ML20212Q028

From kanterella
Revision as of 10:46, 20 January 2021 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Notice of Violation from Insp on 860519-22 & 0623-0702
ML20212Q028
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 08/20/1986
From: Walker R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20212Q016 List:
References
50-424-86-61, NUDOCS 8609030375
Download: ML20212Q028 (1)


Text

, ->

ENCLOSURE 1 NOTICE OF VIOLATION Georgia Power Company Docket No. 50-424 Vogtle License No. CPPR-108 During the Nuclear Regulatory Commission (NRC) inspection conducted on May 19 - 22 and June 23 - July 2,1986, a violation of NRC requirements was identified. The viulation involved the removal of a conduit support with no authorization. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1985), the violation is listed below:

10 CFR 50, Appendix B, Criterion V as implemented by FSAR, Chapter 17, Section 17.1.5 requires, in part, that procedures shall outline the manner in which work is conducted. Construction Procedure ED-T-17, Rev. 4, FPCN 10 Section 4.9 states, " initiate a rework request or maintenance work order as applicable for items requiring rework which have been accepted by electrical QC personnel."

Contrary to the above, on May 21, 1986, conduit support CS-7C4-102-068 was found loose and no Maintenance Work Order or rework request had been issued to authorize work on the support.

ThisisaSeverityLevelIVviolation(SupplementII).

Pursuant to the provisions of 10 CFR 2.201, Georgia Power Company is hereby required to submit to this Office within 30 days of the date of the letter transmitting this Notice a written statement or explanation in reply including:

(1) admission or- denial of the violation, (2) the reason for the violation if

admitted, (3) the corrective steps which have been taken and the results achieved, (4) the corrective steps which will be taken to avoid further violations, and (5) the date when full compliance will be achieved. Where good
cause is shown, consideration will be given to extending the response time.

FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by Luis A. Reyes /for Roger D. Walker, Director Division of Reactor Projects i Dated at Atlanta, Georgia this g 6 day of August 1986

$0 G

DON $4

--. - - - - _ - ._ , - - - - . , . . . . . - .. .-.