OPERATING STATUS Rev. I OPERATING DATAREPORT DOCKET NO.:
50-220 DATE: 3/05/97 PREPARED BY: D. E. Coleman TELEPHONE:
(315) 349-2558 I
- 1. Unit Name:
Nine Mile Point Unit //1
- 2. Reporting Period:
February 1997
- 3. Licensed Thermal Power (MWt):
1850
- 4. Nameplate Rating (Gross MWe):
642
- 5. Design Electrical Rating (Net MWe):
613
- 6. Maximum Dependable Capacity (Gross MWe):
584
- 7. Maximum Dependable Capacity (Net MWe):
565
- 8. If Changes Occur in Capacity Ratings (items Number 3 through 7) Since Last Report, Give Reasons:
Notes
- 9. Power Level To Which Restricted, IfAny (Net MWe):
- 10. Reasons For Restrictions, IfAny:
This Month Yr-to-Date Cumulative 1416.0 1381.9 0
1374,2 0
2,497,347.0 853,969.0 830,712,0 97.0 97.0 103.8 95.7 3.0
- 11. Hours in Reporting Period 672.0
- 12. Number of Hours Reactor Was Critical 672.0
- 13. Reactor Reserve Shutdown Hours 0
- 14. Hours Generator On-Line 672.0
- 15. Unit Reserve Shutdown Hours 0
- 16. Gross Thermal Energy Generated (MWH) 1,211,908.0
- 17. Gross Electrical Energy Generated (MWH) 414,717.0
- 18. Net Electrical Energy Generated (MWH) 403,462.0
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor (Using MDC Net) 106.3
- 22. Unit Capacity Factor (Using DER Net) 97.9
- 23. Unit Forced Outage Rate 0.0
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):
(35 Day Refuel Outage scheduled for March 3, 1997) 240,673.2 163658.9 1,204.2 159,730.4 20.4 271,704,127.0 90,432,425.0 87,692,266,0 66.4 66.4 60.3 58.8 22.2
- 25. Ifshutdown At End of Report Period, Estimated Date of Startup:
97052203%9 970512 PDR ADQCK 05000220