M080717, M080717-Commission Briefing Slides/Exhibits Briefing on Fire Protection

From kanterella
Jump to navigation Jump to search
M080717-Commission Briefing Slides/Exhibits Briefing on Fire Protection
ML082000991
Person / Time
Site: Oconee, Harris, Wolf Creek  Duke Energy icon.png
Issue date: 07/17/2008
From: Baxter D, Canavan K, Donahue J, Muench R
Duke Energy Carolinas, Electric Power Research Institute, Progress Energy Carolinas, Wolf Creek
To:
NRC/SECY
References
M080717
Download: ML082000991 (40)


Text

COMMISSION BRIEFING SLIDES/EXHIBITS BRIEFING ON FIRE PROTECTION JULY 17, 2008

Nuclear Regulatory Commission Briefing on Fire Protection July 17, 2008 Mr. Richard A. Muench President and CEO Wolf Creek Nuclear Operating Corporation 1

Discussion Topics

  • Fire Induced Circuit Failures

Operator Manual Actions

  • Licensees working to complete corrective actions by March of 2009

Fire Induced Circuit Failures

  • Status Agreement on conceptual approach Implementation details addressed in future meetings
  • Use of risk to address associated circuit issues without exemption or LAR must be included 4

Fire Induced Circuit Failures

  • Industry I NRC meetings will continue
  • Industry actions in the interim Developing implementation details Guiding use of risk insights for resolution of issues Preparing draft revision to industry guidance
  • Goal - receive NRC endorsement 5

Fire Induced Circuit Failures

  • Use of risk to address fire induced circuit failures in associated circuits

- Regulations do not prohibit

- Use of risk is consistent with the Commission's Policy Statement on use of PRA (60FR42622)

  • Failure to allow could result in

- actions that could raise overall plant risk,

- need for new exemptions or LAR's and/or

- costly modifications for low risk and low safety-significance items 6

NFPA 805 Transition

  • Pilot plants (Oconee and Harris) license amendment requests submitted
  • Activities necessary to enhance regulatory certainty

- Refinement of LAR template

- Resolve PRA issues Minimize requests for additional information 7

Fire PRA

  • Fire PRA is a challenge

- Preliminary results are conservative

- Goal in PRA is to be more realistic

  • Industry and NRC Staff addressing items seen as main contributors to conservatism
  • Goal. is to resolve by late 2008 8

N*FPA 805 Enforcement Discretion

- Limited qualified resources

- Incorporate lessons learned from pilot plants

-Assure consistent licensing bases

  • Near term Commission decision requested 9

N Acronyms

" NFPA National Fire Protection Association

" LAR License Amendment Request

  • PRA Probability Risk Assessment

/

10

NFPA 805 Lessons Learned Shearon Harris Nuclear Plant.

July 17, 2008 Joe Donahue Vice President Engineering I0 N tICI Progress Energy 1

Fire Protection Defense In Depth o Prevent Fires o Prompt Detection Of Fires o Prompt Control and Suppression Of Fires o Separation Of Safety Systems QProgress Energy 0 Ný Page 2

Fire PRA Implementation o Extensive Walkdowns Identified Potential Fire Sources o 4000+ Fire Scenarios Evaluated o NRC Team Review o Industry Expert Peer Review c~NudL A.A G

G Ottr Criiv UProgress Energy Page 3

Fire PRA Implementation

  • Fire PRA Is Acceptable For Use
  • Other Inputs are Used for Decision Making
  • Process Improvements Provided To NRC and Industry NLICI I CProgress Energy Page 4

Harris NFPA 805 Fire Protection o Implements classical requirements o Implements nuclear safety performance criteria o Addresses fire safety during, non-power operations o License amendment request submitted o Transition resources were greater than originally estimated

'10,ip;,, Progress Energy Page 5

Generic Issues Addressed o Hemyc/MT Fire Wrap Qualification o Operator Manual Actions o Multiple Spurious Operations CProgress Energy Page 6

Harris Physical Plant Changes o New Cable Raceway Wrap o New Fire Rated Cable o Upgrades To Hemyc/Mt Wrap o Additional Equipment Separation o Additional Incipient Fire Detection In Critical Electrical Panels K Progress Energy Page 7

Summary o Transition To NFPA 805 Is Improving Fire Protection Program D Resolution Of Generic Fire Protection Issues D Physical Plant Modifications Already Completed D Additional Modifications Being Implemented Np

  • Progress Energy Page 8

b Summary NFPA 805 License Amendment Request Submitted C On Track To Complete Implementation By End Of 2010 6ou Nue CProgress Energy Page 9

NFPA 805 Lessons Learned Oconee Nuclear Station July 17, 2008 David Baxter Site Vice President

,Duke

'Energy

NFPA 805 Lessons

  • Oconee showed that NFPA 805. is an excellent fit for the older -nuclear stations.
  • A good solid Safe Shutdown Analysis documenting deviations with Fire Regulations should be in place to start transition
Duke 7;Energy

NFPA 805 Lessons

  • The pilot process was very complicated, time consuming and expensive.
  • Document and calculation reviews took much longer than expected due to new program.

Duke

~Energya

NFPA 805 Lessons

  • Oconee required separate Fire PRA models.

oNUREG-6850 turned out to be somewhat conservative, but provided a good foundation to build on.

6iDuke

!FEnergy

D NFPA 805 Lessons

  • Although further tuning is planned, the Fire PRA's models realistically modeled the plant.
  • The process of transition is very man-power intensive Duke 7Energy

r ELECTRIC POWER R RESEARCH INSTITUTE BRIEFING ON FIRE PROTECTION ISSUES Ken Canavan Senior Program Manager Risk and Safety Management July 2008

EPRI Fire PRA Philosophy

  • Consistent with the PRA Policy Statement "Use of the PRA technology should be increased in all regulatory matters to the extent supported by the state of the art ... "
  • Committed to supporting a risk-informed, performance based approach to fire protection

- Realistic methods

- Realistic input

- Monitoring and feedback process 2 I VS' C IE

© 2008 Electric Power Research Institute, Inc. All rights reserved.

Fire PRA Methodology Development

- NRC-RES / EPRI collaboration (EPRI 1011989)

- Only pieces piloted (initially) 0 Two Fire PRA Pilots

- Initial results are conservative

- Not unexpected

- Result of individual minor to moderate conservatisms ELECTRIC IPOW E

© 2008 Electric Power Research Institute, Inc. All rights reserved. 8m ira REEACHINTITUTE

Fire PRA Methodology Issues,

  • Fire Ignition Frequencies

" Credit for Incipient Detection

" Treatment of Large Oil Fires

" Fire Growth and Propagation Models

" Credit for Fire Suppression

" -Hot Short Susceptibility, Probability and Duration

  • High Energy Arching Faults

" Cable Tray Fire Modeling

©0I ELETRICPPWýTR (D 2008 Electric Power Research Institute, Inc. All rights reserved. 4_ = 0 RESEACH INSTITUJTE

Other Issues, Progress and Challenges

  • Other Issues

- Shortage of Trained Risk Personnel

- Practical modeling limitations

  • -Progress

- Education of Risk Professionals and Fire PRA Methods Training

- EPRI / NRC-RES working to refine Fire PRA methods Challenges

- Available resources

- Time constraints

© 2008 Electric Power Research Institute, Inc. All rights reserved.

'2IELECT111POWER RE SEARHIN~STITUTE

SU.S.NRC Uniiced Staces Nuclear Regulatory Cormmission ProtectingPeople and the Environment Commission Briefing on Fire Protection Issues July 17, 2008

Agenda

" Introduction

-Jack Grobe, NRR

" Current Issues

- Mark Cunningham, NRR

  • Summary

- Jack Grobe, NRR 2

Introduction

  • Fire protection at operating reactors
  • Steering Committee activities
  • Remaining issues

- Fire barrier performance

- Operator manual actions

- Fire-induced circuit failures

- Implementation of NFPA 805 3

Fire Barrier Performance

  • Protection of electrical equipment required

" Inspections and research identified deficiencies

" Actions were taken

" Documenting closure 4

Operator Manual Actions

" Inspections identified inconsistencies RIS 2006-10 clarified regulatory positions

" Completing closure

- Plant-specific resolution

- Staff follow up 5

Fire-Induced Circuit Failures

- Methods for protecting safe shutdown capability

- Enforcement discretion proposal

  • Achieving closure

- Finalize and implement guidance

- Complete direct current circuits research

- Implementing closure plan 6 I

NFPA 805 Implementation

  • Alternative approach

- Risk informed

- Performance based

  • 47 units committed to transition

NFPA 805 Implementation

  • Infrastructure being finalized

- Technical methods and standards

- Regulatory Guidance Resource planning and allocation Communications 8

I NFPA 805 Implementation

  • Implementing closure plan

-Finalize guidance

- Standardize review process

- Share lessons learned

- Receive and review amendments Licensees implement changes Staff inspects implementation 9

Summary

  • Maintain a stable and predictable regulatory environment
  • Communicate with licensees and public 10