Category:Letter
MONTHYEARIR 05000338/20240032024-10-28028 October 2024 – Integrated Inspection Report 05000338-2024003 and 05000339-2024003 ML24283A0392024-10-0909 October 2024 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.D ML24281A1372024-10-0707 October 2024 ISFSI - Submittal of Cask Registration for Spent Fuel Storage 05000338/LER-2024-001-01, Automatic Reactor Trip Due to Prni High Negative Rate2024-09-24024 September 2024 Automatic Reactor Trip Due to Prni High Negative Rate IR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter ML24243A0872024-09-20020 September 2024 Response to EPA Comments Regarding the Final Site Specific Supplement to the Generic Eist for License Renewal North Anna Power Station, Units 1 and 2 IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) 05000339/LER-2024-001-01, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant 05000338/LER-2024-001, Automatic Reactor Trip Due to Prni High Negative Rate2024-07-25025 July 2024 Automatic Reactor Trip Due to Prni High Negative Rate ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code 05000339/LER-2024-001, Loss of Generator Field for 2J EDG During 2-PT-82.282024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 ML24165A1462024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 IR 05000338/20240102024-05-24024 May 2024 NRC Fire Protection Team Inspection (FPTI) Report 05000338/2024010 and 05000339/2024010 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24110A1462024-04-18018 April 2024 Independent Spent Fuel Storage Installation (Sfsi) - Annual Radiological Environmental Operating Report ML24110A1502024-04-18018 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24110A1392024-04-18018 April 2024 Annual Environmental Operating Report ML24087A0572024-04-16016 April 2024 Correction to Issuance of Amendment Nos. 296 and 279 ML24088A2692024-03-27027 March 2024 Core Operating Limits Report Cycle 31 Pattern Sos Revision 0 ML24086A4292024-03-25025 March 2024 Response to Request for Additional Information Associated with Alternative Request N1-I5-NDE-007 Request to Deter Additional Required Reactor Coolant Pump Casing Inspection 2024-09-24
[Table view] |
Text
Eric S. Carr, President Nuclear Operations and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Blvd.
Glen Allen, VA 29060
SUBJECT:
ISSUANCE OF SUBSEQUENT RENEWED FACILITY OPERATING LICENSE NOS. NPF-4 AND NPF-7 FOR NORTH ANNA POWER STATION, UNITS 1 AND 2
Dear Eric Carr:
The U.S. Nuclear Regulatory Commission (NRC) has issued Subsequent Renewed Facility Operating License Nos. NPF-4 and NPF-7 to Virginia Electric and Power Company (Dominion),
for North Anna Power Station, Units 1 and 2 (North Anna), respectively. The NRC issued the subsequent renewed facility operating licenses upon completion of the NRC staffs review of your application dated August 24, 2020 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML20246G703), as supplemented by the following letters:
Supplements to Application ADAMS Accession Number February 4, 2021 ML21035A303 March 17, 2021 ML21076B025 March 24, 2021 ML21084A182 April 1, 2021 ML21091A186 April 29, 2021 ML21119A287 May 27, 2021 ML21147A293 July 29, 2021 ML21210A396 August 5, 2021 ML21217A187 August 26, 2021 ML21238A297 December 6, 2021 ML21341B437 September 28, 2022 ML22272A041 Subsequent Renewed Facility Operating License Nos. NPF-4 and NPF-7 for North Anna will expire at midnight on April 1, 2058, for Unit 1, and August 21, 2060, for Unit 2, respectively.
The technical basis for issuing the subsequent renewed facility operating licenses for North Anna is set forth in Safety Evaluation Report Related to the Subsequent License Renewal of North Anna Power Station, Units 1 and 2 - Final Report (ML21354A174). August 28, 2024 E Carr The results of the environmental review related to the issuance of the subsequent renewed licenses are given in the record of decision, which is provided as Enclosure 3 to this letter and in NUREG-1437, Supplement 7a, Second Renewal, "Site-Specific Environmental Impact Statement for License Renewal of Nuclear Plants, Regarding Subsequent License Renewal for North Anna Power Station Units 1 and 2, Final Report (ML24204A104). to this letter is Subsequent Renewed Facility Operating License No. NPF-4 and Technical Specifications for North Anna, Unit 1. to this letter is Subsequent Renewed Facility Operating License No. NPF-7 and Technical Specifications for North Anna, Unit 2. is the Record of Decision. is a draft copy of the related Federal Register notice of issuance of the renewed licenses as sent to the Office of the Federal Register for publication.
No technical changes were made to the Technical Specifications as a result of this subsequent license renewal.
If you have any questions regarding this issue, please feel free to contact Project Manager, Siva P. Lingam, by phone at 301-415-1564 or by e-mail at Siva.Lingam@nrc.gov.
Sincerely, Michele Sampson, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-338 and 50-339
Enclosures:
- 1. North Anna, Unit 1 Subsequent Renewed Facility Operating License and Technical Specifications
- 2. North Anna, Unit 2 Subsequent Renewed Facility Operating License and Technical Specifications
- 3. Record of Decision
- 4. Copy of draft Federal Register notice cc: Listserv Signed by Sampson, Michele on 08/28/24
Package: ML24215A220 Letter: ML24215A262 Subsequent Renewed License, Unit 1: ML24215A263 Subsequent Renewed License, Unit 2: ML24215A264 Record of Decision: ML24215A265 Federal Register Notice: ML24215A266
- via e-mail NRR-106 OFFICE PM:DNRL:NLRP* PM:NMSS REFS* LA:DNRL:NLRP* Tech Editor*
NAME SLingam TTran KBratcher JDougherty DATE 08/2/2024 08/02/2024 08/06/2024 08/12/2024 OFFICE BC:DORL* BC:NMSS:REFS* BC:DNRL:NLRP* OGC (NLO)*
NAME MMarkley SKoenick LGibson STurk DATE 08/14/2024 08/13/2024 08/12/2024 08/22/2024 OFFICE D:DNRL* OD:NRR* D:DNRL*
NAME BSmith: SLee for AVeil MSampson DATE 08/23/2024 08/26/2024
Enclosure 1
North Anna Power Station, Unit 1
Subsequent Renewed Facility Operating License:
ADAMS Accession No. ML24215A263
Technical Specifications:
ADAMS Accession No. ML052990145
The Technical Specifications did not change as a result of the subsequent renewal of the North Anna Power Station, Unit 1, license.
Enclosure 1 Enclosure 2
North Anna Power Station, Unit 2
Subsequent Renewed Facility Operating License:
ADAMS Accession No. ML24215A264
Technical Specifications:
ADAMS Accession No. ML052990147
The Technical Specifications did not change as a result of the subsequent renewal of the North Anna Power Station, Unit 2, license.
Enclosure 2 Enclosure 3
North Anna Power Station, Units 1 and 2 Subsequent License Renewal Record of Decision
ADAMS Accession No. ML24215A265
Enclosure 3 Enclosure 4
Copy of the Draft Federal Register Notice of Subsequent Renewed Facility Operating Licenses North Anna Power Station, Units 1 and 2
ADAMS Accession No. ML24215A266
Enclosure 4