ML12257A200

From kanterella
Jump to navigation Jump to search
2-North Anna Extent of Condition Presentation 9-7-12 Sept 10
ML12257A200
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 09/11/2012
From: Wirtz C
Electric Power Research Institute
To:
Office of Nuclear Reactor Regulation
Rezai A
References
Download: ML12257A200 (21)


Text

Extent of Condition Chuck Wirtz FirstEnergy, BWRVIP Integration Committee Chairman, NIFG Member NRC Meeting - North Anna Actions September 11, 2012

Overview

  • Scope
  • Objective
  • Data Gathering Method
  • Responses
  • Data Analysis
  • Tentative Extent of Condtion Actions
  • Implementation Method

© 2012 Electric Power Research Institute, Inc. All rights reserved. 2

Scope

  • The scope of the extent of condition evaluation included all the Class 1 dissimilar metal welds in the US fleet that have been examined by ASME,Section XI, Appendix VIII, Supplement 10 procedures and personnel (NIFG Action Item 5.1)

© 2012 Electric Power Research Institute, Inc. All rights reserved. 3

Objective

  • The objective is to understand the extent and types of UT examinations performed on dissimilar metal welds (DMWs), their relative risk from an NDE perspective, the overall relative safety risk with consideration of the weld joint materials, and identify the actions to be taken (NIFG Action Item 5.2)

© 2012 Electric Power Research Institute, Inc. All rights reserved. 4

Method

  • A focused survey was developed by the NIFG team
  • Distributed to all US fleet ISI/NDE contacts
  • Key items requested:

- Identification/Description of Supp 10 Welds

- Exam Method (i.e., Auto, Encoded Manual, Manual)

- Was Site-Specific Mock-up Used

- Was Team Scanning Used

- Filler and Base Materials

- Mitigation Status

- Year of Next Scheduled Exam

© 2012 Electric Power Research Institute, Inc. All rights reserved. 5

Response

  • As of September 7, 2012

- Data received from 104 of 104 plants

  • Data provided on more than 2,200 DM welds

- Peer checks of the data performed

  • On a sampling basis, compared data to existing industry DM weld survey information from BWRVIP and MRP databases
  • Peer checks found data was generally consistent, but there were some anomalies that will require follow-up with the plants to resolve

- Responses allowed the NIFG team to screen all the plants and understand the extent of condition and relative safety significance

© 2012 Electric Power Research Institute, Inc. All rights reserved. 6

Data set screening Initial screening of data identified some anomalies resulting in an preliminary Supplement 10 population of 2107 DMW welds Automated vs Manual Examinations 1000 900 800 866 PWR 700 1241 600 BWR 500 400 300 200 100 0

Manual Automated The next screening of data eliminated welds reported as being examined from the inside surface because:

  • all were automated
  • none involved the use of site-specific mockups

© 2012 Electric Power Research Institute, Inc. All rights reserved. 7

Data Analysis

  • Approach was to quantify the data using a risk matrix

© 2012 Electric Power Research Institute, Inc. All rights reserved. 8

Data Analysis Considerations

  • High Risk Contributors
  • Low Risk Contributors

- NDE - NDE

  • Site Specific mock-up
  • No site specific mock-up
  • Manual examination
  • Automated examination
  • Team scanning*

- Materials - Materials

  • Susceptible base material
  • Non-susceptible base
  • Susceptible filler material material
  • Non-mitigated welds
  • Non- susceptible filler material
  • Ultimately not used in the data analysis
  • Mitigated welds because the use of team scanning was not documented consistently.

© 2012 Electric Power Research Institute, Inc. All rights reserved. 9

Data Analysis - Initial Strategy

© 2012 Electric Power Research Institute, Inc. All rights reserved. 10

Risk Assessment Tool

  • The risk assessment strategy is being developed into a tool This will be distributed to all licenses for their use in self assessment Materials and Mitigation strategies determine relative risk category Application of NDE drives relative risk from Red to Green

© 2012 Electric Power Research Institute, Inc. All rights reserved. 11

Data Analysis - Final Strategy

© 2012 Electric Power Research Institute, Inc. All rights reserved. 12

High Level Summary (red box)

Extent of Condition (Preliminary) 866 Welds Plants PWR BWR 13 (1.5%) 6 1241 BWR PWR 40 (3.2%) 6 Fleet 53 (2.5%) 12 (11.5%)

13 40 6

6 7

Welds Plants Utilities

© 2012 Electric Power Research Institute, Inc. All rights reserved. 13

Tentative Extent of Condition Actions

  • For welds identified as high relative risk (red box welds)

- Re-examine within 3 years using the DM weld guidance and NDE improvement tools developed by the NIFG team

© 2012 Electric Power Research Institute, Inc. All rights reserved. 14

Tentative EOC Actions (cont.)

  • For welds identified as medium relative risk (orange box welds)

- Verify the materials are non-susceptible and/or mitigated

- Perform a review of the weld repair history to determine if there were any through-wall repairs or repairs to the ID surface and disposition as follows:

  • If repairs history indicates ID materials could have been compromised, then the weld is to be treated the same as a red box weld and red box extent of condition actions apply
  • If there were no repairs or the repairs were not through-wall or ID repairs, re-examine as normally scheduled using the DM weld guidance and NDE improvement tools developed by the NIFG team

© 2012 Electric Power Research Institute, Inc. All rights reserved. 15

Tentative EOC Actions (cont.)

  • For welds identified as low relative risk (yellow box welds)

- At next scheduled examination apply the DM weld guidance and NDE improvement tools developed by the NIFG team

  • For welds identified as having no relative risk (green box welds)

- No action is really necessary, but these welds will also benefit from application of the DM weld guidance and NDE improvement tools developed by the NIFG team upon their next examination

© 2012 Electric Power Research Institute, Inc. All rights reserved. 16

Implementation

  • Implementation will be through the NEI 03-08 Materials Initiative Program, which will include issuing the extent of condition actions and NDE improvement guidance to the plants as Mandatory, Needed or Good Practice requirements as approved by the BWRVIP and PMMP Executive Committees.

© 2012 Electric Power Research Institute, Inc. All rights reserved. 17

Tentative Implementation Strategy for Red and Orange Box EOC Actions

  • A Risk Assessment Tool will be sent to the plants requiring them to verify or re-evaluate their DMW Supplement 10 examination status, bin their own welds in the proper risk boxes, and follow the extent of condition actions outlined in the previous slides.
  • NEI 03-08 guidance must be documented in plants Corrective Action programs.
  • The plants will report the results of their self-binning to the NDE Integration Committee.

© 2012 Electric Power Research Institute, Inc. All rights reserved. 18

Tentative Implementation Schedule for the Red and Orange Box EOC Actions

  • The targeted completion date for development of the Risk Assessment Tool is October 12th.
  • The Tool and the associated actions will be reviewed and approved through the committees of the applicable NEI 03-08 Issue Programs (i.e., NDE, BWRVIP, and MRP). This process is expected to take at least 8 weeks.
  • Requirements approved by the BWRVIP and PMMP Executive Committees will be transmitted to the plants for self-binning and implementation.

© 2012 Electric Power Research Institute, Inc. All rights reserved. 19

Open Discussion NRC Survey Questions

  • The survey did not ask for differentiation of conventional vs phased array techniques. For the purpose of the extent of condition survey all qualified Supplement 10 exams were treated equally.
  • The survey did not specifically ask for manual vs automated for both axial and circumferential scans. Some responses did identify that both manual and automated were used; these were treated as manual only.
  • The NRC provided numerous detailed questions on the specifics of the site specific mockup applications. For the purposes of the extent of condition analysis, all site specific mockups were treated as equal contributors to risk.

© 2012 Electric Power Research Institute, Inc. All rights reserved. 20

TogetherShaping the Future of Electricity

© 2012 Electric Power Research Institute, Inc. All rights reserved. 21