Subsequent License Renewal Pre-Application - Safety Coordination Meeting North Anna Power Station, Units 1 and 2 April 9, 2020

Agenda

  • Introductions / Contact Information
  • Review Schedule Overview
  • Conclusion / Questions 2

Current Contact Information

  • Safety Project Managers Lauren Gibson Angela Wu 301-415-1056 301-415-2995 Lauren.Gibson@nrc.gov Angela.Wu@nrc.gov
  • Environmental Project Manager Lois James 301-415-3306 Lois.James@nrc.gov 3

Subsequent License Renewal Review Process and Inputs into NRC Licensing Decision 4

Environmental Review (10 CFR 51)

NRC Renewal Decision (10 CFR 54.29)

Subsequent License Renewal Application (SLRA) Accepted Safety Review (10 CFR 54)

ACRS Recommendation (10 CFR54.25)

Hearings*

10 CFR 2

Safety Review 5

Issue Safety Evaluation Report (SER)

Acceptance Review Operating Experience Audit In-Office Review In-Office Audit On-Site Audit

Tentative Review Schedule 6

Activity Estimated Date Application Submitted 9/30/2020 Project Start Date (LRA Acceptance) 11/9/2020 Operating Experience Audit November 2020 In-Office Audit January 2020 Safety Evaluation Report October 2021 Advisory Committee on Reactor Safeguards Full Committee Meeting December 2021 Licensing Decision March 2020

Questions 7