April 12, 2011, Summary of Pre-Application Meeting with Carolina Power & Light Company and Florida Power Corporation, on Brunswick, Units 1 & 2, Crystal River, Unit 3, and H. B. Robinson, Unit 2ML11116A020 |
Person / Time |
---|
Site: |
Harris, Brunswick, Crystal River, Robinson |
---|
Issue date: |
05/12/2011 |
---|
From: |
Farideh Saba Plant Licensing Branch II |
---|
To: |
|
---|
Saba F |
Shared Package |
---|
ML11116A016 |
List: |
---|
References |
---|
Download: ML11116A020 (5) |
|
|
---|
Category:Meeting Summary
MONTHYEARML24165A2362024-06-21021 June 2024 Duke Robinson Technical Report 5-22-24 Public Meeting Summary ML24124A0342024-05-0101 May 2024 Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24011A1652024-02-12012 February 2024 December 11, 2023, Summary of Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant, Unit 1 Planned Exemption Request Related to Turbine Control System and Reactor Protection System Circuitry ML23129A0012023-06-26026 June 2023 May 2, 2023, Summary of Meeting Duke Energy to Discuss an H. B. Robinson Steam Electric Plant, Unit No. 2 License Amendment Request to Add Feedwater Isolation on Steam Generator Level High-High ML23157A3202023-06-26026 June 2023 Summary of April 26, 2023, Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant, Unit 1 Planned License Amendment Request Related to Turbine Control System and Reactor Protection System Circuitry ML23151A2532023-05-31031 May 2023 Meeting Summary of 2022 Annual Assessment Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324, Meeting Number 20230392 ML23151A1232023-05-31031 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Shearon Harris Nuclear Plant ML22262A2882022-10-0303 October 2022 Summary of September 14, 2022, Observation Public Meeting with Duke Energy Progress, LLC to Discuss a Planned TSTF-577, Rev. 1, License Amendment Request Supplement for H. B. Robinson Steam Electric Plant, Unit No. 2 ML22174A2872022-07-14014 July 2022 Summary of Pre-Submittal Meeting with Duke Energy Progress, LLC to Discuss a Potential License Amendment Request Proposed Technical Specification 3.3.2 for the H. B. Robinson Steam Electric Plant, Unit No. 2 ML22166A0182022-07-0707 July 2022 Summary of June 13, 2022, Closed Meeting with Duke Energy Progress, Llc to Discuss Licensee Responses Provided to a Request for Additional Information Associated with a License Amendment Request to Adopt Technical Specifications Task Force ML22167A1852022-06-30030 June 2022 Summary of June 6, 2022, Meeting with Duke Energy to Discuss Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI) 191 ML22131A3802022-05-12012 May 2022 Public Meeting Summary - 2021 Annual Assessment Meeting Regarding the H. B. Robinson Steam Electric Plant, Docket No. 50-261, Meeting Number 20210460 ML22129A0062022-05-10010 May 2022 Summary of April 20, 2022, Meeting with Duke Energy Progress, LLC, to Discuss Proposed License Amendment Request to Revise Reactor Coolant System Pressure Isolation Valve Operational Leakage Surveillance Requirement Frequency (L-2022-LRM 00 ML22130A0302022-05-0909 May 2022 Summary of Public Meeting on 2021 Annual Assessment Meeting Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324; and Shearon Harris Nuclear Power Plant, Docket No. 50-400, Meeting Number 20220350 ML22091A2692022-04-19019 April 2022 Summary of March 30, 2022, Pre-Submittal Meeting with Duke Energy Progress, LLC to Discuss a Potential License Amendment Request Surveillance Requirements 3.8.1.16 for H. B. Robinson Steam Electric Plant, Unit 2 ML21341A5542021-12-29029 December 2021 Summary of November 29, 2021, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Planned License Amendment Request to Relocate ML21172A2672021-08-13013 August 2021 Regulatory Audit Summary Related to the Review of LAR to Revise 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors, Categorization Process to Reflect an Alternative Seis ML21182A2202021-07-0909 July 2021 Summary of June 24, 2021, Meeting with Duke Energy Progress, LLC, Regarding a Proposed Amendment Concerning TSTF-577, Revised Frequencies for Steam Generator Frequencies for Steam Generator Tube Inspections, for the H. B. Robinson Steam Ele ML21131A1472021-05-11011 May 2021 Public Meeting Summary 2020 Annual Assessment Meeting Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324; and Shearon Harris Nuclear Power Plant, Docket No. 50-400, Meeting Number 20210385 ML21057A1172021-04-0101 April 2021 February 17, 2021 Summary of Public Meeting with Duke Energy Progress, LLC, to Discuss a Proposed License Amendment Request to Adopt TSTF-505 Risk-Informed Extended Completion Time ML21068A4172021-03-17017 March 2021 Summary of Meeting with Duke Energy Progress, LLC, Regarding a Proposed Relief Request Concerning Containment Inspections of Liners and Moisture Barriers for the H. B. Robinson Steam Electric Plant, Unit 2 ML21036A3112021-03-0303 March 2021 Summary of February 3, 2021, Public Meeting with Duke Energy Progress, LLC, to Discuss a Proposed LAR to Change the Standby Liquid Control System Technical Specifications for Brunswick Steam Electric Plant, Units 1 and 2 ML21028A6762021-02-24024 February 2021 Summary of January 21, 2021, Closed Meeting with Duke Energy Progress, LLC, to Discuss a Proposed Relief Request Related to Service Water Underground Piping Coating for Brunswick Steam Electric Plant ML20141L6282020-05-20020 May 2020 EOC Meeting Summary ML20136A2222020-05-15015 May 2020 Har - Bru 2019 Aam Meeting Summary ML19331A8062020-01-29029 January 2020 Summary of November 13, 2019 Closed Meeting with Duke Energy Carolinas, LLC and Duke Energy Progress, LLC, to Discuss Security-Related Information for Its Licensed Facilities ML19329A0232019-11-27027 November 2019 Summary of October 29, 2019 Conference Call with Duke Energy Progress, LLC Regarding the Fall 2019 Steam Generator Tube Inspections ML19323F8262019-11-20020 November 2019 NEIMA Meeting Summary ML19241A2902019-09-24024 September 2019 Summary of August 22, 2019, Meeting with Duke Energy Progress, LLC Proposed License Amendment Request to Adopt Risk-Informed Completion Times ML19220A6702019-08-26026 August 2019 Summary of August 7, 2019, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Proposed License Amendment Request for a Common Emergency Plan ML19113A0652019-05-14014 May 2019 Summary of Meeting with Duke Energy to Discuss Proposed License Amendment Request for Shearon Harris, Unit 1, Technical Specification Changes Associated with Departure from Nucleate Boiling Ratio Safety Limit ML19120A1342019-05-0606 May 2019 3/15/19 Summary of Public Meeting with Nuclear Entergy Institute, Duke Energy, and Southern Nuclear Operating Company Post-Pilot Implementation of Tornado Missile Risk Evaluator Methodology at Vogtle, Units 1 and 2 and Shearon Harris, Unit ML19123A3532019-05-0202 May 2019 Public Meeting Summary - Brunswick Steam Electric Plant, Docket Nos. 05000325 and 05000324 ML19123A3522019-05-0202 May 2019 Public Meeting Summary - Shearon Harris Nuclear Plant, Docket No. 50-400 ML19123A1592019-05-0101 May 2019 Summary of Public Meeting with H. B. Robinson Steam Electric Plant, to Provide Opportunities to Discuss the Annual Assessment of the H.B Robison Steam Electric Plant with the Public for Period of January 1, 2018 - December 31, 2018 ML19087A0622019-04-11011 April 2019 Summary of March 25, 2019, Public Teleconference with Duke Energy to Discuss the Request for Additional Information Response Regarding the Proposed Alternative to the Depth Sizing Qualification Requirement (Duke Energy Fleet Relief Request ML18352A3572019-01-0808 January 2019 Summary of Meeting with Duke Energy Progress, LLC to Discuss Proposed License Amendment Request for Shearon Harris Nuclear Power Plant, Unit 1, Regarding Emergency Plan Changes ML18361A6712019-01-0808 January 2019 Summary of Meeting with Duke Energy Progress, LLC to Discuss License Amendment Request for Shearon Harris Unit 1, Regarding 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, ML18355A8142019-01-0707 January 2019 Summary of December 20, 2018, Teleconference Meeting with Duke Energy Progress, LLC to Discuss a Proposed License Amendment Request for Shearon Harris Unit 1, Regarding a Risk-Informed Essential Services Chilled Water System TS ML18094A2632018-08-17017 August 2018 Summary of 01/18/2018, Public Meeting with Nuclear Energy Institute, Duke Energy, Southern Nuclear Operating Co., Entergy Operations, Inc. to Discuss Development of Tornado Missile Risk Evaluator Methodology ML18144A0632018-05-24024 May 2018 Summary of Meeting Concerning Annual Assessment of H.B. Robinson Steam Electric Plant Unit 2 for Period of January 1, 2017 - December 31, 2017 ML18109A0912018-04-19019 April 2018 Summary of 2017 Annual Assessment Public Meeting Regarding Shearon Harris Nuclear Plant, Docket No. 50-400 ML18088A0732018-04-0303 April 2018 March 27, 2018, Summary of Presubmittal Meeting with Duke Energy Progress, LLC to Discuss a Proposed Relief Request for Shearon Harris Nuclear Power Plant, Unit 1 ML18064A1332018-03-19019 March 2018 Summary of February 27, 2018, Meeting with Duke Energy Progress, LLC to Discuss Proposed License Amendment Request for Shearon Harris Nuclear Power Plant, Unit 1, Regarding Emergency Plan Emergency Action Level Scheme Changes (L-2017-LRM-00 ML17340A1302017-12-22022 December 2017 Summary of November 29, 2017, Meeting with Duke Energy Progress, LLC to Discuss Proposed License Amendment Requests to Implement the Requirement of 10 CFR 50.69 at Brunswick, Shearon Harris, and H. B. Robinson ML17317A3302017-12-22022 December 2017 Summary of October 26, 2017, Second Pre-Submittal Meeting with Duke Energy Regarding Brunswick Advanced Areva Methods License Amendment Request (CAC Nos. MF9965 and MF9966; EPID L-2017-LRM-0033) ML17340A0612017-12-0808 December 2017 11/8/17 Summary of Teleconference with Entergy Operations, Inc., Tornado Missile Risk Evaluator with Applicability to Submittals from Duke Energy and Southern Nuclear Operating Co, Inc. ML17286A1222017-11-0101 November 2017 Summary of August 22, 2017, Pre-Submittal Meeting with Duke Energy Re. Brunswick Advanced Areva Methods License Amendment Request (CAC Nos. MF9965 and MF9966; EPID L-2017-LRM-0033) ML17244A0742017-09-28028 September 2017 8/17/2017 Summary of Public Meeting with Nuclear Energy Institute and Licensees to Discuss the Tornado Missile Risk Evaluation Tool for Grand Gulf, Shearon Harris, and Vogtle, Units 1 and 2 ML17257A0992017-09-26026 September 2017 Summary of Public Meeting with Nuclear Energy Institute and Licensees to Discuss the Tornado Missile Risk Evaluation Tool for Grand Gulf, Shearon Harris, and Vogtle, Units 1 and 2 2024-06-21
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 12,2011 LICENSEES: CAROLINA POWER & LIGHT COMPANY AND FLORIDA POWER CORPORATION FACILITIES: Brunswick Steam Electric Plant, Units 1 and 2; Crystal River Nuclear Generating Plant, Unit 3; and H. B. Robinson Steam Electric Plant, Unit 2
SUBJECT:
SUMMARY
OF APRIL 12, 2011, PREAPPLICATION MEETING WITH CAROLINA POWER & LIGHT COMPANY AND FLORIDA POWER CORPORATION, ON BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2; CRYSTAL RIVER NUCLEAR GENERATING PLANT, UNIT NO.3; AND H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.2, TRANSITION TO NFPA 805 REQUIREMENTS On April 12, 2011, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and Progress Energy, representing Carolina Power & Light Company and Florida Power Corporation (the licensees) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the preapplication meeting was to discuss the transition to the requirements of the National Fire Protection Association Standard 805 (NFPA 805) pursuant to Section 50.48(c) of Title 10 of Code of Federal Register (1 0 CFR) for Brunswick Steam Electric Plant, Unit Nos. 1 and 2 (Brunswick); Crystal River Nuclear Generating Plant, Unit NO.3 (Crystal River); and, H. B. Robinson Steam Electric Plant, Unit No.2 (Robinson). The licensees provided a slide presentation prior to the meeting to help facilitate the discussion (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML11102A005). This document was linked to the meeting notice posted on the NRC's website in advance the meeting (ADAMS Accession No. ML110840631). A list of attendees is enclosed.
Following the administrative and introductory meeting portions, Alex Klein, Chief of NRC's Office of Nuclear Reactor Regulation (NRR) Fire Protection Branch, started the meeting by providing background information on NFPA 805 and referring to the previous meeting held on February 9, 2011 (ADAMS Accession No. ML110590918). He also referred to an upcoming meeting with the Nuclear Energy Institute on April 14, 2011, that would discuss the sequence of the NFPA 805 license amendment submittals and the staggered review by the NRC staff.
Jeff Ertman, Progress Energy's NFPA 805 Project Manager, began the licensee's presentation by providing an NFPA 805 fleet submittal schedule (page 2 of the slides). Current license amendment requests (LARs) submittals scheduled are: Crystal River initial submittal in June 2011 with one supplement in the third quarter of 2011; Robinson initial submittal in June 2011 with two supplements in the first and third quarters of 2012; and Brunswick initial submittal in October 2011 with one supplement in the first quarter or 2012. Current target modification completion date for all three plants is 2014. Samson Lee, Deputy Director of NRR's Division of Risk Assessment, commented that submitting planned supplements is not a preferred approach for the NRC and may not pass the acceptance review instructions under NRR's L1C-1 09, "Acceptance Review Procedures." Progress Energy continued by presenting fleet target modification completion dates, project organization, strength and challenges regarding the
-2 NFPA 805 project. During the meeting, the Progress Energy attendees presented and discussed the fleet and site-specific slides. Additional information was provided by the licensee's personnel on the conference call for each site, as needed.
Progress Energy discussed its fleet strength by pointing out at the fleet level variances from deterministic requirements and compensatory measures that address multiple spurious operations and operators manual actions issues are in place. Also, incorporation of lessons-learned and processes from pilot plants, such as the Shearon Harris Nuclear Power Plant (HNP, which is part of the Progress Energy fleet) and Oconee Nuclear Station, and use of the LAR template for the remaining plants are considered as a fleet strength. Progress Energy added that they are not waiting for the NRC staff approval of the LARs to schedule modifications, and many modifications at Robinson and Crystal River are already scheduled and completed.
Progress Energy provided insights regarding its fleet level challenges. Progress Energy stated that most of the work is performed with internal resources that may be impacted by the resources challenges because of emergent plant or industry issues. There is also a continual competition for external resources, particularly in the areas of probabilistic risk assessment and safe shutdown analysis. Other fleet challenges include the first NFPA 805 post-transition triennial inspection, other triennial inspections in 2011, and plant outages.
After the fleet discussions, Progress Energy provided site-specific updates. It provided an update for each site regarding scope and status, plant specific issues, projected modifications, challenges, and impact on safety. During the meeting, Progress Energy, in response to the NRC inquiries, provided the status of steps in NFPA 805 prioritization philosophy for each plant.
At Crystal River, modifications are projected and in progress. The solution for being in compliance is both deterministic and performance based, similar to HNP. The licensee is planning to submit its LAR for the extended power uprate (EPU) in June 2011. The Crystal River EPU and NFPA 805 LARs will be independent. However, the NFPA 805 LAR will describe modifications under post-EPU LAR. The fire impacts will be considered in the EPU internal and external events. Another challenge specific to Crystal River is that, due the containment delamination, it has been in an extended outage since September 2009. The Progress Energy personnel on the conference call supported the Crystal River plant-specific discussions.
At Brunswick, the current target is one submittal in October 2011 with one supplement for nonpower operations. The licensee has not identified any specific open items. The plant-specific challenges include a dual-unit plant with cross-unit power supply, many previously approved Appendix R, III.G.3 areas, and shortage of internal resources.
At Robinson, the current LAR target is June 2011, with two supplements in 2012. It appears that if Robinson submits its NFPA 805 LAR as scheduled, it will not pass a sufficiency review of the NRC's acceptance process (UC-109). The licensee previously requested an extension of its original enforcement discretion to August 2012. However, the NRC staff responded that at that time, the staff was not authorized to grant the request. Many NFPA 805 modifications are projected for the Robinson plant. Modifications will not be impacted by the LAR submittal or the NRC review dates. The Progress Energy personnel on the conference call also supported the Robinson plant-specific discussions.
-3 At the conclusion of the meeting, Progress Energy stated that it will monitor NRC's approval of staggered approach to reviewing staggered reviewing of NFPA 805 applications and it will keep the respective NRC plant project managers up to date on any changes to the LAR submittal schedule as discussed during the meeting.
Members of the public were in attendance and on the phone. Public Meeting Feedback forms were distributed, but no comments were received.
Please direct any inquiries to me at 301-415-1447 orfarideh.saba@nrc.gov.
Sincerely, r~~~h E- ~~
Farideh Saba, Senior Project Manager Plant licensing Branch 11-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325, 50-324, 50-302, 50-261, and 50-400
Enclosure:
list of Attendees cc w/encl: Distribution via listServ
LIST OF AITENDEES April 12, 2011 MEETING WITH PROGRESS ENERGY TRANSITION TO NFPA-805 LICENSE AMENDMENT REQUESTS Nuclear Regulatory Commission Public - call in S. Laur P. Bradley A. Klein M. Lilley S. Lee N. Tyler S. Dinsmore P. Mazzaferro D. Pickett P. Barbadoro P. Lain W. Cross D. Harrison C. Sly J. Robinson F.Saba Progress Energy.
K. Heffner D. Miskiewicz K. Lavin J. Ertman Progress Energy - call in F. Modlin S. Thomposon B. Gerwe J. Linger W. Murray J. Becker J. Caves J. Curham T. Howard C. Kish P. Kannapel Nuclear Energy Institute T. Basso Enclosure
- 3 At the conclusion of the meeting, Progress Energy stated that it will monitor NRC's approval of staggered approach to reviewing staggered reviewing of NFPA 805 applications and it will keep the respective NRC plant project managers up to date on any changes to the LAR submittal schedule as discussed during the meeting.
Members of the public were in attendance and on the phone. Public Meeting Feedback forms were distributed, but no comments were received.
Please direct any inquiries to me at 301-415-1447 or farideh.saba@nrc.gov.
Sincerely, IRA!
Farideh Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325, 50-324, 50-302, 50-261, and 50-400
Enclosure:
List of Attendees cc w/encl: Distribution via ListServ DISTRIBUTION:
PUBLIC RidsOgcRp RidsNrrPMCrystalRiver LPL2-2 Branch Reading RidsRgn2MailCenter PLain, NRR RidsAcrsAcnw_MailCTR CSteger, NRR RidsNrrDra RidsNrrDorlLpl2-2 SDinsmore, NRR RidsNrrDraAfpb RidsNrrPM Brunswick DPickett, NRR RidsNrrDraApla RidsNrrLACSola NSanfilippo, EDO RidsNrrPMRobinson ADAMS Accession No. PKG ML11116A016 Notice ML110840631 SummaryML11116A020 Handouts MI1 1102AOO 5 OFFICE NAME I DORULPL2-2 IPM FSaba IDORUlPl2-2IPM DORULPL2-2/LA CSoia DRAlAPLAlBC DHarrison DATE 5/3/11 5/3111 5/12/11 OFFICE DRAlAFPB/BC DORULPL2-2/BC DORULPL2-2 IPM NAME AKlein DBroaddus (CGratton for) FSaba DATE 5/11/11 5/12/11 05/12111 OFFICIAL RECORD COpy