 Plant Status ML0323805792003-09-16016 September 2003 Summary of Meeting with Florida Power Corp Regarding Fuel Design Changes Planned for Fall 2003 Refueling, Crystal River, Unit No. 3 ML0228000922002-10-0101 October 2002 Closed Meeting Summary - Security Issues at Brunswick, Crystal River, Shearon Harris & H.B. Robinson Plants ML0213601452002-05-16016 May 2002 Training Managers Conference Meeting Summary of 04/25 - 26/02 2019-11-20
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 20, 2012 LICENSEE: Florida Power Corporation FACILITY: Crystal River, Unit 3
SUBJECT:
SUMMARY
OF NOVEMBER 1, 2012, MEETING WITH DUKE ENERGY CONCERNING GENERIC LETTER 2004-02 AND NRC STAFF REVIEW OF DRAFT PROPOSED STRAINER FIBER BYPASS TEST PLAN FOR CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT (TAC NO. MC4678)
On November 1,2012, the Nuclear Regulatory Commission (NRC) staff conducted a Category 1 public meeting via a conference call with Duke Energy, Inc., which is representing Florida Power Corporation (the licensee), including its contractors Enercon and Alion, at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockvi"e, Maryland. The purpose of the meeting was for Duke Energy to present its proposed strainer fiber bypass test plan for Crystal River Unit 3 regarding Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors." The purpose of the meeting was also for the NRC staff to provide the licensee with questions and comments during the meeting. The meeting notice was publicly available on the NRC's website and is documented in Agencywide Document Access and Management System (ADAMS)
Accession No. ML12285A312. The list of participants for this call is provided in the enclosure to the meeting summary.
The licensee's draft bypass fiber quantity test plan that was provided to the NRC staff by an electronic mail (e-mail) is documented in ADAMS Accession No. ML12296A392. The NRC staff's questions/talking points were provided to the licensee via an email. Prior to the meeting the licensee provided its presentation slides that included the NRC staff's questions and the licensee's responses. The presentation slides are documented in ADAMS Access No, ML12305A275, The intent of the strainer bypass test is to measure the amount of fibrous debris that bypasses or passes through an emergency core cooling system sump strainer module. The fibrous material used in the testing is representative of debris that could be generated during a loss-of-coolant accident. The results of the testing will be used to quantify the amount of debris that could bypass a plant strainer to assist in evaluation of the response of equipment downstream of the strainer. During the conference call, the licensee presented the generic safety issue 191 project status, bypass test configuration, bypass test procedure, procedures for debris preparation and introduction, bypass test procedure acceptance criteria, and bypass test schedule, This presentation was followed by discussing the NRC staff's questions and the licensee's responses, For details, refer to the presentation slides in ADAMS. During the conference call, the NRC staff discussed its overall expectation of the test results. No action item was identified at the conclusion of this meeting.
- 2 The NRC staff expects the test to produce results that are realistic or conservative when compared to actual plant strainer bypass. However, the test results are somewhat dependent on human actions and evaluations of the test results after the testing is complete. Therefore, while the NRC staff does not have any questions or additional comments regarding the draft strainer fiber bypass test plan for Crystal River Unit 3, the NRC staff does not endorse this test plan.
The licensee is planning to finalize its draft strainer bypass test plan by mid November and submit it to the NRC by an officialletler. Also, the bypass test is currently schedule for the week of November 26, 2012 at Alion's test facility in Warrenville, Illinois. The NRC staff may observe the strainer bypass testing and review its evaluation and application as part of its overall review of Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors."
Members of the public were invited and in attendance. Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-1447 or Farideh.Saba@nrc.gov.
Farideh Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-302
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
LIST OF A TIENDEES U. S. NUCLEAR REGULATORY COMMISSION PUBLIC MEETING WITH DUKE ENERGY REGARDING DRAFT PROPOSED STRAINER FIBER BYPASS TEST PLAN FOR CRYSTAL RIVER UNIT 3 NOVEMBER 1! 2012 U. S. NUCLEAR REGULATORY COMMISSION S. Bailey S. Smith F.Saba DUKE ENERGY C. Miller W. McGoun B. Wunderly S. McDaniel D. Westcott D. Phillips ENERCON K. Walker Crabtree G. Zigler J. Caldwell ALiON T. Sandy J. Poska M. Jursich PUBLIC P. Grissom, Southern Nuclear Operating Company (SNC)
J. Nevin, SNC G. Miller, Dominion Resources Services, Inc. (Dominion)
G. Nayler, Dominion Enclosure
Package ML12307A127
. ML12285A312 Notice SII'd es M L12305A275 Summary ML12307A128 OFFICE LPL2-2/PM LPL2-21LA SSIB/BC LPL2-?/BC(A) LPL2-2/PM NAME FSaba BTuily SBailey JPoole for JQuichocho FSaba DATE 11/8/12 11/7112 11/8/12 11/19/12 11/20/12