OPERATING STATUS OPERATING DATAREPORT DOCKET NO.:
50-220 DATE: 1/31/91 COMPLETED BY: K. A. Dahlberg TELEPHONE:
(315) 349-2443
- 1. Unit Name:
Nine MilePoint Unit //I
- 2. Reporting Period:
8/1/90 through 8/31/90
- 3. Licensed Thermal Power (MWt):
1850
- 4. Nameplate Rating (Gross MWe):
6454
- 5. Design Electrical Rating (Net MWe):
6254
- 6. Maximum Dependable Capacity (Gross MWe):
635*
- 7. Maximum Dependable Capacity (Net MWe):
615*
- 8. IfChanges Occur in Capacity Ratings (Items Number 3 through 7) Since Last Report, Give Reasons:
- Modification to the high pressure turbine adding 5 MWe to all ratings.
Notes
- 9. Power Level To Which Restricted, IfAny (Net MWe): 25% Power (462.5 MWt)
- 10. Reasons For Restrictions, IfAny: The Unit was unavailable for 967 days.
We are now restricted to 25% power during the first phase of Power Ascension Testing.
This Month Yr-to-Date Cumulative
- 11. Hours in Reporting Period 744.0
- 12. Number ofHours Reactor Was Critical 553.4
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator On-Line 342.9
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Thermal Energy Generated (MWH) 191,618.0
- 17. Gross Electrical Energy Generated (MWH) 36,918.0
- 18. Net Electrical Energy Generated (MWH) 32,169.0
- 19. Unit Service Factor 46.1
- 20. Unit AvailabilityFactor 46.1
- 21. Unit Capacity Factor (Using MDC Net) 7.0
- 22. Unit Capacity Factor (Using DER Net) 6.9
- 23. Unit Forced Outage Rate 50.3
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration ofEach):
5,831.0 583.2 0.0 342.9 0.0 191,733.0 36,918.0 32,169.0 5.9 5.9 0.9 0.9 94.1 183,720.2 115,817.5 1,204.2 11.2,460.1 20.4 188,664,865.0 62,509,988 0 60,556,551.0 612 614 54.0 53.2 26.2
- 25. IfShut Down At Ead ofReport Period, Estimated Date of Startup:
- 26. Unit is Test Status (Prior to Commercial Operation):
Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION 9102200094 910207 PDR ADOCK 05000220 R