Subsequent License Renewal Pre-Application - Safety Coordination Meeting North Anna Power Station, Units 1 and 2 April 9, 2020
Agenda
- Introductions / Contact Information
- Subsequent License Renewal Review Process and Inputs into NRC Licensing Decision
- Review Schedule Overview
- Conclusion / Questions 2
Current Contact Information
- Safety Project Managers Lauren Gibson Angela Wu 301-415-1056 301-415-2995 Lauren.Gibson@nrc.gov Angela.Wu@nrc.gov
- Environmental Project Manager Lois James 301-415-3306 Lois.James@nrc.gov 3
Subsequent License Renewal Review Process and Inputs into NRC Licensing Decision 4
Environmental Review (10 CFR 51)
NRC Renewal Decision (10 CFR 54.29)
Subsequent License Renewal Application (SLRA) Accepted Safety Review (10 CFR 54)
ACRS Recommendation (10 CFR54.25)
Hearings*
Safety Review 5
Issue Safety Evaluation Report (SER)
Acceptance Review Operating Experience Audit In-Office Review In-Office Audit On-Site Audit
Tentative Review Schedule 6
Activity Estimated Date Application Submitted 9/30/2020 Project Start Date (LRA Acceptance) 11/9/2020 Operating Experience Audit November 2020 In-Office Audit January 2020 Safety Evaluation Report October 2021 Advisory Committee on Reactor Safeguards Full Committee Meeting December 2021 Licensing Decision March 2020
Questions 7