Letter Sequence Approval |
|---|
EPID:L-2022-LLA-0166, Proposed License Amendment Request to Revise Emergency Plan Staff Augmentation Times (Approved, Closed) |
|
MONTHYEARML22312A5502022-11-0707 November 2022 Proposed License Amendment Request to Revise Emergency Plan Staff Augmentation Times Project stage: Request ML22335A4842022-12-0101 December 2022 NRR E-mail Capture - Acceptance Review for LAR North Anna Power Station - Units 1 and 2 and Surry Power Station - Units 1 and 2 Emergency Plan Staff Augmentation Times (L-2022-LLA-0166) Project stage: Acceptance Review ML23089A3542023-03-30030 March 2023 Response to Request for Additional Information Regarding Proposed License Amendment Request to Revise Emergency Plan Staff Augmentation Times Project stage: Response to RAI PMNS20230615, Meeting with Virginia Electric and Power Company Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1 and 22023-05-11011 May 2023 Meeting with Virginia Electric and Power Company Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1 and 2 Project stage: Meeting ML23167B0502023-05-11011 May 2023, 26 June 2023 May 25, 2023, Public Meeting with VEPCO Concerning a License Amendment Request to Revise Emergency Plan Staff Augmentation Times Project stage: Request ML23152A0432023-06-22022 June 2023 Audit Plan License Amendment Requests to Change Emergency Plan Staff Augmentation Times Project stage: Other ML23167A7012023-06-26026 June 2023 Summary of Public Meeting with VEPCO Concerning a License Amendment Request to Revise Emergency Plan Staff Augmentation Times Project stage: Meeting ML23198A0322023-07-18018 July 2023 – Regulatory Audit Report Regarding Review of License Amendment to Modify Emergency Plan Staff Augmentation Times Project stage: Approval ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) Project stage: Draft RAI PMNS20231323, Meeting with Virginia Electric and Power Company Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1 and 22023-11-27027 November 2023 Meeting with Virginia Electric and Power Company Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1 and 2 Project stage: Meeting ML23345A1102023-11-27027 November 2023, 14 December 2023 December 7, 2023, Public Meeting with Virginia Electric and Power Company Concerning a License Amendment Request to Revise Emergency Augmentation Times for North Anna Station, Units 1 & 2, and Surry Station, Units 1 & 2 Project stage: Request ML23338A1522023-12-0707 December 2023 Public Meeting Slides for North Anna and Surry Emergency Plan Augmentation Times License Amendment Request Project stage: Meeting ML23345A1092023-12-14014 December 2023 December 7, 2023, Summary of Public Meeting with Virginia Electric and Power Company Concerning a License Amendment Request to Revise Emergency Augmentation Times for North Anna Station, Units 1 & 2, and Surry Station, Units 1 & 2 Project stage: Meeting ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times Project stage: Approval ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times Project stage: Approval 2023-05-11
[Table View] |
Text
June 12, 2024 Mr. Eric S. Carr, President Nuclear Operations and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
CORRECTION TO ISSUANCE OF AMENDMENT NOS. 297 AND 280 FOR NORTH ANNA POWER STATION, UNIT NOS. 1 AND 2, AND AMENDMENT NOS. 317 AND 317 FOR SURRY POWER STATION, UNIT NOS. 1 AND 2, REGARDING CHANGES TO EMERGENCY PLAN STAFF AUGMENTATION TIMES (EPID L-2022-LLA-0166)
Dear Eric Carr:
On April 22, 2024 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML24054A014), the U.S. Nuclear Regulatory Commission (NRC) issued Amendment No. 297 to Renewed Facility Operating License (RFOL) No. NPF-4 and Amendment No. 280 to RFOL No. NPF-7 for the North Anna Power Station, Unit Nos. 1 and 2, and Amendment No. 317 to Subsequent RFOL DPR-32 and Amendment No. 317 to Subsequent RFOL No. DPR-37 for the Surry Power Station, Unit Nos. 1 and 2.
The amendments approved changes to the Emergency Preparedness Plan related to the staff emergency plan augmentation times.
Subsequently, your staff identified an error in the associated safety evaluation (SE).
Specifically, the SE didnt reflect a change in the request from the February 5, 2024, supplement (ML24036A318). The paragraph in Section 3.1.1 of the SE should be modified with the following deletion and addition:
In its letter dated November 7, 2022, as supplemented by letters dated March 30, 2023, October 12, 2023, and February 5, 2024, Dominion proposed to extend the ERO augmentation time for the TSC and CERC, which provide relief and augmentation for the command and control function, from within 60 minutes and 75 minutes, respectively, to within 90 minutes of an Alert or greater emergency classification. Dominion states that the two Unit Supervisors (Senior Reactor Operators) noted in the proposed North Anna and Surry Table 5.1 provide Control Room oversight and direct plant operations as required by Technical Specifications. The Operations Shift Manager, who is the third Senior Reactor Operator, provides emergency preparedness (EP) command and-control functions, including event classification and oversight of event response. The on-shift operations staff administrative requirements for North Anna and Surry as noted in the Dominion Fleet Procedure for Conduct of Operations exceed the
number of senior operators required by 10 CFR 50.54(m) and site Technical Specifications. The proposed change will maintain shift staffing consistent with the existing administrative procedures.
If you have any questions, please contact me at 301-415-2481, or via email at Ed.Miller@nrc.gov.
Sincerely,
/RA/
G. Edward Miller, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-338, 50-339, 50-280, and 50-281 cc: Listserv
Correction Letter: ML24143A162 OFFICE NRR/DORL/LPL2-1/PM NRR/DORL/LPL2-1/LA NRR/DORL/LPL2-1/BC NRR/DORL/LPL2-1/PM NAME GEMiller KGoldstein MMarkley GEMiller DATE 6/11/2024 05/23/2024 6/12/2024 6/12/2024