MONTHYEARML24029A2362024-01-30030 January 2024 Preliminary Results of the Environmental Review, Subsequent License Renewal ML23338A1522023-12-0707 December 2023 Public Meeting Slides for North Anna and Surry Emergency Plan Augmentation Times License Amendment Request ML23255A0992023-09-15015 September 2023 Slides for September 15, 2023 Public Meeting on Poanhi Seismic Evaluations ML23103A3482023-04-14014 April 2023 Annual Assessment Meeting Presentation for North Anna and Surry ML21221A0332022-06-17017 June 2022 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides ML21174A3042021-06-23023 June 2021 SLRA RAI Response Public Meeting - 21-06-24 ML21221A1542021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Dominion Slides ML21145A2172021-05-13013 May 2021 Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion Slides ML21132A2892021-05-13013 May 2021 SLRA RAI Response Public Meeting ML21034A5972021-02-10010 February 2021 External Presentation Am Atkinson_Nrc ISG-06 Meeting Dominion Digital IC Project 02102021 ML20288A3472020-10-14014 October 2020 (COVID-19) Emergency Preparedness Exemption Pre-Application Meeting ML20099F2992020-04-0909 April 2020 NRC Slides for North Anna pre-app April 9 ML20099F2412020-04-0909 April 2020 Co., NRC Safety Pre& 8208;Application Meeting North Anna Power Station (NAPS) ML20098B6022020-04-0707 April 2020 Annual Assessment Meeting Presentation ML19297D1872019-11-18018 November 2019 Pre-Application Meeting - Dominion Slides ML18320A2502018-11-20020 November 2018 50.90 License Amendment Request - Dominion Fleet EAL Scheme Changes, November 20, 2018 Public Meeting ML18141A3072018-05-21021 May 2018 18 - SLR Status ML17123A2092017-05-0303 May 2017 Summary of Meeting to Discuss Annual Assessment of the North Anna Power Station, Units 1 and 2 with the Public for the Period of January 1, 2016 Through December 31, 2016 ML16124A7582016-05-0303 May 2016 April 14, 2016, Summer of Public Meeting - North Anna, Units 1 and 2 ML16124A7632016-05-0303 May 2016 April 14, 2016, Summary of Public Meeting - North Anna Power Station, Units 1 and 2 ML16104A3822016-04-26026 April 2016 New Fuel Storage Rack & SFP Criticality Analysis for April 26th 2016 Scheduled Category 1, Pre-Submittal Public Teleconference ML16104A3872016-04-13013 April 2016 Criticality Analysis Checklist for North Anna ML15273A4292015-09-29029 September 2015 Revised Slides for September 29, 2015 Meeting with Dominion Re North Anna ISFSI License Renewal ML15153A0452015-05-13013 May 2015 Revised North Anna ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15133A0822015-05-13013 May 2015 ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15128A5462015-05-0808 May 2015 Summary of Public Meeting with North Anna, Units 1 and 2 to Discuss the Annual Assessment with the Public ML14101A1202014-04-11011 April 2014 Public Meeting Summary - North Anna Power Station, Docket Nos. 50-338, 50-339 ML14058B1762014-03-0606 March 2014 Presentation Slides - North Anna ISFSI - High Burnup Dry Storage Confirmatory Data Project, TN-32 Storage Cask, Tom Brookmire, March 6, 2014, Docket No. 72-16, TAC No: L24886 ML14071A1672014-01-28028 January 2014 Enclosure 2: Presentation Slides - North Anna ISFSI TN-32 Cask and Pad 1 Assessments Following August 23, 2011, Central Virginia Earthquake ML13159A0092013-06-0404 June 2013 Notable Failures in Nondustructive Testing - June 4, 2013 Public Meeting ML12257A2002012-09-11011 September 2012 2-North Anna Extent of Condition Presentation 9-7-12 Sept 10 ML12257A2342012-09-11011 September 2012 5-Hacker - North Anna Mockup and Search Unit Action Presentation Sept 10 ML12131A5052012-05-0909 May 2012 Presentation for 2011 North Anna EOC Annual Assessment Meeting ML11305A0452011-11-0101 November 2011 Region II - North Anna Public Meeting Slides ML11305A0622011-11-0101 November 2011 Restart Readiness, Public Meeting PR2 ML11276A0242011-10-0303 October 2011 Slides-North Anna AIT Public Meeting October 3, 2011 ML1127701352011-10-0303 October 2011 Ltr to D. Heacock Re Participation in the Commission Meeting on the North Anna Plant on 10/21/11 ML11252A0062011-09-0808 September 2011 Dominion'S Slides Earthquake Response and North Anna Restart Readiness Demonstration Plan ML1124205512011-08-30030 August 2011 Seismic Event ML1110304982011-04-13013 April 2011 Public Meeting Handouts ML1110304942011-04-13013 April 2011 Public Meeting Attendees ML1032204442010-11-18018 November 2010 Public Meeting Summary - North Anna Power Station ML1020100212010-07-14014 July 2010 Nucler Power Station, Units 1 and 2, Westinghouse RFA-2 Fuel Transition Licensing Meeting Presentation Slides ML1012600332010-05-0505 May 2010 Meeting Posters ML1012600342010-05-0505 May 2010 Public Mtg. Slides ML0917610472009-08-0505 August 2009 ECCS Preacs Filtration Presentation ML0911000392009-04-17017 April 2009 Notice of Public Meeting Category 1 - Annual Assessment of North Anna Power Station ML0820501832008-07-23023 July 2008 Meeting Announcement - Summary of Public Meeting Category 1 - Performance Discussion Meeting, North Anna Power Station ML0812008742008-03-24024 March 2008 Annual Assessment Meeting Reactor Oversight Program - Cy 2007 ML0730400332007-11-0101 November 2007 Public Meeting Slides for Meeting with Dominion Nuclear 2024-01-30
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24029A2362024-01-30030 January 2024 Preliminary Results of the Environmental Review, Subsequent License Renewal ML23338A1522023-12-0707 December 2023 Public Meeting Slides for North Anna and Surry Emergency Plan Augmentation Times License Amendment Request ML23255A0992023-09-15015 September 2023 Slides for September 15, 2023 Public Meeting on Poanhi Seismic Evaluations ML23103A3482023-04-14014 April 2023 Annual Assessment Meeting Presentation for North Anna and Surry ML21221A0332022-06-17017 June 2022 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides ML22091A0902022-04-0101 April 2022 Combined 2021 Assessment Meeting Slides ML21221A1542021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Dominion Slides ML21221A1482021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides ML21132A2892021-05-13013 May 2021 SLRA RAI Response Public Meeting ML21145A2172021-05-13013 May 2021 Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion Slides ML21034A5972021-02-10010 February 2021 External Presentation Am Atkinson_Nrc ISG-06 Meeting Dominion Digital IC Project 02102021 ML20288A3472020-10-14014 October 2020 (COVID-19) Emergency Preparedness Exemption Pre-Application Meeting ML20099F2412020-04-0909 April 2020 Co., NRC Safety Pre& 8208;Application Meeting North Anna Power Station (NAPS) ML20099F2992020-04-0909 April 2020 NRC Slides for North Anna pre-app April 9 ML20098B6022020-04-0707 April 2020 Annual Assessment Meeting Presentation ML19297D1872019-11-18018 November 2019 Pre-Application Meeting - Dominion Slides ML18141A3072018-05-21021 May 2018 18 - SLR Status ML16124A7582016-05-0303 May 2016 April 14, 2016, Summer of Public Meeting - North Anna, Units 1 and 2 ML16124A7632016-05-0303 May 2016 April 14, 2016, Summary of Public Meeting - North Anna Power Station, Units 1 and 2 ML15273A4292015-09-29029 September 2015 Revised Slides for September 29, 2015 Meeting with Dominion Re North Anna ISFSI License Renewal ML15133A0822015-05-13013 May 2015 ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15153A0452015-05-13013 May 2015 Revised North Anna ISFSI Presentation Slides - TN-32 High Burnup Dry Storage Research Project, May 13, 2015 (Tom Brookmire) ML15128A5462015-05-0808 May 2015 Summary of Public Meeting with North Anna, Units 1 and 2 to Discuss the Annual Assessment with the Public ML14058B1762014-03-0606 March 2014 Presentation Slides - North Anna ISFSI - High Burnup Dry Storage Confirmatory Data Project, TN-32 Storage Cask, Tom Brookmire, March 6, 2014, Docket No. 72-16, TAC No: L24886 ML14071A1672014-01-28028 January 2014 Enclosure 2: Presentation Slides - North Anna ISFSI TN-32 Cask and Pad 1 Assessments Following August 23, 2011, Central Virginia Earthquake ML13159A0092013-06-0404 June 2013 Notable Failures in Nondustructive Testing - June 4, 2013 Public Meeting ML12257A2342012-09-11011 September 2012 5-Hacker - North Anna Mockup and Search Unit Action Presentation Sept 10 ML12257A2002012-09-11011 September 2012 2-North Anna Extent of Condition Presentation 9-7-12 Sept 10 ML12131A5052012-05-0909 May 2012 Presentation for 2011 North Anna EOC Annual Assessment Meeting ML11305A0452011-11-0101 November 2011 Region II - North Anna Public Meeting Slides ML11305A0622011-11-0101 November 2011 Restart Readiness, Public Meeting PR2 ML1128500392011-10-12012 October 2011 Summary of Augmented Inspection Team Public Exit Meeting with Virginia Electric Power Company to Discuss the Results of an ATI Inspection of an Earthquake Event on August 23, 2011 ML11276A0242011-10-0303 October 2011 Slides-North Anna AIT Public Meeting October 3, 2011 ML1127701352011-10-0303 October 2011 Ltr to D. Heacock Re Participation in the Commission Meeting on the North Anna Plant on 10/21/11 ML11252A0062011-09-0808 September 2011 Dominion'S Slides Earthquake Response and North Anna Restart Readiness Demonstration Plan ML12040A2742011-08-31031 August 2011 E-Mail from G. Wilson, NRR to D. Merzke, EDO; Subject: Seismic Instruments at North Anna ML12044A2792011-08-30030 August 2011 Email from M. Khanna, NRR to R. Auluck, NRR FW: North Anna Earthquake Issue Commissioner Briefing Final with Talking Points ML1124205512011-08-30030 August 2011 Seismic Event ML12044A2912011-08-30030 August 2011 E-mail from G. Bowman, EDO to T. Hipschman, Comm, Et Al; Subject: FYI-Revised Slides on North Anna/Gl-199 ML12044A2572011-08-26026 August 2011 Email from A. Istar, NRR to A. Hiser, NRR on North Anna Nuclear Power Plant. Pptx ML1110304822011-04-13013 April 2011 Public Annual Assessment Meeting/Open House Slides ML1032204442010-11-18018 November 2010 Public Meeting Summary - North Anna Power Station ML1021102592010-08-0404 August 2010 Enclosure 3: Dominion - North Anna Presentation of July 28, 2010 Public Meeting ML1020100212010-07-14014 July 2010 Nucler Power Station, Units 1 and 2, Westinghouse RFA-2 Fuel Transition Licensing Meeting Presentation Slides ML1012600342010-05-0505 May 2010 Public Mtg. Slides ML1012600332010-05-0505 May 2010 Meeting Posters ML0917610472009-08-0505 August 2009 ECCS Preacs Filtration Presentation ML0912104262009-05-12012 May 2009 7th International Conference on NDE - Presentation :a Destructive Validation of NDE Responses of Service-Induced PWSCC Found in North Anna 2 Control Rod Drive Nozzle 31 ML0820501832008-07-23023 July 2008 Meeting Announcement - Summary of Public Meeting Category 1 - Performance Discussion Meeting, North Anna Power Station ML0812008742008-03-24024 March 2008 Annual Assessment Meeting Reactor Oversight Program - Cy 2007 2024-01-30
[Table view] |
Text
Purpose
- During this meeting, Dominion Energy Virginia will:
Brief NRC on the proposed exemption request, supporting information, and proposed timeline Discuss the exemption request prior to formal submittal Provide information to ensure a common understanding of the exemption request, its scope and the regulatory expectations 2 October 13, 2020
Proposed Exemption
- Dominion Energy Virginia is requesting an exemption to postpone the Calendar Year (CY) 2020 offsite biennial EP exercise until CY 2021 The August 18, 2020 NAPS biennial EP exercise was conducted without full ORO participation, placing the exercise outside the requirements of 10 CFR 50, Appendix E, Section IV.F.2.c The last NAPS biennial EP exercise that was federally-evaluated by Federal Emergency Management Agency (FEMA) was held on July 17, 2018 3 October 13, 2020
Regulatory Requirements 10 CFR 50.47 (b)(14) - Conduct periodic exercises 10 CFR 50 Appendix E IV.F.2.c - Offsite Biennial Exercise 4 October 13, 2020
Basis for Request & Precedent
Nuclear Regulatory Commission Planned Actions Related to Emergency Preparedness Biennial Exercise Requirements for All Licensees During the Coronavirus Disease 2019 Public Health Emergency" 5 October 13, 2020
Reasons for Request
- Ongoing response to the COVID-19 pandemic Public Health Emergency (PHE) declared on January 30, 2020 On March 12, 2020, a State of Emergency was declared in Virginia, and then Nationally on March 13, 2020 The COVID-19 PHE created special circumstances (per 10 CFR 50.12) that precluded NAPS and the Commonwealth of Virginia from conducting a full participation biennial EP exercise in August of 2020 6 October 13, 2020
Reasons for Request
- An exemption is needed for Dominion Energy Virginia to reduce the exposure risk to responders/essential workers and to adhere to Center for Disease Control and Prevention (CDC) recommended guidelines
- Commonwealth of Virginia, as well as municipal stakeholders, are engaged in pandemic response Resources for exercise preparation and participation would compete with resources devoted to pandemic response
- Gathering a large group of people (including players, controllers, evaluators) for an exercise when there is no actual emergency:
Puts all participants at risk Conflicts with practices recommended by the CDC 7 October 13, 2020
Scheduling Considerations
- A good faith effort was made to reschedule and conduct the exercise in 2020, but Dominion Energy Virginia and the Commonwealth of Virginia determined they could not participate until 2021
- In addition to ongoing COVID-19 concerns, Dominion Energy Virginias schedule challenges in 2020 include:
2020 Fall North Anna Unit 2 refueling outage Potential conflicts with FEMA Region 3 participation Conversion of Offsite Notification System from Insta- phone to Electronic Conversion of emergency action levels (EAL) program from previous standards (NEI 99-01, Revision 4) to use NEI 99-01, Rev.6
- A proposed date of February 23, 2021 can be supported by all parties for a full-participation offsite biennial EP exercise
- FEMA in-person evaluation is expected but arrangements will be implemented or a virtual evaluation performed, if necessary 8 October 13, 2020
Justification - RIS 2006-03 Guidance
- RIS 2006-03 states that in most cases, the postponed exercise still falls within the 35-month window The proposed one-time change in the NAPS offsite biennial EP exercise to February 23, 2021 is 31 months from the last biennial exercise which meets the intent of the regulation
Justify that postponing the offsite biennial EP exercise does not pose an undue risk to public health and safety Specify that both Dominion Energy Virginia and the Commonwealth of Virginia understand that if the requested exemption is granted allowing NAPS to conduct the CY 2020 offsite biennial EP exercise in CY 2021, subsequent biennial exercises will be held in even numbered years Conform to the remaining guidance provided in RIS 2006-03 9 October 13, 2020
Justification - Guidance in NRC to NEI Letter, dated May 14, 2020
Provide the last full-participation biennial EP exercise date State that reasonable effort was made to reschedule the offsite biennial EP exercise in CY 2020, but was unsuccessful Provide the proposed rescheduled offsite biennial EP exercise date and indicate that this date has been coordinated with the Commonwealth of Virginia and FEMA Region 3 State that Dominion Energy Virginia has conducted drills, exercises, and other training activities that have exercised the emergency response strategies, in coordination with offsite authorities, since the previous biennial exercise 10 October 13, 2020
Applicability & Inspection History
- FEMA has not conducted any evaluations of the Risk Jurisdictions around NAPS since the July 2018 biennial EP exercise which had zero Findings of Significance and zero Programmatic Issues
- Commonwealth of Virginia was evaluated by FEMA during the 2019 Surry Power Station biennial EP exercise Risk Jurisdictions around NAPS are evaluated every 2 years Commonwealth of Virginia is evaluated annually
- The exemption request will demonstrate that rescheduling of the NAPS offsite biennial EP exercise will support COVID-19 mitigation and prevention activities and will not present an undue risk to the public health and safety 11 October 13, 2020
Precedents
From IV.F.2.c for the following plants:
Beaver Valley, Units 1 & 2 (ML20266G366)
Peach Bottom, Units 1, 2 & 3 (ML20269A267)
Palisades (ML20275A110)
From IV.F.2.b and IV.F.2.c for the following plants:
Joseph M. Farley, Units 1 & 2 (ML20265A353)
Duane Arnold (ML20266G292)
Prairie Island, Units 1 & 2 (ML20281A665) 12 October 13, 2020
Schedule
- Exemption submittal Week of November 16, 2020
- NRC approval Requested by December 21, 2020 Based on the requirements for offsite biennial EP exercise participation expiring at the end of 2020 13 October 13, 2020
Summary
- Subsequent to March 13, 2020, isolation activities (e.g.,
social distancing, group size limitations, self-quarantining, etc.) were implemented to prevent the spread of COVID
- Consistent with Precedent - Submittals approved and under review 14 October 13, 2020