NFPA 805 Pilot License Amendment Request Review
& Infrastructure Update SHEARON HARRIS NFPA 805 LAR REVIEW Date Available Information LAR Letter and Enclosures 1 & 2*
5/29/08 ML081560641 LAR Enclosure 3: Publically Available Transition Report*
5/29/08 ML081840706 LAR Submission Ceremony 7/17/08 ML082060554 NRC LAR Acceptance Review Letter to Progress Energy 9/26/08 ML082701158 Public Meeting to Discuss Harris Supplement 9/29/08 ML082960153 Harris LAR Supplement Due to NRC 11/14/08 ML083240593 Harris LAR Supplement (Part 2) 12/11/08 Harris LAR Site Audit Plan (3/16-20/09) 3/09 Issue Harris RAIs to Progress Energy 3/09**
Receive Harris RAI Responses from Progress Energy 5/09**
Harris Safety Evaluation Issued to Progress Energy 9/09**
OCONEE NFPA 805 LAR REVIEW Date Available Information LAR Letter and Transition Report: Attachment A & B*
5/30/08 ML081650475 Transition Report: Attachment D*
5/30/08 ML082041014 LAR Submission Ceremony 7/17/08 ML082060554 LAR Supplement (Part 2) 10/31/08 NRC LAR Conditional Acceptance Review Letter to Duke Energy 2/2/09 ML090330496 Oconee Site Audit Plan (Audit 2/23 - 27/09) 2/12/09 ML090290196 Issue Oconee LAR Site Audit Summary 3/09 Issue LAR RAIs to Duke Energy 3/09**
Receive LAR RAI Responses from Duke Energy 5/09**
LAR Safety Evaluation Issued to Duke Energy 9/09**
NFPA 805 INFRASTRUCTURE DEVELOPMENT SCHEDULE Date Available Information Received NEI 00-01, Revision 2 from NEI 12/21/07 ML082050625 Received NEI 04-02, Revision 2 from NEI 4/15/08 ML081400332 NRC Comments on NEI 00-01, Rev 2 sent to NEI 6/2/08 ML081640340 SRP 9.5.1.2, Risk-Informed, Performance-Based Fire Protection Public Meeting Summary 10/9/08 ML082830934 NFPA 805 Regulatory Audit Plan Template Memo 12/10/08 ML083100575 SRP 9.5.1.2 Published for Public Comment 1/09 ML090050052 Send NRC Comments on NEI 04-02, Rev 2 (unless covered in RG 1.205, Revision 1) 3/09 Publish Draft RG 1.205, Revision 1 for Public Comment 3/09 Publish RG 1.200, Revision 1 4/09
- The Pilots submitted partial LARs, non-Pilot Licensees are expected to have complete LAR submittals.
- These milestone dates are estimates based on a high-quality supplemental submittal.
- Material is considered SUNSI, awaiting a publically available redacted version from the Licensee.
2/18/2009