Summary of November 20, 2018, Pre Application Meeting with Dominion Energy Regarding the Planned License Amendment Request to Revise Emergency Action Levels
ML19144A129
Person / Time
Site: Millstone, Surry, North Anna  Dominion icon.png
Issue date: 05/30/2019
From: Hall J
Plant Licensing Branch II
To: Stoddard D
Dominion Nuclear
Hall J 415-4032
References
EPID L-2018-LRM-0086
Download: ML19144A129 (4)


Text

LICENSEE: Dominion Energy FACILITY: North Anna Power Station, Units 1 and 2; Surry Power Station, Units 1 and 2 and Millstone Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF NOVEMBER 20, 2018, PRE-APPLICATION MEETING WITH DOMINION ENERGY REGARDING THE PLANNED LICENSE AMENDMENT REQUEST TO REVISE EMERGENCY ACTION LEVELS (EPID L-2018-LRM-0086)

On November 20, 2018, a Category 1 public meeting via teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Dominion Energy (Dominion, or the licensee). This was a pre-application meeting to discuss proposed license amendment request (LAR) for the North Anna Power Station, Units 1 and 2 (North Anna), the Surry Power Station, Units 1 and 2 (Surry) and the Millstone Power Station, Units 2 and 3 (Millstone). The proposed LARs would revise each site's Emergency Plan to adopt changes to the Emergency Action Level (EAL) schemes in accordance with the guidance in the Nuclear Energy Institute (NEI) document NEI 99-01, Revision 6, "Development of Emergency Action Levels for Non-Passive Reactors," dated November 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12326A805).

The meeting was noticed on November 5, 2018 (ADAMS Accession No. ML18309A151). A list of participants is provided in the Enclosure. Dominion provided their presentation slides prior to the meeting; the slides can be found at ADAMS Accession No. ML18320A250.

During the meeting, Dominion's presentation described the current licensing basis for the EALs for each site, and the content, scope, and schedule for the proposed fleet license amendment request. Dominion highlighted the planned deviations from the NEI 99-01, Revision 6, guidance and will appropriately justify them in the LAR.

The NRC staff suggested that the licensee include EAL wallcharts in the LAR, consistent with the NEI 99-01, Revisio_n 6, guidance, and the licensee indicated their intent to do so.

Dominion subsequently submitted the license amendment request by letter dated January 4, 2019 (ADAMS Accession No. ML19011A237).

No regulatory decisions or commitments were made during the meeting. There were no public comments.

~ ~e~ ect Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-280, 50-281 50-338, 50-339 50-336 and 50-423

Enclosure:

List of Attendees cc: Listserv

LIST OF PARTICIPANTS NOVEMBER 20, 2018 PRE-APPLICATION MEETING WITH DOMINION ENERGY EMERGENCY ACTION LEVEL SCHEME CHANGE Nuclear Regulatory Commission Randy Hall Ray Hoffman Rich Guzman Alina Schiller Dominion Energy Craig Sly Diane Aitken Joe Graf Kelly Walker Bill Eakin Ed Collins Gary Miller Shayan Sinha Candy Lovett Mary Lou Calderone Robert Page Don Taylor Cynthia Warnecke Enclosure

ML19144A129 OFFICE DORL/LPL2-1/PM DORL/LPL2-1/LA DORL/LPL2-1 /BC DORL/LPL2-1 /PM NAME RHall KGoldstein MMarkley RHall DATE 5/30/19 5/30/19 5/30/19 5/30/19