ML14129A335: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 2: | Line 2: | ||
| number = ML14129A335 | | number = ML14129A335 | ||
| issue date = 05/09/2014 | | issue date = 05/09/2014 | ||
| title = | | title = Summary of Category 1 Public Meeting - Annual Assessment of Shearon Harris Nuclear Plant | ||
| author name = Hopper G | | author name = Hopper G | ||
| author affiliation = NRC/RGN-II/DRP/RPB4 | | author affiliation = NRC/RGN-II/DRP/RPB4 |
Revision as of 06:19, 5 December 2019
ML14129A335 | |
Person / Time | |
---|---|
Site: | Harris |
Issue date: | 05/09/2014 |
From: | Hopper G NRC/RGN-II/DRP/RPB4 |
To: | Kapopoulos E Progress Energy Carolinas |
References | |
Download: ML14129A335 (18) | |
Similar Documents at Harris | |
---|---|
Category:Letter
MONTHYEARML24290A1102024-10-24024 October 2024
[Table view]Notification of Licensed Operator Initial Examination 05000400/2025301 05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out IR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 ML24059A4252024-08-14014 August 2024 Issuance of Amendment No. 202 Regarding Alignment of Certain Technical Specifications with Improved Standard Technical Specifications ML24213A0522024-08-0202 August 2024 Issuance of Amendment No. 201 to Extend Completion Time of Inoperable Reactor Coolant System Accumulator Using Consolidated Line Item Improvement Process ML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 ML24162A1372024-06-24024 June 2024 – Regulatory Audit Summary Related to the Review of Exemption Request from Certain Requirements in 10 CFR 50.55a(h)(2)(EPID L-2024-LLE-00040) ML24136A1382024-05-20020 May 2024 – Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2024011) and Request for Information (RFI) ML24116A2592024-05-14014 May 2024 Staff Evaluation Related to Aging Management Plan and Inspection Plan for Reactor Vessel Internals ML24127A1592024-05-0808 May 2024 – Notification of Licensed Operator Initial Examination 05000400/2024302 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 ML24100A0912024-04-10010 April 2024 Operator License Examination Report ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000400/20243012024-02-21021 February 2024 – NRC Operator Licensing Examination Approval 05000400/2024301 IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter IR 05000400/20230012023-05-10010 May 2023 Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000400/20220032022-11-10010 November 2022 Integrated Inspection Report 05000400/2022003 IR 05000400/20223012022-11-0202 November 2022 NRC Operator License Examination Report 05000400/2022301 2024-09-10 Category:Meeting Briefing Package/Handouts MONTHYEARML24100A8062024-04-0909 April 2024
[Table view]Duke Energy Sites Annual Assessment Meeting Presentation Slides April 23, 2024 ML23341A1522023-12-0707 December 2023 December 11, 2023 Public Meeting - RIPE Exemption Request - Licensee Slides ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22153A3842022-06-0606 June 2022 Duke Energy Presentation Material for June 6, 2022 Public Meeting on GSI-191 Closeout ML22091A1332022-04-0101 April 2022 Bru Har Combined 2021 Assessment Meeting Slides ML20100G6342020-04-0909 April 2020 Revised- Bru 2019 Annual Assessment Meeting Slides ML19318F2912019-11-18018 November 2019 Duke Energy Presentation for the Pre-submittal Meeting on November 18, 2019, Regarding the RPV Stud Examination Relief Request ML19214A0562019-08-0707 August 2019 Presentation: Duke Energy Presubmittal Meeting - August 7, 2019 ML19077A3672019-03-14014 March 2019 March 14, 2019 Pre-submittal Meeting TS DNBR Safety Limit Change LAR Meeting Slides ML18351A1342018-12-20020 December 2018 December 20, 2018 Pre-submittal Meeting Slides for Escw Risk-Informed LAR ML18333A1822018-11-0808 November 2018 Pre-Submittal Meeting - November 8, 2018 - License Amendment Request for Shearon Harris Nuclear Power Plant Emergency Plan Revision ML17331A6272017-11-29029 November 2017 Duke Energy Pre-Submittal Meeting Presentation, Brunswick, Harris, and Robinson License Amendment Requests Regarding 10 CFR 50.69 ML17250B2382017-08-30030 August 2017 TMRE Presubmittal NRC ML17044A0892017-03-0202 March 2017 EDG SR Presubmittal Meeting March 2, 2017 ML16267A0292016-09-29029 September 2016 SFP Pre-Submittal Meeting Slides - BWR Storage Rack Inserts, Updated NCS Analysis at Harris Nuclear Plant ML16112A2932016-05-0202 May 2016 05/02/2016 Presentation for Closed Pre-Submittal Meeting with Duke Energy Progress, Inc., to Discuss Fuel Reload Design Methodology Reports and Proposed LAR Re. H. B. Robinson And Shearon Harris Plants (CAC Nos. MF7443 And MF7444) RA-15-0041, Attachment 1, Affidavit and Attachment 3, Pre-Submittal Meeting Presentation Materials on DPC-NF-2010-A and DPC-NE-2011-P Methodologies (Redacted)2015-09-18018 September 2015 Attachment 1, Affidavit and Attachment 3, Pre-Submittal Meeting Presentation Materials on DPC-NF-2010-A and DPC-NE-2011-P Methodologies (Redacted) ML14129A3352014-05-0909 May 2014 Summary of Category 1 Public Meeting - Annual Assessment of Shearon Harris Nuclear Plant ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13212A3372013-07-31031 July 2013 NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting NEI 01-01, NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting2013-07-31031 July 2013 NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting NEI 01-01, 7/31/2013 NRC Public Meeting Presentation on NEI 01-012013-07-30030 July 2013 7/31/2013 NRC Public Meeting Presentation on NEI 01-01 ML13218B3372013-07-30030 July 2013 Handout for 7/30/13 Conference Call Re. Harris Emergency Response Facility Activation Timeliness and Criteria ML13211A3782013-07-30030 July 2013 7/31/2013 NRC Public Meeting Presentation on NEI 01-01 ML13204A2562013-07-0909 July 2013 Handout - LOOP Voltage Setpoint Change Presubmittal Conference Call - July 9, 2013 ML13170A3352013-06-13013 June 2013 Presentation - NRC Special Inspection Meeting - Harris Reactor Pressure Vessel ML12277A0272012-10-0202 October 2012 Slides - Summary of Meeting with Duke Energy Carolinas to Discuss Noncenservative Technical Specifications License Amendment Requests ML12242A4322012-08-28028 August 2012 Summary of Category 1 Public Meeting - Regulatory Conference and Predecisional Enforcement Conference ML12206A3252012-08-0707 August 2012 G20120513/EDATS: OEDO-2012-0436 - Briefing Book for Meeting with Duke Energy on August 7, 2012 ML12188A0712012-07-11011 July 2012 G20120473/ EDATS: OEDO-2012-0404 - Briefing Book - Briefing Package for Meeting with Duke Energy on July 11, 2012 ML12107A0012012-04-16016 April 2012 Meeting Summary - Category 1 Public Meeting - Annual Assessment of Shearon Harris Nuclear Plant ML11354A3782012-02-0808 February 2012 Meeting Handout - Meeting with Carolina Power and Light Suggested Discussion Items Regarding Realistic Large Break Loss-of-Coolant Accident HNP-12-028, Realistic LBLOCA Question Response Meeting Handout, Enclosure 3 to HNP-12-0282012-01-11011 January 2012 Realistic LBLOCA Question Response Meeting Handout, Enclosure 3 to HNP-12-028 ML12076A1652012-01-11011 January 2012 Meeting Slides - Harris Realistic LBLOCA Question Response Meeting ML1118011132011-06-29029 June 2011 NRC Staff Response to NFPA 805 Transition FAQ 10-0059, Revision 1 ML1113704082011-05-0909 May 2011 Meeting Slides Regarding Human Performance Improvement ML1107301382011-04-21021 April 2011 February 22, 2011, Summary of Pre-application Meeting with Carolina Power & Light and Representatives Regarding Upcoming BWR Boraflew License Amendment Request W/ Public Meeting Slides ML1111000242011-04-20020 April 2011 Meeting Summary - Shearon Harris - List of Attendees ML1014102712010-05-18018 May 2010 Shearon Harris Nuclear Plant Annual Assessment Meeting Slides ML0922900342009-08-17017 August 2009 08/19/09-Meeting Slides for 11th International Seminar on Fire Safety in Nuclear Power Plants and Installations, Risk-Informed, Performance-Based Fire Protection: a U.S. Regulatory Perspective ML0916605042009-06-24024 June 2009 04/21-22/2009 Summary of Category 2 Meeting with Progress Energy Carolinas, Inc., and Duke Energy Carolinas, LLC, to Discuss Topics Involving the License Amendment Requests to Transition Shearon, Unit 1 and Oconee to NFPA 805 ML0904906122009-02-18018 February 2009 NFPA 805 Pilot License Amendment Request Review and Infrastructure Update, February, 2009 ML0829601532008-11-17017 November 2008 Summary of Meeting with Progress Energy Carolinas, Inc., to Discuss Shearon Harris Unit 1 National Fire Protection Association Standard 805 License Amendment Request ML0830800052008-10-31031 October 2008 Meeting Slides, Progress Energy Public Meeting, NRC Region II Visit ML0820703912008-07-17017 July 2008 Meeting Handouts from 7/17/08 Public Meeting on the Harris and Oconee LARs to Transition to NFPA-805 M080717, M080717-Commission Briefing Slides/Exhibits Briefing on Fire Protection2008-07-17017 July 2008 M080717-Commission Briefing Slides/Exhibits Briefing on Fire Protection ML0818407352008-06-20020 June 2008 NFPA-805 Workshop Handouts - Harris Fire PRA Lessons Learned ML0818407312008-06-20020 June 2008 NFPA-805 Workshop Handouts - Harris NFPA-805 Results and Lessons Learned ML0812003342008-04-17017 April 2008 NFPA 805 Transition Pilot Plant FAQ Log - April 2008 2024-04-09 Category:Meeting Summary MONTHYEARML24124A0342024-05-0101 May 2024
[Table view]Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24011A1652024-02-12012 February 2024 December 11, 2023, Summary of Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant, Unit 1 Planned Exemption Request Related to Turbine Control System and Reactor Protection System Circuitry ML23157A3202023-06-26026 June 2023 Summary of April 26, 2023, Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant, Unit 1 Planned License Amendment Request Related to Turbine Control System and Reactor Protection System Circuitry ML23151A1232023-05-31031 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Shearon Harris Nuclear Plant ML22167A1852022-06-30030 June 2022 Summary of June 6, 2022, Meeting with Duke Energy to Discuss Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI) 191 ML22129A0062022-05-10010 May 2022 Summary of April 20, 2022, Meeting with Duke Energy Progress, LLC, to Discuss Proposed License Amendment Request to Revise Reactor Coolant System Pressure Isolation Valve Operational Leakage Surveillance Requirement Frequency (L-2022-LRM 00 ML22130A0302022-05-0909 May 2022 Summary of Public Meeting on 2021 Annual Assessment Meeting Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324; and Shearon Harris Nuclear Power Plant, Docket No. 50-400, Meeting Number 20220350 ML21341A5542021-12-29029 December 2021 Summary of November 29, 2021, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Planned License Amendment Request to Relocate ML21172A2672021-08-13013 August 2021 Regulatory Audit Summary Related to the Review of LAR to Revise 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors, Categorization Process to Reflect an Alternative Seis ML21131A1472021-05-11011 May 2021 Public Meeting Summary 2020 Annual Assessment Meeting Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324; and Shearon Harris Nuclear Power Plant, Docket No. 50-400, Meeting Number 20210385 ML20136A2222020-05-15015 May 2020 Har - Bru 2019 Aam Meeting Summary ML19331A8062020-01-29029 January 2020 Summary of November 13, 2019 Closed Meeting with Duke Energy Carolinas, LLC and Duke Energy Progress, LLC, to Discuss Security-Related Information for Its Licensed Facilities ML19329A0232019-11-27027 November 2019 Summary of October 29, 2019 Conference Call with Duke Energy Progress, LLC Regarding the Fall 2019 Steam Generator Tube Inspections ML19241A2902019-09-24024 September 2019 Summary of August 22, 2019, Meeting with Duke Energy Progress, LLC Proposed License Amendment Request to Adopt Risk-Informed Completion Times ML19220A6702019-08-26026 August 2019 Summary of August 7, 2019, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Proposed License Amendment Request for a Common Emergency Plan ML19113A0652019-05-14014 May 2019 Summary of Meeting with Duke Energy to Discuss Proposed License Amendment Request for Shearon Harris, Unit 1, Technical Specification Changes Associated with Departure from Nucleate Boiling Ratio Safety Limit ML19120A1342019-05-0606 May 2019 3/15/19 Summary of Public Meeting with Nuclear Entergy Institute, Duke Energy, and Southern Nuclear Operating Company Post-Pilot Implementation of Tornado Missile Risk Evaluator Methodology at Vogtle, Units 1 and 2 and Shearon Harris, Unit ML19123A3522019-05-0202 May 2019 Public Meeting Summary - Shearon Harris Nuclear Plant, Docket No. 50-400 ML19087A0622019-04-11011 April 2019 Summary of March 25, 2019, Public Teleconference with Duke Energy to Discuss the Request for Additional Information Response Regarding the Proposed Alternative to the Depth Sizing Qualification Requirement (Duke Energy Fleet Relief Request ML18352A3572019-01-0808 January 2019 Summary of Meeting with Duke Energy Progress, LLC to Discuss Proposed License Amendment Request for Shearon Harris Nuclear Power Plant, Unit 1, Regarding Emergency Plan Changes ML18361A6712019-01-0808 January 2019 Summary of Meeting with Duke Energy Progress, LLC to Discuss License Amendment Request for Shearon Harris Unit 1, Regarding 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, ML18355A8142019-01-0707 January 2019 Summary of December 20, 2018, Teleconference Meeting with Duke Energy Progress, LLC to Discuss a Proposed License Amendment Request for Shearon Harris Unit 1, Regarding a Risk-Informed Essential Services Chilled Water System TS ML18094A2632018-08-17017 August 2018 Summary of 01/18/2018, Public Meeting with Nuclear Energy Institute, Duke Energy, Southern Nuclear Operating Co., Entergy Operations, Inc. to Discuss Development of Tornado Missile Risk Evaluator Methodology ML18109A0912018-04-19019 April 2018 Summary of 2017 Annual Assessment Public Meeting Regarding Shearon Harris Nuclear Plant, Docket No. 50-400 ML18088A0732018-04-0303 April 2018 March 27, 2018, Summary of Presubmittal Meeting with Duke Energy Progress, LLC to Discuss a Proposed Relief Request for Shearon Harris Nuclear Power Plant, Unit 1 ML18064A1332018-03-19019 March 2018 Summary of February 27, 2018, Meeting with Duke Energy Progress, LLC to Discuss Proposed License Amendment Request for Shearon Harris Nuclear Power Plant, Unit 1, Regarding Emergency Plan Emergency Action Level Scheme Changes (L-2017-LRM-00 ML17340A1302017-12-22022 December 2017 Summary of November 29, 2017, Meeting with Duke Energy Progress, LLC to Discuss Proposed License Amendment Requests to Implement the Requirement of 10 CFR 50.69 at Brunswick, Shearon Harris, and H. B. Robinson ML17340A0612017-12-0808 December 2017 11/8/17 Summary of Teleconference with Entergy Operations, Inc., Tornado Missile Risk Evaluator with Applicability to Submittals from Duke Energy and Southern Nuclear Operating Co, Inc. ML17244A0742017-09-28028 September 2017 8/17/2017 Summary of Public Meeting with Nuclear Energy Institute and Licensees to Discuss the Tornado Missile Risk Evaluation Tool for Grand Gulf, Shearon Harris, and Vogtle, Units 1 and 2 ML17257A0992017-09-26026 September 2017 Summary of Public Meeting with Nuclear Energy Institute and Licensees to Discuss the Tornado Missile Risk Evaluation Tool for Grand Gulf, Shearon Harris, and Vogtle, Units 1 and 2 ML17223A1212017-08-17017 August 2017 Summary of August 3, 2017, Meeting with Duke Energy Progress, LLC on Proposed License Amendment Request to Implement Fuel Reload Design Methodology Reports for Shearon Harris and H. B. Robinson ML17145A3142017-05-25025 May 2017 EOC Meeting Summary ML16286A0152016-11-0101 November 2016 Summary Of September 29, 2016, Duke Energy Progress, LLC. To Discuss Proposed License Amendment Request Regarding Shearon Harris Nuclear Power Plant, Unit 1, BWR Storage Rack Inserts And The Spent Fuel Pool Criticality Analysis (CAC No. MF8327) ML16235A2382016-10-17017 October 2016 Summary of the July 12-13, 2016 Audit Supporting the U.S. Nuclear Regulatory Commission Review of DPC-NE-1008-P, Nuclear Design Methodology Using CASMO-5/SIMULATE-3 for Westinghouse Reactors ML16125A0992016-05-20020 May 2016 Summary of May 2, 2016, Meeting with Duke Energy Progress, Inc. to Discuss Fuel Reload Design Methodology Reports and Proposed Supplement to a License Amendment Request Regarding Shearon Harris and H.B. Robinson ML16134A1552016-05-12012 May 2016 Public Meeting Summary - 2015 Annual Assessment Public Meeting Regarding Shearon Harris Nuclear Plant ML16112A3772016-04-25025 April 2016 Summary of Meeting with Duke Energy Progress, Inc. to Discuss the Shearon Harris Nuclear Plant, Unit 1, TSTF-425 LAR Request for Additional Information Reponses ML16034A5242016-03-11011 March 2016 Summary of February 1, 2016, Pre-submittal Meeting with Duke Energy Regarding Consolidation of Emergency Operations Facilities ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment ML15280A2532015-11-25025 November 2015 Summary of Mtg. with Duke Energy Progress Inc. to Discuss Fuel Reload Design Methodology Reports & Proposed License Amendment Request Shearon Harris Nuclear Power Plant Unit 1 and H.B. Robinson Steam Electric Plant Unit No. 2 (MF6701/MF6702 ML15202A4752015-09-24024 September 2015 Summary of Meeting with Duke Energy Progress, Inc. to Discuss Shearon Harris Nuclear Power Plant, Unit 1, Proposed License Amendment Request Regarding Technical Specifications for the Pressurizer and Main Steam Line Safety Valves (MF6233) ML14129A3352014-05-0909 May 2014 Summary of Category 1 Public Meeting - Annual Assessment of Shearon Harris Nuclear Plant ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13204A2672013-09-27027 September 2013 07/09/13 Summary of Meeting with Duke Energy Regarding a Nonconservative Technical Specification Loss of Offsite Power Voltage Setpoint License Amendment Request ML13218B3692013-09-27027 September 2013 7/30/2013 - Summary of Meeting with Duke Energy Regarding a Change to the Emergency Response Facility Activation Timeliness and Criteria ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13171A3292013-06-20020 June 2013 Public Meeting Summary, Category 3, NRC Special Inspection on Reactor Vessel Head Nozzle Repair of Shearon Harris Nuclear Plant ML13155A1052013-06-12012 June 2013 May 2, 2013, Summary of Meeting with Duke Energy Concerning the Relocation of the Emergency Operating Facilities ML13151A2262013-05-30030 May 2013 Meeting Summary - Category 1 Public Meeting Annual Assessment - Shearon Harris Nuclear Plant - Docket 50-400 ML12277A0252012-11-0202 November 2012 10/2/12 Summary of Meeting with Duke Energy Carolinas to Discuss Nonconservative Technical Specifications License Amendment Requests 2024-05-01 Category:Slides and Viewgraphs MONTHYEARML24100A8062024-04-0909 April 2024
[Table view]Duke Energy Sites Annual Assessment Meeting Presentation Slides April 23, 2024 ML23341A1522023-12-0707 December 2023 December 11, 2023 Public Meeting - RIPE Exemption Request - Licensee Slides ML23114A0672023-04-26026 April 2023 April 26 2023 Public Meeting - RIPE LAR - Licensee Slides ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22153A3842022-06-0606 June 2022 Duke Energy Presentation Material for June 6, 2022 Public Meeting on GSI-191 Closeout ML22109A2122022-04-20020 April 2022 Duke Energy Pre-Submittal Public April 20, 2022, Meeting Presentation ML22091A1332022-04-0101 April 2022 Bru Har Combined 2021 Assessment Meeting Slides ML21322A3262021-11-29029 November 2021 Duke Energy November 29, 2021 Pre-Submittal Public Meeting Slides for EOF Relocation Licensing Amendment Request ML20100G6342020-04-0909 April 2020 Revised- Bru 2019 Annual Assessment Meeting Slides ML20099D1282020-04-0808 April 2020 Bru 2019 Mtg Slides ML20099C9992020-04-0808 April 2020 Har 2019 Mtg Slides ML19318F2912019-11-18018 November 2019 Duke Energy Presentation for the Pre-submittal Meeting on November 18, 2019, Regarding the RPV Stud Examination Relief Request ML19233A0462019-08-21021 August 2019 Presentation: Harris/Nrc Pre-submittal Meeting: Risk-Informed Completion Times, August 22, 2019 ML19214A0562019-08-0707 August 2019 Presentation: Duke Energy Presubmittal Meeting - August 7, 2019 ML19123A3522019-05-0202 May 2019 Public Meeting Summary - Shearon Harris Nuclear Plant, Docket No. 50-400 ML18351A1342018-12-20020 December 2018 December 20, 2018 Pre-submittal Meeting Slides for Escw Risk-Informed LAR ML18333A1822018-11-0808 November 2018 Pre-Submittal Meeting - November 8, 2018 - License Amendment Request for Shearon Harris Nuclear Power Plant Emergency Plan Revision ML17331A6272017-11-29029 November 2017 Duke Energy Pre-Submittal Meeting Presentation, Brunswick, Harris, and Robinson License Amendment Requests Regarding 10 CFR 50.69 ML17318A1592017-11-0808 November 2017 Meeting Slides - November 8, 2017 Teleconference with NEI Concerning Feedback on Tornado Missile Risk Evaluator Methodology -Final ML17200C7802017-07-19019 July 2017 Duke Energy Pre-submittal Meeting Presentation, August 3, 2017, Harris and Robinson License Amendment Request to Support the Transition to Duke Non-LOCA Analysis Methods, MF9824, MF9825 ML16267A0292016-09-29029 September 2016 SFP Pre-Submittal Meeting Slides - BWR Storage Rack Inserts, Updated NCS Analysis at Harris Nuclear Plant ML16112A2932016-05-0202 May 2016 05/02/2016 Presentation for Closed Pre-Submittal Meeting with Duke Energy Progress, Inc., to Discuss Fuel Reload Design Methodology Reports and Proposed LAR Re. H. B. Robinson And Shearon Harris Plants (CAC Nos. MF7443 And MF7444) ML14129A3352014-05-0909 May 2014 Summary of Category 1 Public Meeting - Annual Assessment of Shearon Harris Nuclear Plant ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. NEI 01-01, NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting2013-07-31031 July 2013 NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting ML13212A3372013-07-31031 July 2013 NRC NEI-01-01 Meeting Presentation on 7/31/13 Digital I&C Meeting NEI 01-01, 7/31/2013 NRC Public Meeting Presentation on NEI 01-012013-07-30030 July 2013 7/31/2013 NRC Public Meeting Presentation on NEI 01-01 ML13211A3782013-07-30030 July 2013 7/31/2013 NRC Public Meeting Presentation on NEI 01-01 ML13204A2562013-07-0909 July 2013 Handout - LOOP Voltage Setpoint Change Presubmittal Conference Call - July 9, 2013 ML13170A3352013-06-13013 June 2013 Presentation - NRC Special Inspection Meeting - Harris Reactor Pressure Vessel ML12277A0272012-10-0202 October 2012 Slides - Summary of Meeting with Duke Energy Carolinas to Discuss Noncenservative Technical Specifications License Amendment Requests ML12242A4322012-08-28028 August 2012 Summary of Category 1 Public Meeting - Regulatory Conference and Predecisional Enforcement Conference ML12076A1652012-01-11011 January 2012 Meeting Slides - Harris Realistic LBLOCA Question Response Meeting HNP-12-028, Realistic LBLOCA Question Response Meeting Handout, Enclosure 3 to HNP-12-0282012-01-11011 January 2012 Realistic LBLOCA Question Response Meeting Handout, Enclosure 3 to HNP-12-028 ML11354A2912011-12-13013 December 2011 Meeting Slides - Meeting with Carolina Power and Light Discussion of ANP-3011 ML1113704082011-05-0909 May 2011 Meeting Slides Regarding Human Performance Improvement ML1107301382011-04-21021 April 2011 February 22, 2011, Summary of Pre-application Meeting with Carolina Power & Light and Representatives Regarding Upcoming BWR Boraflew License Amendment Request W/ Public Meeting Slides ML1111000262011-04-20020 April 2011 Meeting Summary - Shearon Harris - Slide Presentation ML1014102712010-05-18018 May 2010 Shearon Harris Nuclear Plant Annual Assessment Meeting Slides ML0922900342009-08-17017 August 2009 08/19/09-Meeting Slides for 11th International Seminar on Fire Safety in Nuclear Power Plants and Installations, Risk-Informed, Performance-Based Fire Protection: a U.S. Regulatory Perspective ML0916605042009-06-24024 June 2009 04/21-22/2009 Summary of Category 2 Meeting with Progress Energy Carolinas, Inc., and Duke Energy Carolinas, LLC, to Discuss Topics Involving the License Amendment Requests to Transition Shearon, Unit 1 and Oconee to NFPA 805 ML0915905552009-06-0505 June 2009 Summary of Category 1 Public Meeting to Discuss Annual Assessment of Shearon Harris Nuclear Plant, Unit 1 ML0829601532008-11-17017 November 2008 Summary of Meeting with Progress Energy Carolinas, Inc., to Discuss Shearon Harris Unit 1 National Fire Protection Association Standard 805 License Amendment Request ML0830800052008-10-31031 October 2008 Meeting Slides, Progress Energy Public Meeting, NRC Region II Visit ML0820703912008-07-17017 July 2008 Meeting Handouts from 7/17/08 Public Meeting on the Harris and Oconee LARs to Transition to NFPA-805 M080717, M080717-Commission Briefing Slides/Exhibits Briefing on Fire Protection2008-07-17017 July 2008 M080717-Commission Briefing Slides/Exhibits Briefing on Fire Protection ML0818407312008-06-20020 June 2008 NFPA-805 Workshop Handouts - Harris NFPA-805 Results and Lessons Learned ML0818407352008-06-20020 June 2008 NFPA-805 Workshop Handouts - Harris Fire PRA Lessons Learned ML0815502662008-05-20020 May 2008 Harris Slides, NRC Annual Assessment Meeting 2024-04-09 |
Contents
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 May 9, 2014 Ernest J. Kapopoulos, Jr.
Vice President Shearon Harris Nuclear Power Plant 5413 Shearon Harris Rd New Hill, NC 27562-0165
SUBJECT:
MEETING
SUMMARY
- CATEGORY 1 PUBLIC MEETING - ANNUAL ASSESSMENT OF SHEARON HARRIS NUCLEAR PLANT, DOCKET NO. 50-400
Dear Mr. Kapopoulos:
This refers to the Category 1 public meeting which was held on May 5, 2014, at 5:00 p.m.,
Eastern Daylight Time (EDT), at the Holly Springs Cultural Center. The purpose of the meeting was to discuss the NRC Reactor Oversight Process Annual Assessment of your Shearon Harris Nuclear Power Plant.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agency wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 997-4645.
Sincerely,
/RA/
George T. Hopper, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-400 License Nos.: NPF-63
Enclosure:
- 1. List of Attendees
- 2. NRC Presentation/Handout cc Distribution via ListServ
Ernest J. Kapopoulos, Jr.
Vice President Shearon Harris Nuclear Power Plant 5413 Shearon Harris Rd New Hill, NC 27562-0165
SUBJECT:
MEETING
SUMMARY
- CATEGORY 1 PUBLIC MEETING - ANNUAL ASSESSMENT OF SHEARON HARRIS NUCLEAR PLANT, DOCKET NO. 50-400
Dear Mr. Kapopoulos:
This refers to the Category 1 public meeting which was held on May 5, 2014, at 5:00 p.m.,
Eastern Daylight Time (EDT), at the Holly Springs Cultural Center. The purpose of the meeting was to discuss the NRC Reactor Oversight Process Annual Assessment of your Shearon Harris Nuclear Power Plant.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agency wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/ reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 997-4645.
Sincerely,
/RA/
George T. Hopper, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-400 License Nos.: NPF-63
Enclosure:
- 1. List of Attendees
- 2. NRC Presentation/Handout cc Distribution via ListServ X PUBLICLY AVAILABLE NON-PUBLICLY AVAILABLE SENSITIVE X NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER:_ ___________ _________ X SUNSI REVIEW OFFICE RII:DRP RII:DRP SIGNATURE /RA/ /RA/
NAME JDodson GHopper DATE 05/08/2014 05/09/2014 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: G:\DRPII\RPB4\HARRIS\MEETINGS\HARRIS 2013 EOC MEETING
SUMMARY
.DOCX
2 Enclosure 1
2 Enclosure 2
3 Enclosure 2
4 Enclosure 2
5 Enclosure 2
6 Enclosure 2
7 Enclosure 2
8 Enclosure 2
9 Enclosure 2
10 Enclosure 2
11 Enclosure 2
12 Enclosure 2
13 Enclosure 2
14 Enclosure 2