Nucler Power Station, Units 1 and 2, Westinghouse RFA-2 Fuel Transition Licensing Meeting Presentation Slides
ML102010021
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 07/14/2010
From:
Virginia Electric & Power Co (VEPCO)
To: V Sreenivas
Plant Licensing Branch II
Sreenivas V.NRR/DORL/LPL2-1 415-2597
References
Download: ML102010021 (11)


Text

North Anna Westinghouse RFA-2 Fuel Transition July 14, 2010

Objectives

1) Discuss Dominions Licensing Approach for Transitioning to the Westinghouse RFA-2 Fuel Product at North Anna 2
2) Provide Dominions Schedule of Submittals Required to Support the North Anna Fuel Transition
3) Discuss NRC Resources for November 2011 BELOCA Approval

Fuel Product Description

  • Removable Top Nozzle
  • 0.374 inch OD Fuel Rod with Optimized ZIRLO Cladding 3
  • Zirconium Diboride (ZrB2) Integrated Fuel Burnable Absorbers (IFBA)
  • Reduced Rod Bow Inconel Top Grid
  • Intermediate Flow Mixing Grids (3)
  • Inconel Protective Grid
  • Oxide Coated Cladding on Bottom Six Inches
  • Debris Filter Bottom Nozzle

Licensing Approach

  • Fuel Criteria Evaluation Process (FCEP) -

WCAP-12488-A

NSD NRC 97 5189

  • LTR-NRC-01-44
  • LTR-NRC-02 Applicability of WRB-2M DNB correlation to 17x17 RFA-2 fuel with or without IFM grids

Licensing Approach

  • Required NRC Submittals
1. Optimized ZIRLO - fuel cladding material 5
2. VIPRE-D WRB-2M DNB Correlation Implementation
3. BELOCA Methodology (WCAP-16009-P-A)

Schedule / Milestones

  • Transition is Approximately 50% Complete
  • North Anna RFA-2 Implementation
  • N1C23 Spring 2012 6

N1C23 Spring 2012

  • N2C23 Spring 2013
  • Optimized ZIRLO Submittal

- Currently with the NRC (Dominion Letter No.10-205, May 6, 2010)

- Requested NRC Approval May 2011

Schedule / Milestones

  • VIPRE-D WRB-2M Correlation

- Submit to NRC July 22, 2010

- Requested NRC Approval July 2011 7

  • BELOCA Analysis

- Submit to NRC November 2, 2010

- Requested NRC Approval November 2011

- Working with Vendor to Improve Submittal Schedule

BELOCA Analysis

  • License Amendment Request (LAR) adds ASTRUM methodology to T.S. 5.6.5 (COLR)

- ASTRUM methodology used for Best-Estimate LBLOCA analysis of RFA-2 fuel 8

- T.S. change adds ASTRUM analytical methodology topical report WCAP-16009-P-A to T.S. 5.6.5.b in support of core limits

  • Heat Flux Hot Channel Factor (FQ(Z))
  • Nuclear Enthalpy Rise Hot Channel Factor (FN H)

- Analysis description comparable to Surry submittal

  • Dominion letter 06-936 dated 11/16/06
  • NRC Safety Evaluation Report dated 9/6/07

BELOCA Analysis

  • Approved BELOCA Methodology

- WCAP-16009-P-A with one exception

- 9 node downcomer model 9

  • 3 axial nodes/radial segment aligned to each RCS loop

- Improved resolution of downcomer boiling phenomenon

- Multi-node model in ASTRUM approved by NRC for D.C. Cook (12 nodes for 4 RCS loops)

BELOCA Analysis

  • Unit-Specific Analyses

- Unit 1 - Upflow baffle/barrel configuration

- Unit 2 - Downflow baffle/barrel configuration U it ifi d l d f R

li ti L 10

- Unit-specific models used for Realistic Large Break LOCA analysis of AREVA Advanced Mark-BW fuel (UFSAR Section 15.4.1)

  • Same peaking factors as AREVA LBLOCA analysis in UFSAR Section 15.4.1

- FQ(Z) = 2.32

- FN H = 1.65

Questions?

Questions?

11