MONTHYEARML20217G0361999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20212E7451999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Hcgs,Unit 1.With Summary of Changes,Tests & Experiments Implemented During Aug 1999.With ML20216E4941999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Jmfnp.With ML20210R6031999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With L-99-267, Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20209G0661999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With L-99-023, Monthly Operating Repts for May 1999 for Jfnp Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Jfnp Units 1 & 2. with L-99-020, Monthly Operating Repts for Apr 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With L-99-161, Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20205N0961999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20207M6421999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20203A2651999-01-31031 January 1999 Monthly Operating Repts for Jan 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20199E6591998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20198B2561998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20195C9681998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20154H6001998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20197C8991998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20237B1891998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20236M5981998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20248M3121998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20247F3631998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20216D5941998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Joseph M Farley Nuclear Plant,Units 1 & 2 ML20216D9811998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20202G4211998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20198L6191997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Jm Farley Nuclear Plant,Units 1 & 2 ML20203F6391997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Jm Farley Nuclear Plant,Units 1 & 2 ML20198T4151997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Jm Farley Nuclear Plant ML20211N7221997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Jm Farley Nuclear Plant Units 1 & 2 ML20216J3151997-08-31031 August 1997 Monthly Operating Repts for August 1997 for Jfnp ML20210K5981997-07-31031 July 1997 Monthly Operating Repts for Jul 1997 for Jm Farley Nuclear Plant,Units 1 & 2 ML20141H3191997-06-30030 June 1997 Monthly Operating Repts for June 1997 for Joseph M Farley Nuclear Plant Units 1 & 2 ML20148K6081997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Joseph M Farley Nuclear Plant ML20141E3121997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Jm Farley Nuclear Plant Units 1 & 2 ML20137T1841997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Jm Farley Nuclear Plant Units 1 & 2 ML20136G4731997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Jm Farley Plant Units 1 & 2 ML20138K5881997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Jm Farley Nuclear Plant Units 1 & 2 ML20133F4791996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Jm Farley Nuclear Plant Units 1 & 2 ML20132C0631996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Jm Farley Nuclear Plant Units 1 & 2 ML20134K7141996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Jm Farley Nuclear Plant Units 1 & 2 ML20128Q1161996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Jm Farley Nuclear Plant,Units 1 & 2 ML20117M1291996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Jm Farley Nuclear Plant Units 1 & 2 ML20116J6421996-07-31031 July 1996 Monthly Operating Repts for Jul 1996 for Jm Farley Nuclear Plant Units 1 & 2 ML20115D6821996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Jm Farley Nuclear Plant Units 1 & 2 ML20117M2721996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Jm Farley Nuclear Plant Units 1 & 2 ML20111D1401996-04-30030 April 1996 Monthly Operating Rept for Apr 1996 for Jm Farley Plant Units 1 & 2 ML20101R6271996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Jm Farley Nuclear Plant ML20106H0791996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Jm Farley Nuclear Plant ML20097D5651996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Jm Farley Nuclear Plant ML20096C0921995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Jm Farley Nuclear Plant Units 1 & 2 ML20095E9451995-11-30030 November 1995 Monthly Operating Repts for Nov 1995 for Joseph M Farley Nuclear Plant 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217P0761999-10-0606 October 1999 Non-proprietary, Farley Units 1 & 2 LBB Calculation Results Due to SG Replacement & SG Snubber Elimination Programs ML20217G0361999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20212E7451999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Hcgs,Unit 1.With Summary of Changes,Tests & Experiments Implemented During Aug 1999.With ML20216E4941999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Jmfnp.With ML20210T2161999-08-0606 August 1999 Draft SE Supporting Proposed Conversion of Current TS to ITS for Plant ML20211B2011999-08-0404 August 1999 Informs Commission About Results of NRC Staff Review of Kaowool Fire Barriers at Farley Nuclear Plant,Units 1 & 2 & Staff Plans to Address Technical Issues with Kaowool & FP-60 Barriers ML20210R6031999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20196J3791999-06-30030 June 1999 Safety Evaluation of TR WCAP-14750, RCS Flow Verification Using Elbow Taps at Westinghouse 3-Loop Pwrs. Rept Acceptable ML20209G0661999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With L-99-267, Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With L-99-023, Monthly Operating Repts for May 1999 for Jfnp Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Jfnp Units 1 & 2. with ML20206G7471999-05-0404 May 1999 Safety Evaluation Accepting Corrective Actions Taken by SNC to Ensure That Valves Perform Intended Safety Functions & Concluding That SNC Adequately Addressed Requested Actions in GL 95-07 L-99-020, Monthly Operating Repts for Apr 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20206C9461999-04-30030 April 1999 1:Final Cycle 16 Freespan ODSCC Operational Assessment L-99-161, Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20205N0961999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20204D7271999-03-15015 March 1999 ISI Refueling 15,Interval 2,Period 3,Outage 3 for Jm Farley Nuclear Generating Plant,Unit 1 ML20207M6421999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20203A2651999-01-31031 January 1999 Monthly Operating Repts for Jan 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20199D8611999-01-12012 January 1999 SER Accepting Relief Request for Inservice Insp Program for Plant,Units 1 & 2 ML20199E6591998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20206C8081998-12-31031 December 1998 Alabama Power 1998 Annual Rept ML20198K4091998-12-18018 December 1998 COLR for Jm Farley,Unit 1 Cycle 16 ML20198B2561998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20195E2281998-11-16016 November 1998 Safety Evaluation Authorizing Relief Request for Second 10-year ISI Program Relief Request 56 for Plant,Unit 1 ML20195C9681998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20155E0271998-10-29029 October 1998 SER Approving & Denying in Part Inservice Testing Program Relief Requests for Plant.Relief Requests Q1P16-RR-V-3 & Q2P16-RR-V Denied Since Requests Do Not Meet Size Requirement of GL 89-04 ML20154B6121998-10-0101 October 1998 Safety Evaluation Granting Second 10-year ISI Requests for Relief RR-13 & RR-49 Through RR-55 for Jm Farley NPP Unit 1 ML20151V8341998-09-30030 September 1998 Non-proprietary Rev 2 to NSA-SSO-96-525, Jm Farley Nuclear Plant Safety Analysis IR Neutron Flux Reactor Trip Setpoint Change ML20154H6001998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20154H0121998-09-30030 September 1998 Submittal-Only Screening Review of Farley Nuclear Plant IPEEE (Seismic Portion) ML20197C8991998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20237C5471998-08-20020 August 1998 Suppl to SE Re Amends 137 & 129 to Licenses NPF-2 & NPF-8, Respectively.Se Being Supplemented to Incorporate Clarifications/Changes & Revise Commitment for Insp of SG U-bends in Rows 1 & 2 for Unit 2 Only ML20236Y1121998-07-31031 July 1998 Voltage-Based Repair Criteria 90-Day Rept ML20237B1891998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20237A2181998-07-24024 July 1998 Jm Farley Unit 2 ISI Rept Interval 2,Period 3 Outage 1, Refueling Outage 12 ML20236U6141998-07-23023 July 1998 Safety Evaluation Authorizing Use of Alternative Alloy 690 Welds (Inco 52 & 152) as Substitute for Other Weld Metal ML20236R8671998-07-0909 July 1998 Safety Evaluation Concluding That Southern Nuclear Operating Co USI A-46 Implementation Program Has Met Purpose & Intent of Criteria in GIP-2 & Staff SSER-2 on GIP-2 for Resolution of USI A-46 ML20236M5981998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20154H0461998-06-30030 June 1998 Technical Evaluation Rept on Review of Farley Nuclear Plant IPEEE Submittal on High Winds,Flood & Other External Events (Hfo) ML20248M3121998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20247F3631998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Jm Farley Nuclear Plant,Units 1 & 2 ML20217D2591998-04-21021 April 1998 Safety Evaluation Accepting Licensee Proposed Alternative Re Augmented Exam of Reactor Vessel Shell Welds for Plant ML20247E8851998-03-31031 March 1998 FNP Unit 2 Cycle 13 Colr ML20217H3191998-03-31031 March 1998 Safety Evaluation Accepting Proposed Changes to Plant Matl Surveillance Programs ML20216D5941998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Joseph M Farley Nuclear Plant,Units 1 & 2 ML20217D4081998-03-24024 March 1998 Safety Evaluation Accepting Proposed Changes to Maintain Calibration Info Required by ANSI N45.2.4-1972 ML20216H6731998-03-17017 March 1998 SER Accepting Quality Assurance Program Description Change for Joseph M Farley Nuclear Plant,Units 1 & 2 ML20216J6851998-03-16016 March 1998 Revised Pages 58 & 59 to Fnp,Units 1 & 2,Power Uprate Project BOP Licensing Rept ML20216D9811998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Jm Farley Nuclear Plant,Units 1 & 2 1999-09-30
[Table view] |
Text
JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1 NARRATIVE
SUMMARY
OF OPERATIONS November,-1992 The cycle 11-12 refueling outage continued through the month of November.
The following major safety related maintenance was performed during the month of November:
- 1. Performed testing and maintenance on various safety-related hydraulic and mechanical snubbers.
- 2. Performed numerous maintenance tasks on the reactor coolant pumps including seal inspection and main flange stud elongation checks.
- 3. Performed numerous maintenance tasks on the auxiliary feedwater pumps.
- 4. Replaced the tube bundle in the 600 volt load center IE room cooler.
- 5. Performed various design changes on the service water system-including the replacement of some existing carbon steel piping-with stainless steel.
- 6. Replaced one main steam safety on each main steam line.
- 7. Performed various design changes in 600 volt load centers including calibrating "Agastat" relays.
- 8. Performed miscellaneous corrective and preventive maintenance on the diesel generators.
- 9. Performed internals inspection on various service water and component cooling water check valves,
- 10. Performed eddy current _ testing, sleeving of tubes, and plugging of tubes in all three steam generators.
9212100027 921214 PDR ADOCK 05000340 R. PDR
,6J ,,, - e J -----a -- --- - --_,ws-,6 OPERATING DATA REPORT DOCKET NO. 50-348 DATE December 8.-1992 COMPLETED BY R. D. Hill TELEPHONE (205) 899-5156 OPERATING STATUS ;
- 1. Unit Name: Joseph M. Farley - Unit 1 Notes
- 2. Reporting Period: November-1992 1) Cumulative data since
- 3. Licensed Thermal Power (MWt): 2.652 12-1-77, date of
- 4. Nameplate Rating (Gross MWe): 860 commerical operation. ,
- 5. Design Electrical Rating (Net MWe): 829
- 6. Maximum Dependable Capacity (Gross MWe): 855.7 7 Maximum Dependable Capacity (Net MWe): 812.0
- 8. If Changes Occur in Capacity Ratings (Items Number 3 lhrough 7) Since Last Report, l Give Reasons: N/A
- 9. Power Level To Which Restricted, If Any (Net MWe): N/A
- 10. Reasons for Restrictions, if Any: N/A This Month Yr-to-Date cumulative
- 11. Hours In Reporting Period 720.0 8.040.0 131.496.0
- 12. Number Of Hours Reactor Was Critical 34.6 6.489.0 102.399.9
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 1.650.0
- 14. Hours Generator On-Line 0.0 6.454.1 100.718.4 15.' Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH) 257.2 17.036.145.7 258.440.769.2
- 17. Gross Electrical Energy Generated (MWH) 66.0 5.484.700.0 83.269.462.0
- 18. Net Electrical Energy Generated (MWH) (11.782) 5.185.162.0 78.599.960.0
- 19. Unit Service factor 0.0 801 3 76.6
-20. Unit Availability Factor 0.0 80.3 - 76. 6 -
- 21. Unit _ Capacity Factor (Using MDC Net) N/A 79.4 73.9
- 22. Unit Capacity Factor (Using DER Net) N/A 77.8- 72.1
- 23. Unit Forced Outage Rate 0.0 0.0 _ 6.7
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
N/A
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup: 12/2/92
- 26. Units in Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY 08/06/77 08/09/77 INITIAL ELECTRICITY 08/20/77 08/18/77 COMMERCIAL OPERATION 12/01/77 12/01/77 DATARPT.Ul
DOCKET N0. 50-348 UNIT 1 DATE- December 8. 1992-COMPLETED BY R. D. Hill TELEPHONE (205)-899-5156 MONTH November DAY AVERAGE DAILY PCWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net)_
1 0 17 0 2 0 18 0 3 0 19 0 4 0 20 0 5 0 21 0 6 0' 22 0-7 0 23 0-8 0 24 0 9 0 25 0 10 0 26 0:
-11 0 27 0
-12 0 28 0 13 -0 29 0-14 0 30 0-15 0 31 N/A 16 0 INSTRUCTIONS On.this format, list the average daily unit power level. in MWe-Net for-each _ day in the reporting month. Compute to .the nearest wh' ole megawatt.
AVGDLY.PWR-t - _ _ .- ., . _ _ _ _ . .
t UMT SHUTDOWNS AND POWER REDUCTIONS DOCAET NO. 50-348
' UNIT NAME J M. Fariev - Unit 1 DATE December 8.1992 COMPLETED BY R D. Hat -
REPORT MONTH: NOVEMBER TELEPHONE l205) 899-5156 METHOD OF UCENSEE CAUSE & CORAECTIVE DURATION SHUTTING EVENT SYSTEM COMPONENT ACTION TO NO. DATE- TYPE' (HOURS) REASON' DOWN REACTOR
- PREVENT RECURRENCE 002- 921001 S 720 C 1 N/A N/A N/A The cycle 11-12 refueling continuad from 920925.
1:' 2: 3: 4: 5:.
. F: Forced ' Reason: Method: '. Exhibit G4nstructions for Shibit I- Same Sowee S: Scheduled . 'A Equipment Failure (Explain) . 1 - Manual. Prep rations for Data Entry
. 8 - Maintenance or Test . 2- Manual Scram. Sheets for Ucensee Event '
C - Refueling ' ! 3 - Automatic Scram. Report (LER) File (NUREG4161)
D - Regulatory Restriction 4 - Other (Explain) '
- E - Operator Training & Ucensing Examination F- Administrative G - Operational Error (& plain)
H - Other (Dplain) -
JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2 NARRATIVE
SUMMARY
OF OPERATIONS November, 1992 There were no unit shutdowns or major power reductions during the month of November.
The following major safety-related maintenance was performed during the month:
- 1. Miscellaneous corrective and preventive maintenance was performed on the diesel generators.
P
7 OPERATING DATA REPORT DOCKET N0. 50-364 DATE December 8. 1992 COMPLETED BY R. D. Hill TELEPHONE (205) 899-5156 OPERATING STATUS
- 1. Unit Name: Joseph M. Farley - Unit 2 Notes
-2. Reporting Period: November 1992 1) Cumulative data since
- 3. Licensed Thermal Power (MWt): 2.652 7-30-81, date of
- 4. Nameplate Rating (Gross MWe): 860 commerical operation
- 5. Design Electrical Rating (Net MWe): 829
- 6. Maximum Dependable Capacity (Gross MWe): 864.3 7 Maximum Dependable Capacity (Net MWe): 824.0
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since last Report, Give Reasons:_N/A
- 9. Power Level To Which Restricted, If Any (Net MWe): N/A
- 10. Reasons For Restrictions, If Any: N/A This Month Yr-to-Date Cumul ative
- 11. Hours In Reporting _ Period 720.0 8.040.0 99.409.0
- 12. Number Of Hours Reactor Was Critical 720.0 6.413.6 85.277.9
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 138.0
- 14. Hours Generator On-line 720.0 6.244.2 84.172.7
- 15. Unit Reserve Shutdown Hours 0.0 0.0 -00
- 16. Gross Thermal Energy Generated (MWH) 1.890.053.9 15.619.568.6 214.578.890.2
- 17. Gross Electrical Energy Generated (MWH) 621.225.0 5.072.345.0 70.3682 429.0
- 18. Net Electrical Energy Generated (MWH) 591.885.0 4.791.953.0 66.726.015.0
- 19. Unit Service Factor 100.0 77.7 84.7
-20. Unit Availability Factor 100.0 __.
7 i .- 7 84.7
- 21. Unit Capacity Factor (Using MDC Net) 99.8 72.3 81.9
- 22. Unit Capacity Factor (Using DER Net) 99.2- 71.9 81.0 -
- 23. Unit Forced Outage Rate 0.0 3.1 4.1
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
N/A
- 25. If Shut Down At End Of-Report Period, Estimated Date of Startup: N/A
- 26. Units In Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY 05/06/81 05/08/81 INITIAL ELECTRICITY 05/24/81 05/25/81 COMMERCIAL OPERATION 08/01/81 07/30/81-DATARPT.U2
' DOCKET NO, 50-364 UNIT 2
.DATE~ December 8. 1992' COMPLETED BY R. D. Hill ,
TELEPHONE (205) 899-5156 MONTH November DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE-DAILY POWER LEVEL: ;
(MWe-Net) (MWe-Net) 1 816 17 827 2 815 18 826 3 814 19 823 4 814 20 810 5 822 21 804 6 828 22 814 7 829 23 ;22 8 829 24 820~
9 827 25 816 10 826 26 824-11 823 27 812 12 816 28 828 13- 826 29 827 14 827 827 15- 826 31 N/A 16 828 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
AVGDLY.PWR
UNIT SHUTDOWNS AND POWER REDUCTIOMS ~
DOCKET NO. 90FA UNIT NAME J M. Fariev - Unit 2 DATE December 8.1992 '
COMPLETED BY R D. Hiit
- REPORT MONTH: NOVEMBER TELEPHONE (2051 899-5156 METHOD OF UCENSEE CAUSE & CORRECTIVE DUPATION SHUTTING EVENT SYSTEM COMPONENT ACTION TO DATE TiPE' REASON' DOWN REACTOW REPORT # CODE
- PREVENT RECURRENCE NO. (HOURS)
There were no unit shutdowns or major power reductions during the month of November l
l
'l
. 2- 3: 4: 5: '
1:
F: Forced Reason: - Method. Exhibit G-instructions for Exhibit I- Same Source
. S. Scheduled - . A - Equipment Failure (Explain) 1 - Manual . Preparations for Data Entry j B - Maintenance or Test. 2 - Manual Scram Sheets for Ucensee Event C - Refueling . 3 - Automatic Scram, Report (LER) Ole (NUREG4161)
D - Regulatory Flestriction ' 4 - Other (Explain)-
' E Operator Training & Ucensing Examination F- Administrative G - Operational Error (Explain)
- H - Other (Explain)
- - - -. . w. -_.
a; . _ ~ - - .-.
.-..(.
- . - - - ~ . - -
JOSEPH M. FARLEY NUCLEAR PLANT ADDENDUM CONCERNING REVISION'T0 THE OFFSITE DOSE CALCULATION MANUAL Temporary change 10A to the Offsite Dose Calculation Manual (ODCM) was approved by the Plant Operations Review Committee (PORC) on September 14, 1992. This temporary change was incorporated into revision 11 and approved by the PORC on December 1, 1992. The ODCM was revised to include a specific step showing the calculation of the actual (anticipated) dilution factor available for a liquid effluent release and to modify the manner in which concentrations of non-gamma-emitting radionuclides are applied in the liquid effluent monitor setpoint calculation. This revision was desirable since the liquid effluent monitor only responds to gamma-emitting radionuclides. The entire ODCM is attached.
It was determined by the PORC that these changes do not reduce the accuracy or reliability of dose calculation or setpoint determinations.
The ODCM applies to Farley Nuclear Plant Units 1 and 2.