Monthly Operating Repts for Feb 1998 for Jm Farley Nuclear Plant,Units 1 & 2
ML20216D981
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 02/28/1998
From: Phillips A
SOUTHERN NUCLEAR OPERATING CO.
To:
Shared Package
ML20216D975 List:
References
NUDOCS 9803170382
Download: ML20216D981 (4)


Text

_______-__ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

F~ OPERATING DATA REPORT DOCKET NO.: 50-348

,. . UNIT NAME: J. M. Farley - Unit 1 DATE: March 4,1998 COMPLETED BY: A. M. Phillips TELEPHONE: (334) 899-5156, ext. 3640 OPERATING _ STATUS

1. Reporting Period: February 1998
2. Design Electrical Rating (Net MWe): _

829

3. Maximum Dependable Capacity (Net MWe): 822 This3fonth YeattoDate Cumulative
4. Number Of Hours Reactor Was Critical: 672.0 1,416.0 143,697.6
5. Hours Generator On-line: 672.0 1,416.0 141,635.4
6. Unit Reserve Shutdown Hours: 0.0 0.0 0.0
7. Net Electrical Energy Generated (MWH): 552,262.0 1,170,939.0 111,471,267.0 CHALLENGES TO PRESSURIZER PORY OR PRESSURIZER SAFETY VALVES Date l Tag No. I hvent Description There were no challenges to Pressurizer PORV or Pressurizer Safety Valves.

El-1 9003170382 900311 PDR ADOCK 05000348 R PDR .

~

. UNIT SHUTDOWNS DOCKET NO.: 50-348

, , UNIT NAME: - J. M. Farley - Unit 1 DATE: March 4,1998 COMPLETED BY: A. M. Phillips REPORTING PERIOD: Echruary_199.8 TELEPHONE: (334) 899-5156, ext.3640 Type Method of F: Forced Duration Reason Shutting Down Cause/ Corrective Actions No. Date S: Scheduled (Hours) (1) (2) Comments There were no unit shutdowns daring the month.

m anuu. m muuvu.

A Equipment Failure (Explain) 1 - Manual D - Maintenance or Test 2 - Manual Ts;p/ Scram C Refueling 3 Automatic TrifvScram D- Regulatory Restriction 4 Continuation E operatorTraining/ License Examination 5 - Other(Explain)

F Administrative 0 operational Error (Explain) 11 other(Explain)

CAUSE/ CORRECTIVE ACTION / COMMENTS 1

i I

NARRATIVE REPORT At 1813 on 980211, with the unit operating at 100% reactor power, the unit was ramped to 24% reactor power to replace a electronic card in the controls of the 'B' Main Feedwater Reg Bypass Valve Controller. Repair wr- bompleted and the unit was returned to 100% reactor power at 1135 on 980212.

El-2

~

OPERATING DATA REPORT DOCKET NO.: 50-364 UNIT NAME: J. M. Farley - Unit 2 DATE: March 4,1998 COMPLETED BY: A. M. Phillips TELEPHONE: (334) 899-5156, ext. 3640 DPERATINGSTATllS

1. Reporting Period: February 1998
2. Design Electrical Rating (Net MWe): 829
3. Maximum Dependable Capacity (Net MWe): 828 IbisJdonth YeatioEite Cumulative
4. Number Of Hours Reactor Was Critical: 672.0 1,416.0 126,333.0
5. Hours Generator On-line: 672.0 1,416.0 124,546.9
6. Unit Reserve Shutdown Hours: 0.0 0.0 0.0
7. Net Electrical Energy Generated (MWH): 566,815.0 1,193,920.0 99,025,284.0 CIIALLENGES TO PRESSURIZER PORY OR PRESSURIZER SAFETY VALVES Date l Tag No. I Event Description There were no challenges to Pressurizer PORV or Pressurizer Safety Valves.

I I

)

E2-1

I i

..;~ UNIT SHUTDOWNS j DOCKET NO.: 50-364 i ,_ , UNIT NAME: J. M. Farley - Unit 2 DATE: March 4,1998 COMPLETED BY: A. M. Phillips ~

REPORTING PERIOD: February _1998 TELEPHONE: (334) 899-5156, ext.3640 Type Method of l F: Forced Duration Reason Shutting Down Cause/ Corrective Actions No. Date s: scheduled (Hours) (1) (2) Comments l There were no unit shutdowns during the month.

I (1) KLASUN. (2) Mt.IllVD, A Equipment Failure (Explain) 1 - Manual D Maintenanx orTest 2 - Manual Trip / Scram C Refueling 3 AutomaticTrip/ Scram D - Regulatory Restriction 4 Continuation E OperatorTraining/ License Exarnination 5 Other(Explain)

F Administrative 0- Operational Error (Explain) 11 Other(Explain)

CAUSE/ CORRECTIVE ACTION / COMMENTS l

NARRATIVE REPORT There were no significant power reductions or major safety related maintenance during the month.

l l

I l

E2-2  ;