ML20099F299

From kanterella
Jump to navigation Jump to search
NRC Slides for North Anna pre-app April 9
ML20099F299
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 04/09/2020
From:
Office of Nuclear Reactor Regulation
To:
References
Download: ML20099F299 (7)


Text

Subsequent License Renewal Pre-Application - Safety Coordination Meeting North Anna Power Station, Units 1 and 2 April 9, 2020

Agenda

  • Introductions / Contact Information
  • Review Schedule Overview
  • Conclusion / Questions 2

Current Contact Information

  • Safety Project Managers Lauren Gibson Angela Wu 301-415-1056 301-415-2995 Lauren.Gibson@nrc.gov Angela.Wu@nrc.gov
  • Environmental Project Manager Lois James 301-415-3306 Lois.James@nrc.gov 3

Subsequent License Renewal Review Process and Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

Subsequent License NRC Renewal Renewal Application Hearings* Decision (SLRA) Accepted 10 CFR 2 (10 CFR 54.29)

Safety ACRS Review Recommendation (10 CFR 54) (10 CFR54.25) 4

Safety Review Acceptance Review Operating In-Office Review Experience On-Site Audit In-Office Audit Audit Issue Safety Evaluation Report (SER) 5

Tentative Review Schedule Activity Estimated Date Application Submitted 9/30/2020 Project Start Date (LRA 11/9/2020 Acceptance)

Operating Experience Audit November 2020 In-Office Audit January 2020 Safety Evaluation Report October 2021 Advisory Committee on Reactor Safeguards Full December 2021 Committee Meeting Licensing Decision March 2020 6

Questions 7