ML21174A304
Letter Sequence RAI | |
---|---|
EPID:L-2020-SLR-0000, Application for Subsequent Renewed Operating Licenses (Approved, Closed) | |
Initiation
Administration Questions
Answers Results
Other: ML20246G698, ML20258A284, ML20269A465, ML20274A111, ML20274A198, ML20276A192, ML20303A199, ML20307A177, ML20322A052, ML20337A022, ML20351A388, ML21025A340, ML21036A060, ML21067A504, ML21067A507, ML21084A182, ML21091A004, ML21097A027, ML21145A217, ML21181A186, ML21217A187, ML21239A064, ML21239A066, ML21239A068, ML21256A067, ML21256A069, ML21312A002, ML21312A003, ML21312A007, ML23062A466, ML24206A043, PMNS20211071, Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - Safety Issue - Cyclic Fatigue, PMNS20211128, Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - an Inconsistency in Documentation Regarding Reactor Coolant Pump Code Case N 481, TLAA 4.7.6 | |
MONTHYEARML20246G6982020-08-24024 August 2020
[Table View]Appendix E: Applicants Environmental Report Subsequent Operating License Renewal Stage North Anna Power Station Units 1 and 2 Project stage: Other ML20246G6972020-08-24024 August 2020 Application for Subsequent Renewed Operating Licenses Project stage: Request ML20269A4652020-10-0606 October 2020 SLRA - Portal Letter Project stage: Other ML20276A1922020-10-0909 October 2020 Subsequent License Renewal Aging Management Audit Plan Project stage: Other ML20258A2842020-10-13013 October 2020 SLRA - Acceptance and Opportunity for Hearing Letter Project stage: Other ML20274A1112020-10-19019 October 2020 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID No. L-2020-SLE-0000) - Letter to Applicant Project stage: Other ML20274A1982020-10-19019 October 2020 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID No. L-2020-SLE-0000) - Federal Register Notice Project stage: Other PMNS20201188, Environmental Scoping Meeting Related to the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application2020-10-28028 October 2020 Environmental Scoping Meeting Related to the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application Project stage: Meeting ML20303A1992020-10-29029 October 2020 Subsequent License Renewal Safety Project Management Assignment Project stage: Other ML20307A1772020-11-0404 November 2020 NRC Presentation North Anna Power Station, Units 1 and 2 Subsequent License Renewal Review Project stage: Other ML20317A2062020-11-12012 November 2020 Environmental Scoping Meeting Related to the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application Project stage: Meeting ML20324A6792020-11-13013 November 2020 Comment (1) of Kevin Quigley on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6832020-11-13013 November 2020 Comment (5) from Joseph Sucha on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6822020-11-13013 November 2020 Comment (4) from Keith Scott on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6812020-11-13013 November 2020 Comment (3) from Frederick Gerloff on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6802020-11-13013 November 2020 Comment (2) from Luther Jones on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0512020-11-14014 November 2020 Comment (8) of Lisa Hicks-Thomas on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20324A6862020-11-14014 November 2020 Comment (7) from Nancy Ashberry on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6852020-11-14014 November 2020 Comment (6) from Thomas Owens on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0532020-11-15015 November 2020 Comment (9) of Martin Blough on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0582020-11-16016 November 2020 Comment (12) from Melissa Haley on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0572020-11-16016 November 2020 Comment (11) of Lauren Lopez on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20325A0542020-11-16016 November 2020 Comment (10) of Michael Hamby on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0602020-11-17017 November 2020 Comment (13) of Terry Clouthier on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20329A4392020-11-17017 November 2020 Pamunkey Consultation Request_North Anna Power Station_17NOV20 Project stage: Request ML20325A0662020-11-18018 November 2020 Comment (18) from Jim Norvelle on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0612020-11-18018 November 2020 Comment (14) of Kevin Cordray on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0622020-11-18018 November 2020 Comment (15) from Jason Evans on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0632020-11-18018 November 2020 Comment (16) of Tracy Gill on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0652020-11-18018 November 2020 Comment (17) of Tommy Flynn on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1012020-11-18018 November 2020 Comment (28) from Ralph Joyce on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0682020-11-18018 November 2020 Comment (19) of Ronald Buchanan on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0712020-11-18018 November 2020 Comment (20) of Harold Vaughan on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0722020-11-18018 November 2020 Comment (21) of Mel Holley on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0732020-11-18018 November 2020 Comment (22) of Sarah Marshall on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0742020-11-18018 November 2020 Comment (23) of Andrew Moncol on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0752020-11-18018 November 2020 Comment (24) of Richard Zuercher on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20325A0922020-11-18018 November 2020 Comment (25) of J. Crouch on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0942020-11-18018 November 2020 Comment (26) from J. Crouch on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0972020-11-18018 November 2020 Comment (27) from Jenna Brown on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1132020-11-18018 November 2020 Comment (37) of Shawn Williams on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20325A1242020-11-18018 November 2020 Comment (42) of Edmond Longest on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1172020-11-18018 November 2020 Comment (39) from Carl Aimee Newcomb of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1152020-11-18018 November 2020 Comment (38) of Eric Hendrixson on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1042020-11-18018 November 2020 Comment (30) of David Strole on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1112020-11-18018 November 2020 Comment (35) of Greg Boutchyard on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1052020-11-18018 November 2020 Comment (31) from Carl Eng on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1072020-11-18018 November 2020 Comment (32) of Angela Baker on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1102020-11-18018 November 2020 Comment (34) of Terrance Perrone on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1122020-11-18018 November 2020 Comment (36) from Robert George on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request 2020-11-13 |
ML21174A304 | |
Person / Time | |
---|---|
Site: | North Anna |
Issue date: | 06/23/2021 |
From: | NRC/NRR/DNRL |
To: | |
James L, NRR/DNRL/NLRP, 301-415-3306 | |
Shared Package | |
James L M, NRR/DNRL/NLRP, 301-415-3306 | List: |
References | |
L-2020-SLR-0000 | |
Download: ML21174A304 (5) | |
Similar Documents at North Anna | |
---|---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24283A1442024-10-16016 October 2024
[Table view]Main Steam Line Break Accident Analysis LAR Pre-Application Meeting ML24247A0042024-09-0303 September 2024 SLR Efficiencies Public Meeting - NRC Presentation - September 5, 2024 ML24108A0712024-04-30030 April 2024 Combined - 2023 Annual Assessment Public Meeting Slides ML24029A2362024-01-30030 January 2024 Preliminary Results of the Environmental Review, Subsequent License Renewal ML23338A1522023-12-0707 December 2023 Public Meeting Slides for North Anna and Surry Emergency Plan Augmentation Times License Amendment Request ML23255A0992023-09-15015 September 2023 Slides for September 15, 2023 Public Meeting on Poanhi Seismic Evaluations ML23103A3482023-04-14014 April 2023 Annual Assessment Meeting Presentation for North Anna and Surry ML21221A0332022-06-17017 June 2022 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides ML21174A3042021-06-23023 June 2021 SLRA RAI Response Public Meeting - 21-06-24 ML21221A1542021-05-27027 May 2021 Meeting Summary: Discussion of Dominions Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Dominion Slides ML21145A2172021-05-13013 May 2021 Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion Slides ML21132A2892021-05-13013 May 2021 SLRA RAI Response Public Meeting ML21034A5972021-02-10010 February 2021 External Presentation Am Atkinson_Nrc ISG-06 Meeting Dominion Digital IC Project 02102021 ML20288A3472020-10-14014 October 2020 (COVID-19) Emergency Preparedness Exemption Pre-Application Meeting ML20099F2992020-04-0909 April 2020 NRC Slides for North Anna pre-app April 9 ML20099F2412020-04-0909 April 2020 Co., NRC Safety Pre& 8208;Application Meeting North Anna Power Station (NAPS) ML20098B6022020-04-0707 April 2020 Annual Assessment Meeting Presentation ML19297D1872019-11-18018 November 2019 Pre-Application Meeting - Dominion Slides ML18320A2502018-11-20020 November 2018 50.90 License Amendment Request - Dominion Fleet EAL Scheme Changes, November 20, 2018 Public Meeting ML18141A3072018-05-21021 May 2018 18 - SLR Status ML17123A2092017-05-0303 May 2017 Summary of Meeting to Discuss Annual Assessment of the North Anna Power Station, Units 1 and 2 with the Public for the Period of January 1, 2016 Through December 31, 2016 ML16124A7582016-05-0303 May 2016 April 14, 2016, Summer of Public Meeting - North Anna, Units 1 and 2 ML16124A7632016-05-0303 May 2016 April 14, 2016, Summary of Public Meeting - North Anna Power Station, Units 1 and 2 ML16104A3822016-04-26026 April 2016 New Fuel Storage Rack & SFP Criticality Analysis for April 26th 2016 Scheduled Category 1, Pre-Submittal Public Teleconference ML16104A3872016-04-13013 April 2016 Criticality Analysis Checklist for North Anna ML15273A4292015-09-29029 September 2015 Revised Slides for September 29, 2015 Meeting with Dominion Re North Anna ISFSI License Renewal ML15153A0452015-05-13013 May 2015 Revised North Anna ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15133A0822015-05-13013 May 2015 ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15128A5462015-05-0808 May 2015 Summary of Public Meeting with North Anna, Units 1 and 2 to Discuss the Annual Assessment with the Public ML14101A1202014-04-11011 April 2014 Public Meeting Summary - North Anna Power Station, Docket Nos. 50-338, 50-339 ML14058B1762014-03-0606 March 2014 Presentation Slides - North Anna ISFSI - High Burnup Dry Storage Confirmatory Data Project, TN-32 Storage Cask, Tom Brookmire, March 6, 2014, Docket No. 72-16, TAC No: L24886 ML14071A1672014-01-28028 January 2014 Enclosure 2: Presentation Slides - North Anna ISFSI TN-32 Cask and Pad 1 Assessments Following August 23, 2011, Central Virginia Earthquake ML13159A0092013-06-0404 June 2013 Notable Failures in Nondustructive Testing - June 4, 2013 Public Meeting ML12257A2342012-09-11011 September 2012 5-Hacker - North Anna Mockup and Search Unit Action Presentation Sept 10 ML12257A2002012-09-11011 September 2012 2-North Anna Extent of Condition Presentation 9-7-12 Sept 10 ML12131A5052012-05-0909 May 2012 Presentation for 2011 North Anna EOC Annual Assessment Meeting ML11305A0452011-11-0101 November 2011 Region II - North Anna Public Meeting Slides ML11305A0622011-11-0101 November 2011 Restart Readiness, Public Meeting PR2 ML11276A0242011-10-0303 October 2011 Slides-North Anna AIT Public Meeting October 3, 2011 ML1127701352011-10-0303 October 2011 Ltr to D. Heacock Re Participation in the Commission Meeting on the North Anna Plant on 10/21/11 ML11252A0062011-09-0808 September 2011 Dominion'S Slides Earthquake Response and North Anna Restart Readiness Demonstration Plan ML1124205512011-08-30030 August 2011 Seismic Event ML1110304942011-04-13013 April 2011 Public Meeting Attendees ML1110304982011-04-13013 April 2011 Public Meeting Handouts ML1032204442010-11-18018 November 2010 Public Meeting Summary - North Anna Power Station ML1020100212010-07-14014 July 2010 Nucler Power Station, Units 1 and 2, Westinghouse RFA-2 Fuel Transition Licensing Meeting Presentation Slides ML1012600332010-05-0505 May 2010 Meeting Posters ML1012600342010-05-0505 May 2010 Public Mtg. Slides ML0917610472009-08-0505 August 2009 ECCS Preacs Filtration Presentation ML0911000392009-04-17017 April 2009 Notice of Public Meeting Category 1 - Annual Assessment of North Anna Power Station 2024-09-03 |
Text
North Anna Units 1 and 2 SLRA Discussion of Dominion's Response to Select Staff RAIs on Subsequent License Renewal Application June 24, 2021
Ground Rules Observational Meeting
- Technical Discussion between NRC and Dominion regarding request for additional information (RAI) responses
- The public will have an opportunity at the end of the meeting to make comments or ask the NRC staff questions.
RAI Response Discussion
- Dominion will explain what current situation for each item
- NRC staff will ask questions and seek information and understanding
- Each item has been allotted 25 minutes Public Comment
- One member of the public will speak at a time.
- If you want to speak, raise your hand in Teams
- Each member will have three minutes. After which, the individual will be muted 2
Agenda
- Introduction
- Ground Rules
- RAI Response Discussion
- RAI B2.1.16-1a (Exception for Fire Pump Suction Screen Inspections)
- RAI B.2.1.17-2 (no justification for the exception between the recommended and proposed inspection frequency
- RAI B2.1.21-1a (no justification for using the extent of inspections)
- RAI B2.1.21-1a (single 10-foot piping section)
- RAI B2.1.27-1a (Cyclic Fatigue - Follow-Up)
- Public Comment
- Wrap-up 3
Public Comment
- Comments should be associated with the safety review of the North Anna Subsequent License Renewal Application
- The staff cannot address questions associated with the pending litigation
- Ground Rules
- Comments/questions should be directed to the NRC staff
- One member of the public will speak at a time.
- If you want to speak, raise your hand in Teams
- Each member will have three minutes. After which, the individual will be muted 4
Wrapup/Adjourn
- Thank you to all who participated and listened.
5