SUBJECT:

SHEARON HARRIS NUCLEAR PLANT, UNIT 1 - SECURITY BASELINE INSPECTION REPORT 05000400/2024401

Dear Linwood Faulk:

On June 13, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Shearon Harris Nuclear Plant, Unit 1 and discussed the results of this inspection with David Hoffman and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jannette G. Worosilo, Chief Plant Support Branch Division of Reactor Safety Docket No. 05000400 License No. NPF-63

Enclosure:

As stated

Inspection Report

Docket Number:

05000400

License Number:

NPF-63

Report Number:

05000400/2024401

Enterprise Identifier:

I-2024-401-0052

Licensee:

Duke Energy Progress, LLC

Facility:

Shearon Harris Nuclear Plant, Unit 1

Location:

New, Hill, NC

Inspection Dates:

June 10, 2024 to June 13, 2024

Inspectors:

D. Egelstad, Physical Security Inspector

J. Justice, Sr. Physical Security Inspector

Approved By:

Jannette G. Worosilo, Chief

Plant Support Branch

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Shearon Harris Nuclear Plant, Unit 1, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

SAFEGUARDS

71130.02 - Access Control

The inspectors evaluated the access control program through completion of the following

inspection elements: Access Control

(1)

  • Tier I: All Requirements
  • Tier II: 02.06(a - c), 2.08(a,d,f,g,i)
  • Tier III: 02.09

71130.09 - Security Plan Changes

The inspectors evaluated the security plan changes through completion of the following procedure elements:

Security Plan Changes (1 Partial)

(1)

(Partial)

The opportunity to apply this procedure was not available in accordance with IMC 0306. This sample was not available because the licensee did not conduct the activity covered by this IP. Specifically, the licensee has not initiated a physical security plan change in accordance with 10 CFR 50.54(p(2) since the last performance of this IP.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17) (1 Sample)

(1) May 2023 - May

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On June 13, 2024, the inspectors presented the security baseline inspection results to David Hoffman and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

2512626

2512699

2488746

2482763

2493687

2498328

2499594

2505091

Miscellaneous

Protected Area/ Vital Area Control Log

04/19/2024

Shearon Harris Nuclear Plant Physical Security Plan

Rev 16

AD-SY-ALL-0110

Protection of Information related to Nuclear Safety

Rev 10

AD-SY-ALL-0210

Site Access Controls

Rev 8

AD-SY-ALL-0215

Security Search and Entry Processing

Rev 12

AD-SY-ALL-0240

Security Key and Lock Controls

Rev 3

CSD-SY-HNP-

215-01

HNP Security Search and Entry Processing

Rev 5

CSD-SY-HNP-

240-01

HNP Security Key and Lock Program

Rev 0

Procedures

SP-015

Emergency Plan Support

Rev 33

71130.02

Self-Assessments

24-HNP-SEC-

LSA-01

Nuclear Oversight - Conditional Audit Harris Physical

Security

01/18/2024

71151

Procedures

AD-PI-ALL-0700

Performance Indicators

Rev 6