| | number = ML103220444 | | | number = ML103220444 |
| | issue date = 11/18/2010 | | | issue date = 11/18/2010 |
| | title = 11/17/2010 Public Meeting Summary - North Anna Power Station | | | title = Public Meeting Summary - North Anna Power Station |
| | author name = Mccoy G | | | author name = Mccoy G |
| | author affiliation = NRC/RGN-II/DRP/RPB5 | | | author affiliation = NRC/RGN-II/DRP/RPB5 |
Line 15: |
Line 15: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 November 18, 2010 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 November 18, 2010 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060 |
| | |
| Glen Allen, VA 23060 | |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
Line 23: |
Line 21: |
|
| |
|
| ==SUMMARY== | | ==SUMMARY== |
| - NORTH ANNA POWER STATION, DOCKET NOS. 50-338 AND 50-339 | | - NORTH ANNA POWER STATION, DOCKET NOS. 50-338 AND 50-339 |
|
| |
|
| ==Dear Mr. Heacock:== | | ==Dear Mr. Heacock:== |
|
| |
|
| This letter refers to the Category 1 public meeting conducted at your request in the Region II Office on November 17, 2010, at 1:00 p.m. The meeting's purpose was to provide an open public forum to discuss the recent discovery and remediation of containment insulation issues at the North Anna Power Station. Enclosed is a list of attendees (Enclosure 1) and the presentation handouts (Enclosure 2). | | This letter refers to the Category 1 public meeting conducted at your request in the Region II Office on November 17, 2010, at 1:00 p.m. The meetings purpose was to provide an open public forum to discuss the recent discovery and remediation of containment insulation issues at the North Anna Power Station. Enclosed is a list of attendees (Enclosure 1) and the presentation handouts (Enclosure 2). |
| | The meeting was mutually beneficial and provided the NRC staff with an understanding of your goals and direction for the remediation of containment insulation issues at North Anna Power Station. |
| | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). |
| | Should you have any questions concerning this meeting, please contact me at (404) 997-4551. |
| | Sincerely, |
| | /RA/ |
| | Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos.: 50-338, 50-339 License Nos.: NPF-4, NPF-7 |
| | |
| | ==Enclosures:== |
| | As stated cc w/encl.: See page 2 |
| | |
| | VEPCO 2 cc w/encl: Michael M. Cline Daniel G. Stoddard, Director Senior Vice President Virginia Department of Emergency Services Nuclear Operations Management Virginia Electric and Power Company Electronic Mail Distribution Electronic Mail Distribution County Administrator Fred Mladen Louisa County Director, Station Safety & Licensing P.O. Box 160 Virginia Electric and Power Company Louisa, VA 23093 Electronic Mail Distribution Michael Crist N. L. Lane Plant Manager Site Vice President North Anna Power Station North Anna Power Station Virginia Electric & Power Company Virginia Electric & Power Company Electronic Mail Distribution Electronic Mail Distribution Chris L. Funderburk Director, Nuclear Licensing & Operations Support Virginia Electric and Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq. |
| | Senior Counsel Dominion Resources Services, Inc. |
| | Electronic Mail Distribution Executive Vice President Old Dominion Electric Cooperative Electronic Mail Distribution Ginger L. Melton Virginia Electric and Power Company Electronic Mail Distribution Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission P.O. Box 490 Mineral, VA 23117 |
| | |
| | 4 N |
| | * z * |
| | ) |
| | * m C. |
| | C. |
| | 1* 1\ |
| | C C. |
| | l ft j |
| | ii z tn 0 |
| | -I ZI o :ZtTj H |
| | CDZ tni 0* tnHt1ir |
| | -C |
| | -w I .r C-. |
| | p I- C |
| | .h rri 0 |
| | it. m cJ D m tn C -I A) 3 z 0 H tM C-, |
| | r1 C |
| | I 5 |
| | 5 1 |
| | L I r |
| | |
| | *Dominion North A nna Power Station GL 2004-02 (GSI 191) |
| | Larry Lane Site Vice President Dominion Nuclear Safety First Enclosure 2 |
| | |
| | Dominion Timelm e |
| | * Unit 1 Containment walkdownsfor insulation performed per NEI 02-01 Spring 2003 |
| | * Unit 2 Containment walkdowns for insulation performed per NEI 02-01 Spring 2004 |
| | * GL 2004-02 issued on September 13, 2004 |
| | * AECL testing ofdebris load identfied Calcium Silicate (Cal-Sil) and Microtherm as particulates that affect RS and LHSI strainers August 2006 Dominion Nuclear Safety First 2 Enclosure 2 |
| | |
| | I ominion 4 Timeline |
| | * DCP 07-004 removes Cal-Sil and Microtherm on Unit 2. DCP 05-014 installs sump strainers. Spring 2007 |
| | * DCP 07-129 removes Cal-Sil on Unit 1. DCP 05-013 installs sump strainers. Fall 2007 |
| | * Dominion letter summarizes resolution of GL 2004-02 exceptfor in-vessel effects. |
| | February 2009 Dominion Nuclear Safety First 3 Enclosure 2 |
|
| |
|
| The meeting was mutually beneficial and provided the NRC staff with an understanding of your goals and direction for the remediation of containment insulation issues at North Anna Power
| | rDominion Timeline |
| | * NRC acknowledges North Anna effort complete exceptfor in-vessel effects. May 2009 Dominion Nuclear Safety First 4 Enclosure 2 |
|
| |
|
| Station.
| | .sfJ 7 |
| In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
| | L Enclosure 2 |
|
| |
|
| Should you have any questions concerning this meeting, please contact me at (404) 997-4551.
| | IDominion Redesigned Sump NUCLEAR DESIGN INFORMATION PORTAL Figure 6.2-5 ARRANGEMENT CONTAINMENT SUMP STRAINER FOR UNIT 1 0 |
| Sincerely,
| | C PLAN ELEVATiON 2S-11 Dominion Nuclear Safety First 6 Enclosure 2 |
| /RA/ Gerald J. McCoy, Chief Reactor Projects Branch 5
| | |
| | Dominion Redesigned Sump Dominion Nuclear Safety First 7 Enclosure 2 |
|
| |
|
| Division of Reactor Projects Docket Nos.: 50-338, 50-339 License Nos.: NPF-4, NPF-7
| | Dominion Sump Testing Initial Strainer Sizing Rig #33 Thin Bed RS 2.1 psi LHSI 1.1 psi Full Debris RS 0.14 psi LHSI 0.33 psi Dominion Nuclear Safety First 8 Enclosure 2 |
|
| |
|
| ==Enclosures:==
| | Dominion Verfication GSI 191 Implementation Microtherm and Cal-Sil insulation was replaced in the Zones OfInfluence (ZOl) |
| As stated
| | Physical implementation was completed during 2007 |
| | * Supplemental Response Serial No. 08-0019 All Microtherm removedfrom Unit 2 with none installed in Unit 1 Dominion Nuclear Safety First 9 Enclosure 2 |
|
| |
|
| cc w/encl.: See page 2 VEPCO 2 cc w/encl:
| | Dominion Discovery Neutron Shielding Evaluation |
| Daniel G. Stoddard, Senior Vice President Nuclear Operations Virginia Electric and Power Company Electronic Mail Distribution
| | * Unit 2 Spring 2010 RFO boric acid target inspection |
| | * Neutron Saddle Shields degraded |
| | * Subsequent Unit 1 extent ofcondition inspection noted some Neutron Saddle Shields also not intact Dominion Nuclear Safety First 10 Enclosure 2 |
|
| |
|
| Fred Mladen Director, Station Safety & Licensing Virginia Electric and Power Company Electronic Mail Distribution
| | Domjnie Neutron Saddle Shield Saddle Shields Vessel Shieldi Aimulus Wall Dominion Nuclear Safety First 11 Enclosure 2 |
|
| |
|
| N. L. Lane Site Vice President North Anna Power Station Virginia Electric & Power Company Electronic Mail Distribution
| | Dominion Disco very Neutron Shielding Evaluation |
| | * Design Change development for removing the Neutron Saddle Shields Reactor Vessel Nozzles |
| | * RCS intermediate loop |
| | * RCP casing |
| | * Unit 2 was shutdown and inspections identfled Microtherm and Cal-Sil insulation in the ZOl |
| | * Informational Report made to NRC upon shut down of Unit 2 Dominion Nuclear Safety First 12 Enclosure 2 |
|
| |
|
| Chris L. Funderburk Director, Nuclear Licensing & Operations Support Virginia Electric and Power Company Electronic Mail Distribution
| | Unit 1 Intermediate Elbow Microtherm Removal JIVDOmI nion 1/4 Micro therm encased in metal Dominion U |
| | Nuclear Safety First 13 Enclosure 2 |
|
| |
|
| Lillian M. Cuoco, Esq.
| | Unit 1 RCP Casing srDomi nion Arrow to Panel ofMicrotherm Insulation Dominion Nuclear Safety First 14 Enclosure 2 |
| Senior Counsel Dominion Resources Services, Inc.
| |
| Electronic Mail Distribution
| |
|
| |
|
| Executive Vice President Old Dominion Electric Cooperative Electronic Mail Distribution
| | Unit 1 RCP Casing Dominion Arrow to panel ofMicrotherm Insulation Dominion K |
| | Nuclear Safety First 15 Enclosure 2 |
|
| |
|
| Ginger L. Melton Virginia Electric and Power Company Electronic Mail Distribution Attorney General Supreme Court Building
| | Dominion Inspection |
| | * Inspection procedures developed |
| | * Training developed to qualify inspectors |
| | * Complete review of the documentation Insulation vendor drawings S& W design changes for specifications associated with insulation Insulation specification changes Design Changes which could have impacted insulation Dominion Nuclear Safety First 16 Enclosure 2 |
|
| |
|
| 900 East Main Street
| | Dominion Inspection |
| | *Specialized Inspection Team established QualfIed Inspectors (2), Insulator, QMT Hand-over-hand inspections ofpiing and components Dominion Nuclear Safety First 17 Enclosure 2 |
|
| |
|
| Richmond, VA 23219 Senior Resident Inspector
| | As Found Insulation Dominion (Inside Zones ofInfluence) |
| | Unit 1 Unit 2 Microtherm 5811 3 62ft Cal Sil 3 8ft 3 9ft Dominion U |
| | Nuclear Safety First 18 Enclosure 2 |
|
| |
|
| North Anna Power Station U.S. Nuclear Regulatory Commission P.O. Box 490
| | Dominion Remediation |
| | * Unacceptable insulation (Cal-Sil and/or Microtherm) was fully remediated when identified during walk downs within the ZOIs for Unitsl&2 |
| | * Microtherm outside ZOl was verified to be encased Dominion Nuclear Safety First 19 Enclosure 2 |
|
| |
|
| Mineral, VA 23117
| | Dominion 2-RH-MO V-2 700 Remedia ted Dominion Nuclear Safety First Enclosure 2 |
|
| |
|
| Michael M. Cline Director Virginia Department of Emergency Services Management Electronic Mail Distribution
| | Dominion Operabiiity Impact |
| | * Small break small amount offibrous material does not affect operability |
| | * Medium break outside testing assumptions |
| | * Large break outside testing assumptions |
| | * PRA review appears to be Green Dominion Nuclear Safety First 21 Enclosure 2 |
|
| |
|
| County Administrator Louisa County P.O. Box 160 Louisa, VA 23093
| | Dominion |
| | * RCE in Progress |
| | * Preliminary A flawed methodology used to determine types and quantities of insulation during the GSI-191 containment walkdowns, resulting in unacceptable insulation not being included in the containment debris inventory or subsequently remediated. |
| | Incomplete as-built drawings Ineffective project management (inventory and remediation) |
| | Ineffective oversight and over-reliance on vendor Dominion Nuclear Safety First Enclosure 2 |
|
| |
|
| Michael Crist
| | I Dominion Corrective ii c ti ons A |
| | * Microtherm and Cal-Sil was remediated in Unit 1 and 2 containments |
| | * Insulation re-inventoried in containment |
| | * Process improvements initiated Insulation changes reviewed by Engineering prior to work and are independently reviewed Insulation database changes are independently reviewed |
| | * Pending completion ofRCEOO1O3O |
| | * LER submittal by 11/23/10 |
| | * GL 2004-02 Response will be updated Dominion Nuclear Safety First Enclosure 2 |
|
| |
|
| Plant Manager
| | Dominion Con c/usion |
| | * Extent ofcondition for both units was promptly pursued |
| | * Conservative decision making employed to shutdown and inspect Unit 2 |
| | * All discrepancies werefully remediated |
| | * Unit 1 and 2 containment sumps are operable Dominion Nuclear Safety First Enclosure 2 |
|
| |
|
| North Anna Power Station Virginia Electric & Power Company Electronic Mail Distribution}}
| | IDominion Questions? |
| | Dominion Nuclear Safety First 25 Enclosure 2}} |
|
---|
Category:Letter
MONTHYEARML24283A0392024-10-0909 October 2024 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.D ML24281A1372024-10-0707 October 2024 ISFSI - Submittal of Cask Registration for Spent Fuel Storage 05000338/LER-2024-001-01, Automatic Reactor Trip Due to Prni High Negative Rate2024-09-24024 September 2024 Automatic Reactor Trip Due to Prni High Negative Rate IR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter ML24243A0872024-09-20020 September 2024 Response to EPA Comments Regarding the Final Site Specific Supplement to the Generic Eist for License Renewal North Anna Power Station, Units 1 and 2 IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) 05000339/LER-2024-001-01, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24165A1462024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 IR 05000338/20240102024-05-24024 May 2024 NRC Fire Protection Team Inspection (FPTI) Report 05000338/2024010 and 05000339/2024010 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24110A1502024-04-18018 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24110A1462024-04-18018 April 2024 Independent Spent Fuel Storage Installation (Sfsi) - Annual Radiological Environmental Operating Report ML24110A1392024-04-18018 April 2024 Annual Environmental Operating Report ML24087A0572024-04-16016 April 2024 Correction to Issuance of Amendment Nos. 296 and 279 ML24088A2692024-03-27027 March 2024 Core Operating Limits Report Cycle 31 Pattern Sos Revision 0 ML24086A4292024-03-25025 March 2024 Response to Request for Additional Information Associated with Alternative Request N1-I5-NDE-007 Request to Deter Additional Required Reactor Coolant Pump Casing Inspection ML24082A2742024-03-22022 March 2024 Request for Approval of Alternative Request N1-I5-NDE-007 to Deter Additional Required Reactor Coolant Pump Casing Inspection ML24086A4682024-03-21021 March 2024 Summary of Facility Changes, Tests and Experiments ML24005A0042024-03-18018 March 2024 Issuance of Amendment Nos. 296 and 279, Regarding Revised Emergency Plan for Relocation of the Technical Support Center 2024-09-24
[Table view] Category:Meeting Summary
MONTHYEARML24222A4232024-08-19019 August 2024 Summary of June 17, 2024, Meeting with Virginia Electric and Power Company About Guidance in Section 7.5 of Standard Review Plan for Light Water Reactors ML24222A6992024-08-16016 August 2024 August 6, 2024, Summary of Regarding Potential License Amendment Request Change to Surveillance Requirements for Moderator Temperature Coefficient for Millstone, Unit No. 3, North Anna, Unit Nos. 1 and 2, and Summer, Unit No. 1 - ML23345A1092023-12-14014 December 2023 December 7, 2023, Summary of Public Meeting with Virginia Electric and Power Company Concerning a License Amendment Request to Revise Emergency Augmentation Times for North Anna Station, Units 1 & 2, and Surry Station, Units 1 & 2 ML23167A7012023-06-26026 June 2023 Summary of Public Meeting with VEPCO Concerning a License Amendment Request to Revise Emergency Plan Staff Augmentation Times ML23151A5472023-06-0101 June 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding North Anna Power Station, Docket Nos. 50-338 and 50-339; and Surry Power Station ML22130A1702022-05-20020 May 2022 Summary of April 21, 2022, Public Meeting to Discuss Potential Emergency Preparedness License Amendment Request ML22130A0332022-05-0909 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting Regarding North Anna Power Station, Docket Nos. 50-338 and 50-339; and Surry Power Station, Docket Nos. 50-280 and 50-281, Meeting Number 20220349 ML22091A0902022-04-0101 April 2022 Combined 2021 Assessment Meeting Slides ML21293A0992021-12-10010 December 2021 Meeting Summary for Draft Supplemental Environmental Impact Statement Public Meeting ML21221A3022021-10-18018 October 2021 June 24, 2021, Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Meeting Summary ML21221A3032021-10-18018 October 2021 June 24, 2021, Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000)- List of Attendees ML21239A0662021-09-0202 September 2021 August 27, 2021, Summary: Discussion Between NRC and Dominion Regarding the NAPS Subsequent License Renewal - an Inconsistency in Documentation Regarding RCP Code Case N-481 (EPID No. L-2020-SLR-0000) - Summary ML21236A0532021-08-27027 August 2021 August 16, 2021, Meeting Summary: Discussion of Aging Management of Cyclic Fatigue in the Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Meeting Summary ML21221A0312021-08-27027 August 2021 Meeting Summary Regarding Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application ML21236A0512021-08-27027 August 2021 August 16, 2021, Meeting Summary: Discussion of Aging Management of Cyclic Fatigue in the Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Memo ML21236A0582021-08-27027 August 2021 August 16, 2021, Meeting Summary: Discussion of Aging Management of Cyclic Fatigue in the Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - List of Attendees ML21221A0262021-08-26026 August 2021 Meeting Summary Regarding Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application ML21221A1382021-08-10010 August 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Meeting Summary ML21145A2152021-06-0909 June 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Enclosure 2 - List of Attendees ML21145A2132021-06-0909 June 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Enclosure 1 - Summary ML21131A1612021-05-11011 May 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Virgil C. Summer Nuclear Station, Docket No. 50-395; North Anna Power Station, Docket Nos. 50-338 and 50-339; and Surry Power Station, Docket Nos. 50-280 and 50-281, Meeting ML21027A0232021-01-28028 January 2021 Summary of January 26, 2021 Closed Meeting with Dominion Energy Regarding Performance of Force on Force Exercises in a Pandemic Environment ML20324A2592020-12-0303 December 2020 Scoping Meeting Summary ML20136A1752020-05-15015 May 2020 Sur 2019 Aam Meeting Summary ML20104A0392020-04-21021 April 2020 Presubmittal Meeting Summary ML19190A2862019-07-16016 July 2019 Summary of July 7, 2019, Public Meeting with Dominion to Discuss Open Phase Condition RAI Responses ML19144A1292019-05-30030 May 2019 Summary of November 20, 2018, Pre Application Meeting with Dominion Energy Regarding the Planned License Amendment Request to Revise Emergency Action Levels ML19128A3432019-05-0808 May 2019 Public Meeting Summary - 2018 Annual Assessment Public Meeting Regarding North Anna Power Station, Docket Nos. 50-338 and 50-339 ML18151A4682018-05-29029 May 2018 Public Meeting Summary - 2017 Annual Assessment Public Meeting Regarding North Anna Power Station, Docket Nos. 50-338 and 50-339 ML18066A0192018-03-16016 March 2018 Meeting Summary of October 4, 2017 Pre-Submittal Public Meeting to Discuss LAR Request Regarding Consolidation of the Emergency Operations Facilities ML17123A2092017-05-0303 May 2017 Summary of Meeting to Discuss Annual Assessment of the North Anna Power Station, Units 1 and 2 with the Public for the Period of January 1, 2016 Through December 31, 2016 ML16138A0752016-05-19019 May 2016 Summary of April 26, 2016, Pre-Application Teleconference with Virginia Electric and Power Company for Increase in Maximum Fuel Enrichment for the New Fuel Storage Racks and the Spent Fuel Pool ML16124A7632016-05-0303 May 2016 April 14, 2016, Summary of Public Meeting - North Anna Power Station, Units 1 and 2 ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment ML15316A2522015-11-19019 November 2015 October 20, 2015, Millstone, Units 2 and 3, Surry, Units 1 and 2, North Anna, Units 1 and 2 - Summary of Pre-submittal Conference Call Regarding Emergency Action Level Scheme Changes ML15128A5462015-05-0808 May 2015 Summary of Public Meeting with North Anna, Units 1 and 2 to Discuss the Annual Assessment with the Public ML14101A1202014-04-11011 April 2014 Public Meeting Summary - North Anna Power Station, Docket Nos. 50-338, 50-339 ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13151A1282013-05-31031 May 2013 Public Meeting Summary - North Anna Power Station Docket Nos. 50-338 and 50-339 ML12131A5032012-05-0909 May 2012 5/1/2012 Summary of Category 1 Public Meeting Regarding the Annual Assessment of the North Anna Power Station ML12060A3682012-03-0101 March 2012 G20110668/EDATS: OEDO-2011-0622 - 02/02/12 - Meeting Summary for Meeting with Paul Gunter Et Al. Regarding Their 10 CFR 2.206 Petition to Suspend the Operating Licenses for North Anna Power Station, Unit Nos. 1 and 2 ML12060A3522012-03-0101 March 2012 G20110757/EDATS: OEDO-2011-0701 - 12/12/11 - Meeting Summary of Meeting with Paul Gunter Et Al. Regarding Their 10 CFR 2.206 Petition to Suspend the Operating Licenses (Ols) for North Anna 1 and 2 ML1131804092011-11-14014 November 2011 Public Meeting Summary - Status of Nrc'S Restart Review and Inspection - North Anna Power Station ML1128500392011-10-12012 October 2011 Summary of Augmented Inspection Team Public Exit Meeting with Virginia Electric Power Company to Discuss the Results of an ATI Inspection of an Earthquake Event on August 23, 2011 ML1110304742011-04-13013 April 2011 Public Meeting/Open House Summary Letter ML1032204442010-11-18018 November 2010 Public Meeting Summary - North Anna Power Station ML1023804682010-08-26026 August 2010 08/18/10 Summary of Meeting NRC Initial Exam Writer'S Workshop ML1021102592010-08-0404 August 2010 Enclosure 3: Dominion - North Anna Presentation of July 28, 2010 Public Meeting ML1020704582010-07-28028 July 2010 Summary of Meeting with VEPCO to Discuss Fuel Transition Licensing ML0923803922009-08-26026 August 2009 08/11-12/2009-Summary of Meeting Re 2009 Us NRC Initial Exam Development Workshop 2024-08-19
[Table view] Category:Meeting Briefing Package/Handouts
MONTHYEARML24283A1442024-10-16016 October 2024 Main Steam Line Break Accident Analysis LAR Pre-Application Meeting ML24247A0042024-09-0303 September 2024 SLR Efficiencies Public Meeting - NRC Presentation - September 5, 2024 ML24108A0712024-04-30030 April 2024 Combined - 2023 Annual Assessment Public Meeting Slides ML24029A2362024-01-30030 January 2024 Preliminary Results of the Environmental Review, Subsequent License Renewal ML23338A1522023-12-0707 December 2023 Public Meeting Slides for North Anna and Surry Emergency Plan Augmentation Times License Amendment Request ML23255A0992023-09-15015 September 2023 Slides for September 15, 2023 Public Meeting on Poanhi Seismic Evaluations ML23103A3482023-04-14014 April 2023 Annual Assessment Meeting Presentation for North Anna and Surry ML21221A0332022-06-17017 June 2022 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides ML21174A3042021-06-23023 June 2021 SLRA RAI Response Public Meeting - 21-06-24 ML21221A1542021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Dominion Slides ML21145A2172021-05-13013 May 2021 Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion Slides ML21132A2892021-05-13013 May 2021 SLRA RAI Response Public Meeting ML21034A5972021-02-10010 February 2021 External Presentation Am Atkinson_Nrc ISG-06 Meeting Dominion Digital IC Project 02102021 ML20288A3472020-10-14014 October 2020 (COVID-19) Emergency Preparedness Exemption Pre-Application Meeting ML20099F2992020-04-0909 April 2020 NRC Slides for North Anna pre-app April 9 ML20099F2412020-04-0909 April 2020 Co., NRC Safety Pre& 8208;Application Meeting North Anna Power Station (NAPS) ML20098B6022020-04-0707 April 2020 Annual Assessment Meeting Presentation ML19297D1872019-11-18018 November 2019 Pre-Application Meeting - Dominion Slides ML18320A2502018-11-20020 November 2018 50.90 License Amendment Request - Dominion Fleet EAL Scheme Changes, November 20, 2018 Public Meeting ML18141A3072018-05-21021 May 2018 18 - SLR Status ML17123A2092017-05-0303 May 2017 Summary of Meeting to Discuss Annual Assessment of the North Anna Power Station, Units 1 and 2 with the Public for the Period of January 1, 2016 Through December 31, 2016 ML16124A7582016-05-0303 May 2016 April 14, 2016, Summer of Public Meeting - North Anna, Units 1 and 2 ML16124A7632016-05-0303 May 2016 April 14, 2016, Summary of Public Meeting - North Anna Power Station, Units 1 and 2 ML16104A3822016-04-26026 April 2016 New Fuel Storage Rack & SFP Criticality Analysis for April 26th 2016 Scheduled Category 1, Pre-Submittal Public Teleconference ML16104A3872016-04-13013 April 2016 Criticality Analysis Checklist for North Anna ML15273A4292015-09-29029 September 2015 Revised Slides for September 29, 2015 Meeting with Dominion Re North Anna ISFSI License Renewal ML15153A0452015-05-13013 May 2015 Revised North Anna ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15133A0822015-05-13013 May 2015 ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15128A5462015-05-0808 May 2015 Summary of Public Meeting with North Anna, Units 1 and 2 to Discuss the Annual Assessment with the Public ML14101A1202014-04-11011 April 2014 Public Meeting Summary - North Anna Power Station, Docket Nos. 50-338, 50-339 ML14058B1762014-03-0606 March 2014 Presentation Slides - North Anna ISFSI - High Burnup Dry Storage Confirmatory Data Project, TN-32 Storage Cask, Tom Brookmire, March 6, 2014, Docket No. 72-16, TAC No: L24886 ML14071A1672014-01-28028 January 2014 Enclosure 2: Presentation Slides - North Anna ISFSI TN-32 Cask and Pad 1 Assessments Following August 23, 2011, Central Virginia Earthquake ML13159A0092013-06-0404 June 2013 Notable Failures in Nondustructive Testing - June 4, 2013 Public Meeting ML12257A2342012-09-11011 September 2012 5-Hacker - North Anna Mockup and Search Unit Action Presentation Sept 10 ML12257A2002012-09-11011 September 2012 2-North Anna Extent of Condition Presentation 9-7-12 Sept 10 ML12131A5052012-05-0909 May 2012 Presentation for 2011 North Anna EOC Annual Assessment Meeting ML11305A0452011-11-0101 November 2011 Region II - North Anna Public Meeting Slides ML11305A0622011-11-0101 November 2011 Restart Readiness, Public Meeting PR2 ML11276A0242011-10-0303 October 2011 Slides-North Anna AIT Public Meeting October 3, 2011 ML1127701352011-10-0303 October 2011 Ltr to D. Heacock Re Participation in the Commission Meeting on the North Anna Plant on 10/21/11 ML11252A0062011-09-0808 September 2011 Dominion'S Slides Earthquake Response and North Anna Restart Readiness Demonstration Plan ML1124205512011-08-30030 August 2011 Seismic Event ML1110304942011-04-13013 April 2011 Public Meeting Attendees ML1110304982011-04-13013 April 2011 Public Meeting Handouts ML1032204442010-11-18018 November 2010 Public Meeting Summary - North Anna Power Station ML1020100212010-07-14014 July 2010 Nucler Power Station, Units 1 and 2, Westinghouse RFA-2 Fuel Transition Licensing Meeting Presentation Slides ML1012600332010-05-0505 May 2010 Meeting Posters ML1012600342010-05-0505 May 2010 Public Mtg. Slides ML0917610472009-08-0505 August 2009 ECCS Preacs Filtration Presentation ML0911000392009-04-17017 April 2009 Notice of Public Meeting Category 1 - Annual Assessment of North Anna Power Station 2024-09-03
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24283A1442024-10-16016 October 2024 Main Steam Line Break Accident Analysis LAR Pre-Application Meeting ML24247A0042024-09-0303 September 2024 SLR Efficiencies Public Meeting - NRC Presentation - September 5, 2024 ML24108A0712024-04-30030 April 2024 Combined - 2023 Annual Assessment Public Meeting Slides ML24029A2362024-01-30030 January 2024 Preliminary Results of the Environmental Review, Subsequent License Renewal ML23338A1522023-12-0707 December 2023 Public Meeting Slides for North Anna and Surry Emergency Plan Augmentation Times License Amendment Request ML23255A0992023-09-15015 September 2023 Slides for September 15, 2023 Public Meeting on Poanhi Seismic Evaluations ML23103A3482023-04-14014 April 2023 Annual Assessment Meeting Presentation for North Anna and Surry ML21221A0332022-06-17017 June 2022 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides ML22091A0902022-04-0101 April 2022 Combined 2021 Assessment Meeting Slides ML21221A1482021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides ML21221A1542021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Dominion Slides ML21132A2892021-05-13013 May 2021 SLRA RAI Response Public Meeting ML21145A2172021-05-13013 May 2021 Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion Slides ML21034A5972021-02-10010 February 2021 External Presentation Am Atkinson_Nrc ISG-06 Meeting Dominion Digital IC Project 02102021 ML20288A3472020-10-14014 October 2020 (COVID-19) Emergency Preparedness Exemption Pre-Application Meeting ML20099F2412020-04-0909 April 2020 Co., NRC Safety Pre& 8208;Application Meeting North Anna Power Station (NAPS) ML20099F2992020-04-0909 April 2020 NRC Slides for North Anna pre-app April 9 ML20098B6022020-04-0707 April 2020 Annual Assessment Meeting Presentation ML19297D1872019-11-18018 November 2019 Pre-Application Meeting - Dominion Slides ML18141A3072018-05-21021 May 2018 18 - SLR Status ML16124A7582016-05-0303 May 2016 April 14, 2016, Summer of Public Meeting - North Anna, Units 1 and 2 ML16124A7632016-05-0303 May 2016 April 14, 2016, Summary of Public Meeting - North Anna Power Station, Units 1 and 2 ML15273A4292015-09-29029 September 2015 Revised Slides for September 29, 2015 Meeting with Dominion Re North Anna ISFSI License Renewal ML15153A0452015-05-13013 May 2015 Revised North Anna ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15133A0822015-05-13013 May 2015 ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15128A5462015-05-0808 May 2015 Summary of Public Meeting with North Anna, Units 1 and 2 to Discuss the Annual Assessment with the Public ML14058B1762014-03-0606 March 2014 Presentation Slides - North Anna ISFSI - High Burnup Dry Storage Confirmatory Data Project, TN-32 Storage Cask, Tom Brookmire, March 6, 2014, Docket No. 72-16, TAC No: L24886 ML14071A1672014-01-28028 January 2014 Enclosure 2: Presentation Slides - North Anna ISFSI TN-32 Cask and Pad 1 Assessments Following August 23, 2011, Central Virginia Earthquake ML13159A0092013-06-0404 June 2013 Notable Failures in Nondustructive Testing - June 4, 2013 Public Meeting ML12257A2002012-09-11011 September 2012 2-North Anna Extent of Condition Presentation 9-7-12 Sept 10 ML12257A2342012-09-11011 September 2012 5-Hacker - North Anna Mockup and Search Unit Action Presentation Sept 10 ML12131A5052012-05-0909 May 2012 Presentation for 2011 North Anna EOC Annual Assessment Meeting ML11305A0452011-11-0101 November 2011 Region II - North Anna Public Meeting Slides ML11305A0622011-11-0101 November 2011 Restart Readiness, Public Meeting PR2 ML1128500392011-10-12012 October 2011 Summary of Augmented Inspection Team Public Exit Meeting with Virginia Electric Power Company to Discuss the Results of an ATI Inspection of an Earthquake Event on August 23, 2011 ML11276A0242011-10-0303 October 2011 Slides-North Anna AIT Public Meeting October 3, 2011 ML1127701352011-10-0303 October 2011 Ltr to D. Heacock Re Participation in the Commission Meeting on the North Anna Plant on 10/21/11 ML11252A0062011-09-0808 September 2011 Dominion'S Slides Earthquake Response and North Anna Restart Readiness Demonstration Plan ML12040A2742011-08-31031 August 2011 E-Mail from G. Wilson, NRR to D. Merzke, EDO; Subject: Seismic Instruments at North Anna ML12044A2912011-08-30030 August 2011 E-mail from G. Bowman, EDO to T. Hipschman, Comm, Et Al; Subject: FYI-Revised Slides on North Anna/Gl-199 ML1124205512011-08-30030 August 2011 Seismic Event ML12044A2792011-08-30030 August 2011 Email from M. Khanna, NRR to R. Auluck, NRR FW: North Anna Earthquake Issue Commissioner Briefing Final with Talking Points ML12044A2572011-08-26026 August 2011 Email from A. Istar, NRR to A. Hiser, NRR on North Anna Nuclear Power Plant. Pptx ML1110304822011-04-13013 April 2011 Public Annual Assessment Meeting/Open House Slides ML1032204442010-11-18018 November 2010 Public Meeting Summary - North Anna Power Station ML1021102592010-08-0404 August 2010 Enclosure 3: Dominion - North Anna Presentation of July 28, 2010 Public Meeting ML1020100212010-07-14014 July 2010 Nucler Power Station, Units 1 and 2, Westinghouse RFA-2 Fuel Transition Licensing Meeting Presentation Slides ML1012600332010-05-0505 May 2010 Meeting Posters ML1012600342010-05-0505 May 2010 Public Mtg. Slides ML0917610472009-08-0505 August 2009 ECCS Preacs Filtration Presentation 2024-09-03
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 November 18, 2010 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060
SUBJECT:
PUBLIC MEETING
SUMMARY
- NORTH ANNA POWER STATION, DOCKET NOS. 50-338 AND 50-339
Dear Mr. Heacock:
This letter refers to the Category 1 public meeting conducted at your request in the Region II Office on November 17, 2010, at 1:00 p.m. The meetings purpose was to provide an open public forum to discuss the recent discovery and remediation of containment insulation issues at the North Anna Power Station. Enclosed is a list of attendees (Enclosure 1) and the presentation handouts (Enclosure 2).
The meeting was mutually beneficial and provided the NRC staff with an understanding of your goals and direction for the remediation of containment insulation issues at North Anna Power Station.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 997-4551.
Sincerely,
/RA/
Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos.: 50-338, 50-339 License Nos.: NPF-4, NPF-7
Enclosures:
As stated cc w/encl.: See page 2
VEPCO 2 cc w/encl: Michael M. Cline Daniel G. Stoddard, Director Senior Vice President Virginia Department of Emergency Services Nuclear Operations Management Virginia Electric and Power Company Electronic Mail Distribution Electronic Mail Distribution County Administrator Fred Mladen Louisa County Director, Station Safety & Licensing P.O. Box 160 Virginia Electric and Power Company Louisa, VA 23093 Electronic Mail Distribution Michael Crist N. L. Lane Plant Manager Site Vice President North Anna Power Station North Anna Power Station Virginia Electric & Power Company Virginia Electric & Power Company Electronic Mail Distribution Electronic Mail Distribution Chris L. Funderburk Director, Nuclear Licensing & Operations Support Virginia Electric and Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq.
Senior Counsel Dominion Resources Services, Inc.
Electronic Mail Distribution Executive Vice President Old Dominion Electric Cooperative Electronic Mail Distribution Ginger L. Melton Virginia Electric and Power Company Electronic Mail Distribution Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission P.O. Box 490 Mineral, VA 23117
4 N
)
C.
1* 1\
C C.
l ft j
ii z tn 0
-I ZI o :ZtTj H
CDZ tni 0* tnHt1ir
-C
-w I .r C-.
p I- C
.h rri 0
it. m cJ D m tn C -I A) 3 z 0 H tM C-,
r1 C
I 5
5 1
L I r
Larry Lane Site Vice President Dominion Nuclear Safety First Enclosure 2
Dominion Timelm e
- Unit 1 Containment walkdownsfor insulation performed per NEI 02-01 Spring 2003
- Unit 2 Containment walkdowns for insulation performed per NEI 02-01 Spring 2004
- AECL testing ofdebris load identfied Calcium Silicate (Cal-Sil) and Microtherm as particulates that affect RS and LHSI strainers August 2006 Dominion Nuclear Safety First 2 Enclosure 2
I ominion 4 Timeline
- DCP 07-004 removes Cal-Sil and Microtherm on Unit 2. DCP 05-014 installs sump strainers. Spring 2007
- DCP 07-129 removes Cal-Sil on Unit 1. DCP 05-013 installs sump strainers. Fall 2007
- Dominion letter summarizes resolution of GL 2004-02 exceptfor in-vessel effects.
February 2009 Dominion Nuclear Safety First 3 Enclosure 2
rDominion Timeline
- NRC acknowledges North Anna effort complete exceptfor in-vessel effects. May 2009 Dominion Nuclear Safety First 4 Enclosure 2
.sfJ 7
L Enclosure 2
IDominion Redesigned Sump NUCLEAR DESIGN INFORMATION PORTAL Figure 6.2-5 ARRANGEMENT CONTAINMENT SUMP STRAINER FOR UNIT 1 0
C PLAN ELEVATiON 2S-11 Dominion Nuclear Safety First 6 Enclosure 2
Dominion Redesigned Sump Dominion Nuclear Safety First 7 Enclosure 2
Dominion Sump Testing Initial Strainer Sizing Rig #33 Thin Bed RS 2.1 psi LHSI 1.1 psi Full Debris RS 0.14 psi LHSI 0.33 psi Dominion Nuclear Safety First 8 Enclosure 2
Dominion Verfication GSI 191 Implementation Microtherm and Cal-Sil insulation was replaced in the Zones OfInfluence (ZOl)
Physical implementation was completed during 2007
- Supplemental Response Serial No. 08-0019 All Microtherm removedfrom Unit 2 with none installed in Unit 1 Dominion Nuclear Safety First 9 Enclosure 2
Dominion Discovery Neutron Shielding Evaluation
- Neutron Saddle Shields degraded
- Subsequent Unit 1 extent ofcondition inspection noted some Neutron Saddle Shields also not intact Dominion Nuclear Safety First 10 Enclosure 2
Domjnie Neutron Saddle Shield Saddle Shields Vessel Shieldi Aimulus Wall Dominion Nuclear Safety First 11 Enclosure 2
Dominion Disco very Neutron Shielding Evaluation
- Design Change development for removing the Neutron Saddle Shields Reactor Vessel Nozzles
- Unit 2 was shutdown and inspections identfled Microtherm and Cal-Sil insulation in the ZOl
- Informational Report made to NRC upon shut down of Unit 2 Dominion Nuclear Safety First 12 Enclosure 2
Unit 1 Intermediate Elbow Microtherm Removal JIVDOmI nion 1/4 Micro therm encased in metal Dominion U
Nuclear Safety First 13 Enclosure 2
Unit 1 RCP Casing srDomi nion Arrow to Panel ofMicrotherm Insulation Dominion Nuclear Safety First 14 Enclosure 2
Unit 1 RCP Casing Dominion Arrow to panel ofMicrotherm Insulation Dominion K
Nuclear Safety First 15 Enclosure 2
Dominion Inspection
- Inspection procedures developed
- Training developed to qualify inspectors
- Complete review of the documentation Insulation vendor drawings S& W design changes for specifications associated with insulation Insulation specification changes Design Changes which could have impacted insulation Dominion Nuclear Safety First 16 Enclosure 2
Dominion Inspection
- Specialized Inspection Team established QualfIed Inspectors (2), Insulator, QMT Hand-over-hand inspections ofpiing and components Dominion Nuclear Safety First 17 Enclosure 2
As Found Insulation Dominion (Inside Zones ofInfluence)
Unit 1 Unit 2 Microtherm 5811 3 62ft Cal Sil 3 8ft 3 9ft Dominion U
Nuclear Safety First 18 Enclosure 2
Dominion Remediation
- Unacceptable insulation (Cal-Sil and/or Microtherm) was fully remediated when identified during walk downs within the ZOIs for Unitsl&2
- Microtherm outside ZOl was verified to be encased Dominion Nuclear Safety First 19 Enclosure 2
Dominion 2-RH-MO V-2 700 Remedia ted Dominion Nuclear Safety First Enclosure 2
Dominion Operabiiity Impact
- Small break small amount offibrous material does not affect operability
- Medium break outside testing assumptions
- Large break outside testing assumptions
- PRA review appears to be Green Dominion Nuclear Safety First 21 Enclosure 2
Dominion
- Preliminary A flawed methodology used to determine types and quantities of insulation during the GSI-191 containment walkdowns, resulting in unacceptable insulation not being included in the containment debris inventory or subsequently remediated.
Incomplete as-built drawings Ineffective project management (inventory and remediation)
Ineffective oversight and over-reliance on vendor Dominion Nuclear Safety First Enclosure 2
I Dominion Corrective ii c ti ons A
- Microtherm and Cal-Sil was remediated in Unit 1 and 2 containments
- Insulation re-inventoried in containment
- Process improvements initiated Insulation changes reviewed by Engineering prior to work and are independently reviewed Insulation database changes are independently reviewed
- Pending completion ofRCEOO1O3O
- LER submittal by 11/23/10
- GL 2004-02 Response will be updated Dominion Nuclear Safety First Enclosure 2
Dominion Con c/usion
- Extent ofcondition for both units was promptly pursued
- Conservative decision making employed to shutdown and inspect Unit 2
- All discrepancies werefully remediated
- Unit 1 and 2 containment sumps are operable Dominion Nuclear Safety First Enclosure 2
IDominion Questions?
Dominion Nuclear Safety First 25 Enclosure 2