ML18037A140: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:~Q BEGULATO INFORMATION DISTRIBUTION | {{#Wiki_filter:~ Q BEGULATO INFORMATION DISTRIBUTION . TEht (BI DS) | ||
.TEht (BI DS)ACCESSION NBB.-7812120103 DOC.DATE~78/11/30 NOTARIZED~NO FACIL~50-220 NINE MILE, POINT | ACCESSION NBB.-7812120103 DOC.DATE ~ 78/11/30 NOTARIZED ~ NO DOCKET ¹0 | ||
~PERKINS T.J~NIAGARA MOHAWK.PWR BECI P.NAME BEG I P I ENT'FF I L | ¹ FACIL~50-220 NINE MILE,POINT I, NIAGARA MOHAWK,POWER CORP. 05000220 AUTH. NAME AUTHOR AFFILIATION | ||
&MONTHLY, | ~ PERKINS T.J ~ NIAGARA MOHAWK .PWR BECI P . NAME I BEG I P I ENT'FF I L ATION SUBJECT! Monthly Op er Rept for Nov 1,978. | ||
~ DISTRIBUTION CODE: A008S COPIES RECEIVED-LTR ENCL 3'ITLE - ANNUAL SEMI-ANNUAL & MONTHLY,OPERATING REPORTS SIZE-(OL STAG NOTES- ~ | |||
RECIPIENT COPI ES REC I P I ENT COP I ES 0 ACTION: ID CODE/NAME 05 BC LTTR ENCL 6 6 ID CODF/NAME LTTR ENCL INTERNAL: OJ REG FILE I I 02 NRC PDR 01 01 11 I &E 02 02 13 HANAUEB 01 01 14 MIPC 02 02 16 DIR DOB 01 , 01 17AD SYS 8 PBOJ 01 18 ENGR BB 01 01 19 REAC SAFT BR 0.1 0.1 '1 20 PLANT S YS BR O.l 01 21 EEB 0.1 01 22 CORE PEBF BR 01,. 0.1 0 23 EFFL TR SYS 01 01 EXTERNAL- 03 LPDR 02 02 04 NSIC 01 01 24 NATL LAB 0.1 O,l 25 BROOKHAVEN 01 01 26 ACRS 15 15 TOTAL NUMBER OF COPI ES BEQUI BED! LTTB 4,1 ENCL 41 | |||
n h | |||
l | |||
~ | 'E | ||
) | |||
t~ | |||
l,' | |||
( | OPERATING DATA REPORT | ||
November 1-4 The unit operated at 92$power maintained with recirculation flow.November 5 | ~~i, 8 | ||
At 0840 all control rods were at position 48.At 1345 pre-conditioning started at a rate of approximately 3 MWe/hr.November 24-27 | DOCKET NO. 50-220 DATE 1978 COMPLBTBD BY L8r~~k'nS TELEPHONE 32 '~~10 ext. 1312 OPERATING STATUS Notes I. Unit Name: | ||
: 2. Reporting Period: 11 Ol 8 11 30 8 | |||
: 3. Licensed Thermal Power (MlVt): | |||
: 4. Nameplate Rating (Gross MlVe): 640 | |||
: 5. Design Electrical Rating (Net MNe): 6 | |||
~6 | |||
: 7. srfaximum Dependable Capacity (Net MIVe): | |||
: 8. IfChanges Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons: | |||
: 9. Power Level To which Restricted, If Any (Net M)Ve): | |||
: 10. Reasons For Restrictions, If Any: V R 'b d W This Month Yr.-to.Date4 Cumulative | |||
: 11. Hours In Reporting Period | |||
',o16 79,6o8 | |||
: 12. iNumber Of Hours Reactor )Vas Critical | |||
: 13. Reactor Reserve Shutdown Hours 0 0 1 204 | |||
: 14. Hours Generator On-Line 15. | |||
16. | |||
17. | |||
18. | |||
Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MPH) | |||
Gross Electrical Energy Generated (iWIVH) | |||
Net Electrical Energy Generated (MNH) | |||
~86 387~357 374,330 | |||
~66 4 210 845 4,070, 77 0 | |||
~6 29 922 557 29,0 7, 00 | |||
: 20. 2 | |||
.8 | |||
: 19. Unit Service Factor 70.7 | |||
: 20. Unit Availability Factor 100 70s 7 | |||
: 21. Un! t Capacity Factor (Using hfDC Net) 85.2 83.2 59.8 | |||
: 22. Unit Capacity Factor (Using DER Net) | |||
: 23. Unit Forced Outage Rate 0 1.6 | |||
: 24. Shutdorvns Scheduled Over Next 6 irifonths (Type. Date. arid Duratio;r of Each): | |||
: 25. If Shut Down At End Of Report Period, Estimated Date of Startup: | |||
: 26. Units ln Test Status (Prior to Comruercial Operation): Forecast Acllrcved INITIAL CRITICALITY IN ITIAL ELECTRICITY CO81f Af ERCIA L OPERATION 781%.8 Q(Q (rl/77 ) | |||
l | |||
~s Wl | |||
DOCKET NO. 5 UniM1 9 8 COMPLETED DY TELEPIIONE 315-3 3-2110 ex'. 1312 MONTH DAY AVERAGE DAlLYPO'O'ER LEVEL DAY AVERAGE DAILYPOh'ER LEVEL (M)s'e-Net ) (MWe-Net) 17 554 19 4 51 20 553 5 ~.4 552 23 548 383 25 391 10 4O 26 422 497 12 551 13 555 14 30 554 15 31 16 INSTRUCTIONS On this format, list the average daily unit power level in MNe-Net I'or each day in thc rcport to ntontlt. Contputc tti the nearest whole megaivat t. | |||
(')!77 l | |||
UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME | |||
. BM20- nit 1 DATE 8 REPORT MONTH COMPLETED BY ext. 1312 Lice nscc O~ Cause ('orrcctivc Cp CP o l~ Er. | |||
l)ate Event EA Acth>n t>> | |||
Rcport- cn' o Prevent Rect>ffcncc 11/05/78 3.6 Condensate Demin Change ll/10/78 4.5 ¹12 Condensate Demit Change ll/12/78 6.7 H ¹13 Condensate Demin Change 11/24/78 96 H All Control Rods Full Out-Preconditioning F: F.>reed Reason: hlcthod: Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) I hlanual for Prcparath>n of Data B-hiaintenance or Test 2-h(anual Scram. Entry Shc'ts I'or Licensee C-Refueling 3-Automatic Sera>n. I:.v nt R p >rt (I.l!I() File(NURI!G-D.Reiudatory Restriction 4.Other (Explain) OI6I) | |||
I':Operator Trainint, k, License Fxatnination I -Adn>inist rat ivc (I.Operal>onal I:rf>>f (I:xplaln) Exhibit I - Sa>nc Source | |||
('>/77) I I Other (Explair>) ~ | |||
(J l | |||
NIAGARA MOHAWK POWER CORPORATION NINE MILE POINT NUCLEAR STATION UNIT Pl NARRATIVE OF OPERATING EXPERIENCE November 1978 The station operated at 85.2/ electrical capacity factor with an availability of 100'5. The unit is derated to 92.0A thermal power as a result of scram reactivity restrictions. | |||
November 1-4 The unit operated at 92$ power maintained with recirculation flow. | |||
November 5 Reduced load to 500 MWe for condensate demineralizer change at 0005. At 0335 load was increased back to 558 MWe after demineralizer change. | |||
November 6-9 The unit maintained 92% power with recirculation flow. | |||
November 10 Reduced load to 500 MWe at 0130 for condensate demineralizer change. At 0558 load was returned to 560 MWe after demineralizer change. | |||
November 11 Unit was operated at 92/ power. | |||
November 12 Reduced load to 500 MWe for condensate demineralizer change at 0132. At 0648 load was'eturned after demineralizer change. | |||
November 13-21 Maintained load at 92/ thermal power with recir-culation flow. On the 21st, 100/ recirc flow was reached. | |||
November 21-24 Load slowly coasted down until 0600 on the 24th when power was reduced to 350 MWe for control rod pattern change to an all rods out configuration. At 0840 all control rods were at position 48. At 1345 pre-conditioning started at a rate of approximately 3 MWe/hr. | |||
November 24-27 Increasing load as PCIOMR limits allow. | |||
November 28 Reached 92/ power (all rods out). | |||
November 29-30 The unit maintained 92%%d power with recirculation flow. | |||
Jk f}} |
Latest revision as of 15:27, 3 February 2020
ML18037A140 | |
Person / Time | |
---|---|
Site: | Nine Mile Point |
Issue date: | 12/05/1978 |
From: | Perkins T NIAGARA MOHAWK POWER CORP. |
To: | |
Shared Package | |
ML18037A139 | List: |
References | |
NUDOCS 7812120103 | |
Download: ML18037A140 (10) | |
Text
~ Q BEGULATO INFORMATION DISTRIBUTION . TEht (BI DS)
ACCESSION NBB.-7812120103 DOC.DATE ~ 78/11/30 NOTARIZED ~ NO DOCKET ¹0
¹ FACIL~50-220 NINE MILE,POINT I, NIAGARA MOHAWK,POWER CORP. 05000220 AUTH. NAME AUTHOR AFFILIATION
~ PERKINS T.J ~ NIAGARA MOHAWK .PWR BECI P . NAME I BEG I P I ENT'FF I L ATION SUBJECT! Monthly Op er Rept for Nov 1,978.
~ DISTRIBUTION CODE: A008S COPIES RECEIVED-LTR ENCL 3'ITLE - ANNUAL SEMI-ANNUAL & MONTHLY,OPERATING REPORTS SIZE-(OL STAG NOTES- ~
RECIPIENT COPI ES REC I P I ENT COP I ES 0 ACTION: ID CODE/NAME 05 BC LTTR ENCL 6 6 ID CODF/NAME LTTR ENCL INTERNAL: OJ REG FILE I I 02 NRC PDR 01 01 11 I &E 02 02 13 HANAUEB 01 01 14 MIPC 02 02 16 DIR DOB 01 , 01 17AD SYS 8 PBOJ 01 18 ENGR BB 01 01 19 REAC SAFT BR 0.1 0.1 '1 20 PLANT S YS BR O.l 01 21 EEB 0.1 01 22 CORE PEBF BR 01,. 0.1 0 23 EFFL TR SYS 01 01 EXTERNAL- 03 LPDR 02 02 04 NSIC 01 01 24 NATL LAB 0.1 O,l 25 BROOKHAVEN 01 01 26 ACRS 15 15 TOTAL NUMBER OF COPI ES BEQUI BED! LTTB 4,1 ENCL 41
n h
l
'E
)
t~
l,'
OPERATING DATA REPORT
~~i, 8
DOCKET NO. 50-220 DATE 1978 COMPLBTBD BY L8r~~k'nS TELEPHONE 32 '~~10 ext. 1312 OPERATING STATUS Notes I. Unit Name:
- 2. Reporting Period: 11 Ol 8 11 30 8
- 3. Licensed Thermal Power (MlVt):
- 4. Nameplate Rating (Gross MlVe): 640
- 5. Design Electrical Rating (Net MNe): 6
~6
- 7. srfaximum Dependable Capacity (Net MIVe):
- 8. IfChanges Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
- 9. Power Level To which Restricted, If Any (Net M)Ve):
- 10. Reasons For Restrictions, If Any: V R 'b d W This Month Yr.-to.Date4 Cumulative
- 11. Hours In Reporting Period
',o16 79,6o8
- 12. iNumber Of Hours Reactor )Vas Critical
- 13. Reactor Reserve Shutdown Hours 0 0 1 204
- 14. Hours Generator On-Line 15.
16.
17.
18.
Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MPH)
Gross Electrical Energy Generated (iWIVH)
Net Electrical Energy Generated (MNH)
~86 387~357 374,330
~66 4 210 845 4,070, 77 0
~6 29 922 557 29,0 7, 00
- 20. 2
.8
- 19. Unit Service Factor 70.7
- 20. Unit Availability Factor 100 70s 7
- 21. Un! t Capacity Factor (Using hfDC Net) 85.2 83.2 59.8
- 22. Unit Capacity Factor (Using DER Net)
- 23. Unit Forced Outage Rate 0 1.6
- 24. Shutdorvns Scheduled Over Next 6 irifonths (Type. Date. arid Duratio;r of Each):
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup:
- 26. Units ln Test Status (Prior to Comruercial Operation): Forecast Acllrcved INITIAL CRITICALITY IN ITIAL ELECTRICITY CO81f Af ERCIA L OPERATION 781%.8 Q(Q (rl/77 )
l
~s Wl
DOCKET NO. 5 UniM1 9 8 COMPLETED DY TELEPIIONE 315-3 3-2110 ex'. 1312 MONTH DAY AVERAGE DAlLYPO'O'ER LEVEL DAY AVERAGE DAILYPOh'ER LEVEL (M)s'e-Net ) (MWe-Net) 17 554 19 4 51 20 553 5 ~.4 552 23 548 383 25 391 10 4O 26 422 497 12 551 13 555 14 30 554 15 31 16 INSTRUCTIONS On this format, list the average daily unit power level in MNe-Net I'or each day in thc rcport to ntontlt. Contputc tti the nearest whole megaivat t.
(')!77 l
UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME
. BM20- nit 1 DATE 8 REPORT MONTH COMPLETED BY ext. 1312 Lice nscc O~ Cause ('orrcctivc Cp CP o l~ Er.
l)ate Event EA Acth>n t>>
Rcport- cn' o Prevent Rect>ffcncc 11/05/78 3.6 Condensate Demin Change ll/10/78 4.5 ¹12 Condensate Demit Change ll/12/78 6.7 H ¹13 Condensate Demin Change 11/24/78 96 H All Control Rods Full Out-Preconditioning F: F.>reed Reason: hlcthod: Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) I hlanual for Prcparath>n of Data B-hiaintenance or Test 2-h(anual Scram. Entry Shc'ts I'or Licensee C-Refueling 3-Automatic Sera>n. I:.v nt R p >rt (I.l!I() File(NURI!G-D.Reiudatory Restriction 4.Other (Explain) OI6I)
I':Operator Trainint, k, License Fxatnination I -Adn>inist rat ivc (I.Operal>onal I:rf>>f (I:xplaln) Exhibit I - Sa>nc Source
('>/77) I I Other (Explair>) ~
(J l
NIAGARA MOHAWK POWER CORPORATION NINE MILE POINT NUCLEAR STATION UNIT Pl NARRATIVE OF OPERATING EXPERIENCE November 1978 The station operated at 85.2/ electrical capacity factor with an availability of 100'5. The unit is derated to 92.0A thermal power as a result of scram reactivity restrictions.
November 1-4 The unit operated at 92$ power maintained with recirculation flow.
November 5 Reduced load to 500 MWe for condensate demineralizer change at 0005. At 0335 load was increased back to 558 MWe after demineralizer change.
November 6-9 The unit maintained 92% power with recirculation flow.
November 10 Reduced load to 500 MWe at 0130 for condensate demineralizer change. At 0558 load was returned to 560 MWe after demineralizer change.
November 11 Unit was operated at 92/ power.
November 12 Reduced load to 500 MWe for condensate demineralizer change at 0132. At 0648 load was'eturned after demineralizer change.
November 13-21 Maintained load at 92/ thermal power with recir-culation flow. On the 21st, 100/ recirc flow was reached.
November 21-24 Load slowly coasted down until 0600 on the 24th when power was reduced to 350 MWe for control rod pattern change to an all rods out configuration. At 0840 all control rods were at position 48. At 1345 pre-conditioning started at a rate of approximately 3 MWe/hr.
November 24-27 Increasing load as PCIOMR limits allow.
November 28 Reached 92/ power (all rods out).
November 29-30 The unit maintained 92%%d power with recirculation flow.