Monthly Operating Rept for Aug 1983
ML20080G498
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 09/01/1983
From: Clayton F, Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
NUDOCS 8309200297
Download: ML20080G498 (5)


Text

- -

r .

JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1.

NARRATIVE

SUMMARY

OF OPERATIONS AUGUST, 1983 During the month of August, there were no unit shutdowns or significant power reductions.

The following safety-related maintenance was performed in the month of August:

1. Performed miscellaneous maintenance on diesel generators.
2. Cleaned out 1A charging pump lube oil cooler.
3. Replaced numerous waste evaporator: feed filters.
4. Replaced mechanical seal on spent fuel pool skimmer pump.

i-

5. Adjusted numerous packing glands on main steam system valves.

8309200297 830901 PDR ADOCK 05000348 R PDR

OPERATING DATA REPORT DOCKET NO. 50-348 DATE 9-1-83 COMPLETED BY UA Unfrston III TELEPHONE (205) 899-5155 OPERATING STATUS Joseph M.'Farlev - Unit 1 Notes

1. Unit Nam *.

An m" 10R1

1) Cumulative dasa since
2. Reporting Period: 12/1/77, data of
3. Licensed Thermal Power (MWt): 2652 commercial operation.
4. Nameplate Rating (Gross MWe): 860
5. Design Electrical Rating (Net MWe): 829
6. Maximum Dependable Capacity (Gross MWe): 844.6
7. Maximum Dependable Capacity (Net MWe):

803.6

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since.Last Report. Give Reasons:

N/A

9. Power Level To Which Res*ricted,If Any (Net MWe): ' M/A
10. Reasons For Restrictions,If Any: N/A This Month Yr..to.Date n ulative

' Cur'

11. Hours In Reporting Period 744 5,831 50.399
12. Number Of Hours Reactor Was Critical 766 r) 4,068.2 32,215.7
13. Reactor Reserve Shutdown Hours 0.0 25.1 3,639.6
14. Hours Generator On.Line 744.0 1966.3 31,234.5
15. Unit Reserve Shutdown Hi urs 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1.971.688 10,029,740 7g qio 7po I 7. Gross Electrical Energy Generated (MWH) 617,154 3,162,260 74;937_gog
18. Net Electrical Energy Generated (MWH) 585,990 2,971,936 23.412.156
19. Unit Service Factor 100.0 68.0 62.0
20. Unit Availability Factor inn n 68.0 62.0
21. Unit Capacity Factor (Using MDC Net) 98.0 63.4 57 g
22. Unit Capacity Factor (Using DER Net) 95.0 __

61.5 56.0

23. Unit Forced Outage Rate 0.0 0.7 16.4
24. Shutdowns Scheduled Over Nevt 6 Months (Type. Date, and Duration of Eacht:
25. If Shur Down At End Of Report Period. Estimated Date of Startup: N/A
26. Units in Test Status iPrior to Commercial Operation): Forecast Achieved iNITIA L CRITICa LiTY R/6/77 8/o/77 INITIAL ELECTRICITY 8/20/77 8/l8/77 COMMERCIAL CPERATION 12/1/77 12/1/77 (4/77)

DOCKET No. 50-348 UNIT DATE 9-1-83 C05fPLETED BY W.G. Hairston, III (205) 899-5156 TELEPHONE August. 1983 StONTil DAY AVERAGE DAILY POWER LEVEL DAY' AVERAGE DAILY POWER LEVEL talwe Net) (MWe-Net) 793 793 g, 37 2 795 13 792 709 g9 791 3

4 789 J 785 787 783 5 21 785 22 781 6

788 23 7R9 7

783 3 797 24 786 g 72 3 9

782 10 785 26 g3 785 n 788 787 ;3 7ga 12 787 785 l3 3 789 30 788 14 31 7on

- IS 796 16 INSTRUCTIONS On this fonn:t. list the svenge daily unit power levelin MWe Net for e:ch d:y in the reporting month. Compute to

, the neste:t whole me;2 watt.

(9p7) w - ,,-,-c., w4 ,c. . , - - , , , -,,,7,- -,-%,y- .-, ,-.w------r e -Es----v--wy- -w-- - + - 1-- -- -e- <- -w *w-- ww m-n --g- ----tw*----~w, , , - +

UNIT Sil01 DOWNS AND POWER REDUC 110NS DOCKE T NO. _ _50-348 UNII NAME J.M. Farley UnTt l' DAIE _9/1/83 COMPLEI ED ilY W.G. Ilairston, III ftEPORT alONiil Aueust. 1983 TEl.LPIIONE (205) 899-5156 3 -

~.

c_

.2 e re g

5 sa =

9 sX Licensee c .t.

5"

c. Cause & Coniective No. Date g 3g  ;; jg5 Event u? 8-3 Action to H

$E 5 j5y 5

Report * ,

<# G fu Pacvent Recutience THERE WERE NO JNIT Sil rTDOW) S OR SIGNIFICANT PuWER RH: DUCTIONS IN THE MONTil 0F AUGUST.

I I 2 3 4 1:: l'osted Reason: Method: Exhibit G . Instrutiion -

S: Sthednied A liguipment Failure (Explain) 1 -Manual for Prepa:Jtion of Das i i 11 Maintenance o( Test 2 M.mual Scram. Entiy Sheels foi 1.iccei C Itefacting 3 Autenuatic Scram. Esent Ilepint li.Elti! ! (NilRI:G-D.Itegulatory Resisittion 4 Othes (Esplain) 01611 I Operator Training & license Examination F. Adininist raiive 5 G Opciational Lisor (E= plain) INinhis t . S.une Som.

19/77) ll Othes (E xplain)

e E Mailing Address Alabama Power Comp ny 600 North 18th Street Post Office Box 2641 Birmingham, Alabama 35291 Telephone 205 783-6081 F. L Clayton, Jr. b

= lac;3g7"' AlabamaPbwer the southem elettnc system September 12, 1983 Docket No. 50-348 Di rector, Of fice of Management Inf ormation and Program Control U. S. Nuclea r Regul atory Commi s sion Washington, D.C. 20555 Dea r Si r:

RE: Joseph M. Farley Nuclear Plant Unit 1 Monthly Operating Data Report Attached are two (2) copies of the August, 1983 Monthly Operating Report for Joseph M. F a rl ey Nuclear Plant, U r. i t 1, required by Section 6.9.1.10 of the Appendix A Tech-nical Specifications. As requested by letter f rom Mr. John F.

Stolz to Mr. Alan R. Barton, dated October 21, 1977, a "Narra-tive Summa ry of Operating Experience" is included in the attached report.

If you have any questions, please advise.

Yours very ,uly,

)?/6

,/

F. L. Cl ayton, J r.

ILCJr/KWM:nac Enclosures xc: Mr. Ted Cintula (1 copy)