Other: ML20258A284, ML20269A465, ML20276A192, ML20303A199, ML21036A060, ML21067A504, ML21067A507, ML21084A182, ML21091A004, ML21097A027, ML21145A217, ML21217A187, ML21239A064, ML21239A066, ML21239A068, ML21256A067, ML21256A069, ML21312A002, ML21312A003, ML21312A007, PMNS20211071, Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - Safety Issue - Cyclic Fatigue, PMNS20211128, Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - an Inconsistency in Documentation Regarding Reactor Coolant Pump Code Case N 481, TLAA 4.7.6
|
MONTHYEARML20246G6972020-08-24024 August 2020 Application for Subsequent Renewed Operating Licenses Project stage: Request ML20269A4652020-10-0606 October 2020 SLRA - Portal Letter Project stage: Other ML20276A1922020-10-0909 October 2020 Subsequent License Renewal Aging Management Audit Plan Project stage: Other ML20258A2842020-10-13013 October 2020 SLRA - Acceptance and Opportunity for Hearing Letter Project stage: Other ML20303A1992020-10-29029 October 2020 Subsequent License Renewal Safety Project Management Assignment Project stage: Other ML21035A3032021-02-0404 February 2021 (Naps), Units 1 and 2 - Update to Subsequent License Renewal Application (SLRA) Supplement 1 Project stage: Supplement ML21063A5602021-03-0404 March 2021 Final Request for Additional Information Set 1 - North Anna SLRA Safety Review (EPID L-2020-SLR-0000) - Enclosure Project stage: RAI ML21063A5522021-03-0404 March 2021 Final Request for Additional Information Set 1 - North Anna SLRA Safety Review (EPID L-2020-SLR-0000) - Email Project stage: RAI ML21067A5042021-03-0808 March 2021 Final Request for Confirmation of Information (RCI) Set 1 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email Project stage: Other ML21067A5072021-03-0808 March 2021 Final Request for Confirmation of Information (RCI) Set 1 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure Project stage: Other ML21076B0252021-03-17017 March 2021 Update to Subsequent License Renewal Application, Supplement 2 Project stage: Supplement ML21084A1822021-03-24024 March 2021 Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information for the Safety Review - Set 1 Project stage: Other ML21091A0042021-04-0101 April 2021 SLRA Safety Review - Withdrawn Requests for Information (EPID No. L-2020-SLR-0000) - Enclosure 2 Project stage: Other ML21091A1872021-04-0101 April 2021 Response to NRC Request for Additional Information Regarding Safety Review - Set 1 & Clarification to Aging Management of Fire Protection System Lined Ductile Iron Valves Project stage: Supplement ML21091A0022021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email Project stage: RAI ML21091A0032021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure 1 - RAIs Project stage: RAI ML21036A0602021-04-0808 April 2021 Report for the Aging Management Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML21097A0272021-04-14014 April 2021 Request for Withholding from Public Disclosure Regarding Subsequent License Renewal Application Project stage: Other ML21104A0372021-04-15015 April 2021 Request for Withholding Information Regarding Subsequent License Renewal Application Project stage: Withholding Request Acceptance ML21119A2872021-04-29029 April 2021 (Naps), Unit 1 and 2 - Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Safety Review - Set 2 and Flow Accelerated Corrosion Program Enhancement Completion Project stage: Response to RAI ML21123A2972021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail Project stage: RAI ML21123A2982021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure Project stage: RAI PMNS20210548, Discussion of Dominions Response to Select Staff RAIs on North Anna Subsequent License Renewal Application2021-05-12012 May 2021 Discussion of Dominions Response to Select Staff RAIs on North Anna Subsequent License Renewal Application Project stage: RAI ML21132A2892021-05-13013 May 2021 SLRA RAI Response Public Meeting Project stage: RAI ML21145A2172021-05-13013 May 2021 Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion Slides Project stage: Other ML21221A1542021-05-27027 May 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Dominion Slides Project stage: Meeting ML21147A2932021-05-27027 May 2021 (Naps), Units 1 and 2 Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Safety Review - Set 3 and Administrative Change to SLRA Table A4.0-1, Item 25 Project stage: Response to RAI ML21221A1482021-05-27027 May 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides Project stage: RAI PMNS20210666, Discussion of Dominions Response to Select Staff RAIs on North Anna Subsequent License Renewal Application2021-05-27027 May 2021 Discussion of Dominions Response to Select Staff RAIs on North Anna Subsequent License Renewal Application Project stage: RAI ML21145A2122021-06-0909 June 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Memoranda Project stage: RAI ML21145A2152021-06-0909 June 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Enclosure 2 - List of Attendees Project stage: RAI ML21145A2132021-06-0909 June 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Enclosure 1 - Summary Project stage: RAI PMNS20210777, Discussion of Dominions Response to Select Staff RAIs on North Anna Subsequent License Renewal Application - Topics to Be Determined2021-06-15015 June 2021 Discussion of Dominions Response to Select Staff RAIs on North Anna Subsequent License Renewal Application - Topics to Be Determined Project stage: RAI ML21166A3512021-06-15015 June 2021 Safety RAIs - Set 4 - Draft Project stage: Draft RAI ML21174A3042021-06-23023 June 2021 SLRA RAI Response Public Meeting - 21-06-24 Project stage: RAI PMNS20210778, Discussion of Dominions Response to Select Staff RAIs on North Anna Subsequent License Renewal Application - Topics to Be Determined2021-06-23023 June 2021 Discussion of Dominions Response to Select Staff RAIs on North Anna Subsequent License Renewal Application - Topics to Be Determined Project stage: RAI ML21174A1952021-06-23023 June 2021 Safety RAIs - Set Y - Draft - Enclosure Project stage: Draft RAI ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email Project stage: RAI ML21188A1652021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure Project stage: RAI ML21210A3962021-07-29029 July 2021 (Naps), Units 1 and 2 - Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Safety Review - Set 4 and Supplement 3 Project stage: Supplement ML21217A1872021-08-0505 August 2021 (Naps), Units 1 and 2 - Subsequent License Renewal Application First 10 CFR 54.21 (B) Annual Amendment Project stage: Other ML21221A1362021-08-10010 August 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application Project stage: RAI ML21221A1412021-08-10010 August 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Attendees Project stage: RAI ML21221A1382021-08-10010 August 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Meeting Summary Project stage: RAI ML21225A5642021-08-13013 August 2021 Discussion Point for Public Meeting Regarding Fire Protection Piping Cyclic Loading - Presentation Project stage: Meeting PMNS20211071, Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - Safety Issue - Cyclic Fatigue2021-08-13013 August 2021 Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - Safety Issue - Cyclic Fatigue Project stage: Other ML21225A5512021-08-13013 August 2021 Discussion Point for Public Meeting Regarding Fire Protection Piping Cyclic Loading - Transmittal E-mail Project stage: Meeting ML21238A0982021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure Project stage: Draft RAI ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email Project stage: Draft RAI ML21238A2972021-08-26026 August 2021 Subsequent License Renewal Application Supplement 4 Project stage: Supplement 2021-04-08
[Table View] |
Text
Enclosure 1 U.S. Nuclear Regulatory Commission Public Meeting Summary
Title:
Discussion of Dominion's Response to Select Staff RAIs on North Anna Subsequent License Renewal Application Date of Meeting: May 27, 2021, 2:00 pm - 5:00 pm Location:
Webinar Type of Meeting: This is an Observation Meeting. This is a meeting in which attendees will have an opportunity to observe the U.S. Nuclear Regulatory Commission (NRC) performing its regulatory function or discussing regulatory issues. Attendees will have an opportunity to ask questions of the NRC staff or make comments about the issues discussed following the business portion of the meeting; however, the NRC is not actively soliciting comments toward regulatory decisions at this meeting.
Purpose of the Meeting(s):
To discuss Virginia Electric and Power Company's (Dominion Energy's) responses to select NRC requests for additional information (RAIs) associated with the safety review of the North Anna Power Station, Units 1 and 2 (NAPS) Subsequent License Renewal Application (SLRA).
To enable the staff to gain a better understanding of Dominion Energy's approach to aging management and to formulate a path forward.
General Details:
The NRC staff held a public, observational meeting with Dominion Energy to discuss responses to select NRC RAIs associated with the safety review of the NAPS SLRA. The meeting began at 2:00 pm and ended approximately at 5:00 pm. There were 13 NRC staff members, 8 applicant staff and contractor, and four members of the public. The meeting began with introductions of the NRC staff, Dominion Energy staff and contractor, and members of the public who wished to introduce themselves.
Summary of Meeting:
B2.1.7-1, Pressurized-Water Reactor Vessel Internals The staff explained that it had reviewed the slides and did not have further questions on this item. The staff finds the proposal acceptable, if provided on the docket.
B2.1.15-1 Basis for 20-Year Replacement Frequency for Diesel Engine Heat Exchanger The staff explained that it had reviewed the slides and did not have further questions on this item. The staff finds the proposal acceptable, if provided on the docket.
B2.1.27-1 Cyclic Fatigue of Buried Gray Cast Iron Using Jockey Pump Monitoring Dominion began by describing how the jockey pump monitoring is actually accomplished.
Dominion stated that it believed that jockey pump monitoring can identify a leak. The current system is continuous monitoring of the main pumps in the control room. Dominion
should be able to make trends and identify anomalies, such as test runs. The jockey pump run time will be monitored monthly to detect and prevent unexpected pump starts.
Installation of jockey pump run time totalizer to monitor has been requested to facilitate this monitoring.
The staff questioned the periodicity of the monitoring and whether leakage could be detected and addressed within the proposed monthly periodicity.
Dominion will continue to consider the staffs concerns and the staff will continue to consider Dominions proposal to use jockey pump monitoring to identify leakage in the fire water piping.
B2.1.21-1 Basis for Extent of Inspections for Selective Leaching Dominion discussed that they would be using a graded approach to dealing with selective leaching similar to aging related cracking. For example, in category A, there is no indication of aging relating cracking (or selective leaching). In category B, there is some indicating of aging related cracking (or selective leaching) but actions were taken to mitigate and considered successful because no additional failures were identified. In category C, there is active aging related degradation (or selective leaching) and no mitigation efforts.
Dominion is recommending using category B and would conduct a one-time inspection for selective leaching of grey cast iron with additional work as the opportunities arise.
Dominion further explained that it would complete three to four digs to get the 25 inspections per unit prior to the subsequent period of extended operation, Including two destructive examination per unit.
B2.1.21-2 Basis for Single 10-Foot Sample for Selective Leaching Dominion summarized their position as follows:
Periodically excavating one 10-foot piping segment per unit will satisfy the visual inspections (8 samples) and the mandatory destructive examination (2 samples).
o Selection of piping excavation location consistent with leading sample criteria o NUREG-2191 considers each 1-foot piping segment (or equivalent 1-foot segment) as one component: M33, M36, M38 (any combination of 1-foot lengths), M41 (inspections based on 10-foot lengths), and M42 o Opportunistic inspections based on enhanced jockey pump monitoring to target specific piping leakage issues will augment periodic sampling - informed opportunistic inspections as a result of enhanced jockey pump Dominion stated that it already has a commitment to restore cathodic protection five years prior to entering the subsequent period of operation.
In order to understand what portions of the fire protection system are covered by existing cathodic protection, Dominion will post a map of the cathodic protection on the portal and a
drawing of the fire protection runs. Combining the two should show what fire protection pipes are covered by the existing cathodic protection.
B2.1.35-1, RG 1.127, Inspection of Water-Control Structures Associated with Nuclear Power Plants Dominion provided slides for discussion, but the topic was not discussed.
Public Participation Themes:
There were four members of the public on the phone. One member of the public spoke.
Erica Grey stated that all meetings should be recorded and transcribed. Further, Ms. Grey stated that North Anna should not be allowed to do any generic analysis. It is a unique based on seismic concerns (it actually experienced an earthquake) and analysis and test should be completed on piping etc.
Action Items/Next Steps:
The NRC staff will prepare and issue a meeting summary.
Attachments:
Meeting description and agenda - ADAMS Accession No. ML21147A044 NRC slide presentation - ADAMS Accession No. ML21221A148 Dominion slide presentation - ADAMS Accession No. ML21221A154