ISFSI, Submittal of Cask Registration for Spent Fuel Storage
ML24241A069
Person / Time
Site: North Anna, 07201030  Dominion icon.png
Issue date: 08/06/2024
From: Lane N
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
18-306
Download: ML24241A069 (1)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 August 6, 2018 ATTN: Document Control Desk Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 VIRGINIA ELECTRIC AND POWER COMPANY Serial No.

NAPS/DPM Docket Nos.18-306 RO 50-338 50-339 72-56 License Nos. NPF-4/7 NORTH ANNA POWER STATION UNITS 1 AND 2 AND ISFSI SUBMITTAL OF CASK REGISTRATION FOR SPENT FUEL STORAGE Pursuant to 10 CFR 72.212, "Conditions of general license issued under 72.210,"

paragraph (b)(2), Virginia Electric and Power Company (Dominion) hereby provides the Nuclear Regulatory Commission (NRC) notification regarding registration of spent fuel storage casks approved under NRG Certificate of Compliance (CoC) No. 1030.

The required registration information is submitted within 30 days after using the Dry Shielded Canister (DSC), listed below, to store spent fuel. The information required per 10 CFR 72.212(b)(2) is provided as follows:

Licensee Name:

Licensee Address:

Reactor License Nos.:

Reactor Docket Nos.:

Cask Certificate No.:

Cask Model No.:

Cask Identification No.:

Cask Identification No.:

Cask Identification No.:

Virginia Electric and Power Company 5000 Dominion Boulevard Glen Allen, VA 23060 NPF-4/7 50-338/339 72-56 Coe 1030, Amendment 1 NUHOMS-HD 32PTH Canister DSC DOM-32PTH-063-D, Initial Use DSC DOM-32PTH-067-D, Initial Use DSC DOM-32PTH-068-D, Initial Use July 12, 2018 July 19, 2018 July 26, 2018 If you have any questions or require additional information, please contact Mr. Daniel McGinnis, Station Licensing, at (540) 894-2487.

Sincerely, 4L\\

N. Larry Lane Site Vice President Commitments made by this letter: None

cc:

U.S. Nuclear Regulatory Commission Regional Administrator - Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Mr. R. Hall NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, Maryland 20852-2738 Ms. K. R. Cotton NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, Maryland 20852-2738 NRC Senior Resident Inspector North Anna Power Station Serial No.18-306 Docket Nos. 50-338/339, 72-56 Submittal of Cask Registration For Spent Fuel Storage

be: (electronic distribution except as noted with *)

Mr. B. E. Standley - NAPS Mr. D. R. Taylor - NAPS Mr. B. M. Williams - NAPS Mr. R. L. Ridder - IN3SW Mr. D. D. Tomlinson - IN3SW Mr. B. H. Wakeman - IN3SW Mr. T. J. Szymanski - IN2SE Licensing File - IN2SE

  • Innsbrook Records Management - IN-GW*

Concurrence:

B. E. Standley D.R. Taylor Verification of Accuracy Serial No.18-306 Cask Registration Submittal be Page 1 of 1

1. Transmission of DSC DOM-32PTH-063-D Initial Loading Notification dated 07/12/18.
2. Transmission of DSC DOM-32PTH-067-D Initial Loading Notification dated 07/19/18.
3. Transmission of DSC DOM-32PTH-068-D Initial Loading Notification dated 07/26/18.

Action Plan:

1. None Changes to the UFSAR, USAR. QA Topical Report, ISFSI FSAR, DSAR or PSDAR
1. None