Category:Meeting Agenda
MONTHYEARPMNS20241326, Notice of Presubmittal Meeting with Duke Energy to Discuss Their Plans to Submit a License Amendment Request for Adoption of PAD5 Code, Fsloca, and Use of Axiomtm Fuel Rod Cladding2024-10-17017 October 2024 Notice of Presubmittal Meeting with Duke Energy to Discuss Their Plans to Submit a License Amendment Request for Adoption of PAD5 Code, Fsloca, and Use of Axiomtm Fuel Rod Cladding PMNS20240948, Regulatory Conference with Duke Energy Carolinas, LLC (Duke) Catawba Nuclear Station2024-07-23023 July 2024 Regulatory Conference with Duke Energy Carolinas, LLC (Duke) Catawba Nuclear Station PMNS20240596, Public Meeting with Duke Energy Progress, LLC to Discuss Methods to Review Plant-Specific Topical Reports for H.B. Robinson Steam Electric Plant, Unit 22024-04-26026 April 2024 Public Meeting with Duke Energy Progress, LLC to Discuss Methods to Review Plant-Specific Topical Reports for H.B. Robinson Steam Electric Plant, Unit 2 PMNS20240492, Duke Sites Annual Assessment Meeting2024-04-10010 April 2024 Duke Sites Annual Assessment Meeting ML24100A8062024-04-0909 April 2024 Duke Energy Sites Annual Assessment Meeting Presentation Slides April 23, 2024 PMNS20240153, Public Meeting to Receive Comments on the Draft Site-Specific Oconee Environmental Impact Statement2024-02-0808 February 2024 Public Meeting to Receive Comments on the Draft Site-Specific Oconee Environmental Impact Statement PMNS20240150, Public Meeting to Receive Comments on the Draft Site-Specific Oconee Environmental Impact Statement2024-02-0808 February 2024 Public Meeting to Receive Comments on the Draft Site-Specific Oconee Environmental Impact Statement PMNS20231317, Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant Planned Exemption Request to Be Submitted the Under Risk-Informed Process for Evaluations (RIPE)2023-11-21021 November 2023 Meeting with Duke Energy to Discuss a Shearon Harris Nuclear Power Plant Planned Exemption Request to Be Submitted the Under Risk-Informed Process for Evaluations (RIPE) PMNS20230561, Annual Assessment Meeting2023-04-26026 April 2023 Annual Assessment Meeting PMNS20230406, Meeting with Duke Energy to Discuss License Amendment Request to Add Feedwater Isolation on Steam Generator Level High-High to Technical Specifications2023-04-13013 April 2023 Meeting with Duke Energy to Discuss License Amendment Request to Add Feedwater Isolation on Steam Generator Level High-High to Technical Specifications PMNS20230395, Meeting with Duke Energy to Discuss a Planned License Amendment Request (LAR) to Be Submitted Under Risk-Informed Process for Evaluations (RIPE)2023-04-13013 April 2023 Meeting with Duke Energy to Discuss a Planned License Amendment Request (LAR) to Be Submitted Under Risk-Informed Process for Evaluations (RIPE) PMNS20230392, Annual Assessment Meeting2023-04-0707 April 2023 Annual Assessment Meeting PMNS20230332, and Oconee Nuclear Station Annual Assessment Meeting for 20222023-03-30030 March 2023 and Oconee Nuclear Station Annual Assessment Meeting for 2022 PMNS20230333, Annual Assessment Meeting2023-03-29029 March 2023 Annual Assessment Meeting ML22336A0382022-12-0808 December 2022 Presentation Slides December 8, 2022, pre-submittal Meeting to Discuss Proposed License Amendment Request Regarding TS 3.7.11, Control Room Area Chilled Water System (Cracws) PMNS20221105, Pre-submittal Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Catawba Nuclear Station, Units 1 and 22022-10-25025 October 2022 Pre-submittal Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Catawba Nuclear Station, Units 1 and 2 PMNS20221085, Pre-submittal Meeting with Duke Energy Carolinas, LLC (Duke Energy, the Licensee) to Discuss Proposed License Amendments to Adopt TSTF-505 and 10 CFR 50.69 at McGuire Nuclear Station, Units 1 and 2 (McGuire)2022-10-25025 October 2022 Pre-submittal Meeting with Duke Energy Carolinas, LLC (Duke Energy, the Licensee) to Discuss Proposed License Amendments to Adopt TSTF-505 and 10 CFR 50.69 at McGuire Nuclear Station, Units 1 and 2 (McGuire) PMNS20220916, Public Meeting with Duke Energy to Discuss a Planned TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1, License Amendment Request Supplement for H. B. Robinson Steam Electric Plant, Unit No. 22022-09-0909 September 2022 Public Meeting with Duke Energy to Discuss a Planned TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1, License Amendment Request Supplement for H. B. Robinson Steam Electric Plant, Unit No. 2 PMNS20220537, Meeting with Duke Energy to Discuss the Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI)-1912022-06-0202 June 2022 Meeting with Duke Energy to Discuss the Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI)-191 PMNS20220536, Duke Energy Progress, LLC Discussion Regarding TSTF-577 Request for Additional Information Response Regarding for the H. B. Robinson Steam Electric Plant, Unit No. 22022-05-25025 May 2022 Duke Energy Progress, LLC Discussion Regarding TSTF-577 Request for Additional Information Response Regarding for the H. B. Robinson Steam Electric Plant, Unit No. 2 PMNS20220533, Pre-submittal Meeting with Duke Energy Progress, LLC to Discuss a Future Licensing Submittal Regarding Proposed Technical Specification 3.3.2 for the H. B. Robinson Steam Electric Plant, Unit No. 22022-05-19019 May 2022 Pre-submittal Meeting with Duke Energy Progress, LLC to Discuss a Future Licensing Submittal Regarding Proposed Technical Specification 3.3.2 for the H. B. Robinson Steam Electric Plant, Unit No. 2 PMNS20220375, Pre-submittal Public Meeting with Duke Energy to Discuss the Proposed License Amendment Request to Revise Surveillance Frequency for Reactor Cooling System Pressurized Isolation Valve2022-04-19019 April 2022 Pre-submittal Public Meeting with Duke Energy to Discuss the Proposed License Amendment Request to Revise Surveillance Frequency for Reactor Cooling System Pressurized Isolation Valve PMNS20220350, Annual Assessment Meetingshearon Harris Nuclear Power Plant Annual Assessment Meeting2022-04-0404 April 2022 Annual Assessment Meetingshearon Harris Nuclear Power Plant Annual Assessment Meeting PMNS20220324, Annual Assessment Meeting2022-03-30030 March 2022 Annual Assessment Meeting PMNS20220260, Presubmittal Meeting with Duke Energy Progress, LLC to Discuss a Future Licensing Submittal Regarding Proposed Removal of 4.160 Kv Bus 2 from Surveillance Requirements (SR) 3.8.1.16 for the H. B. Robinson Steam Electric Plant, Unit No.2022-03-15015 March 2022 Presubmittal Meeting with Duke Energy Progress, LLC to Discuss a Future Licensing Submittal Regarding Proposed Removal of 4.160 Kv Bus 2 from Surveillance Requirements (SR) 3.8.1.16 for the H. B. Robinson Steam Electric Plant, Unit No. 2 PMNS20220232, and Oconee Nuclear Station Annual Assessment Meeting for 20212022-03-10010 March 2022 and Oconee Nuclear Station Annual Assessment Meeting for 2021 ML22007A2592022-02-0202 February 2022 Presubmittal Licensee Presentation for TS 3.5.3 PIV Testing LAR PMNS20220093, SLRA - Public Meeting to Discuss Select RAI Responses2022-02-0202 February 2022 SLRA - Public Meeting to Discuss Select RAI Responses PMNS20220016, Presubmittal Meeting with Duke Energy Progress, LLC to Discuss a Future Licensing Submittal Regarding Proposed Revision to Technical Specification (TS) 3.5.3, ECCS - Shutdown, for the H. B. Robinson Steam Electric Plant, Unit No. 22022-01-12012 January 2022 Presubmittal Meeting with Duke Energy Progress, LLC to Discuss a Future Licensing Submittal Regarding Proposed Revision to Technical Specification (TS) 3.5.3, ECCS - Shutdown, for the H. B. Robinson Steam Electric Plant, Unit No. 2 ML21336A1422021-12-0707 December 2021 December 7, 2021, Pre-submittal Presentation Slides Regarding Embedded Flaw Repair Relief Request - Revised PMNS20211387, Pre-application Meeting with Duke Energy Carolinas to Discuss Relief Request Related to the Reactor Vessel Closure Head Nozzle Repair for Catawba Nuclear Station Unit 22021-10-25025 October 2021 Pre-application Meeting with Duke Energy Carolinas to Discuss Relief Request Related to the Reactor Vessel Closure Head Nozzle Repair for Catawba Nuclear Station Unit 2 PMNS20211268, Environmental Scoping Meeting Related to the Saint Lucie Plant, Units 1 and 2, Subsequent License Renewal Application2021-10-19019 October 2021 Environmental Scoping Meeting Related to the Saint Lucie Plant, Units 1 and 2, Subsequent License Renewal Application PMNS20211035, Environmental Scoping Meeting Related to the Oconee Nuclear Station, Unit Nos. 1, 2 and 3, Subsequent License Renewal Application2021-08-0909 August 2021 Environmental Scoping Meeting Related to the Oconee Nuclear Station, Unit Nos. 1, 2 and 3, Subsequent License Renewal Application PMNS20211019, Pre-application Meeting with Duke Energy Carolinas to Discuss a Revision to the end-of-cycle Moderator Temperature Coefficient Measurement Methodology for Catawba and McGuire Nuclear Stations2021-08-0303 August 2021 Pre-application Meeting with Duke Energy Carolinas to Discuss a Revision to the end-of-cycle Moderator Temperature Coefficient Measurement Methodology for Catawba and McGuire Nuclear Stations ML21174A3212021-06-24024 June 2021 Licensee Presentation for Robinson Presubmittal Meeting TSTF 577, Rev. 1 PMNS20210775, Presubmittal Meeting with Duke Energy Progress, Llc., to Discuss a Future Licensing Submittal of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections for the H. B. Robinson Steam Electric Plant, Unit No. 22021-06-10010 June 2021 Presubmittal Meeting with Duke Energy Progress, Llc., to Discuss a Future Licensing Submittal of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections for the H. B. Robinson Steam Electric Plant, Unit No. 2 PMNS20210460, Annual Assessment Meeting2021-04-15015 April 2021 Annual Assessment Meeting PMNS20210385, and Shearon Harris Nuclear Plant 2020 Annual Assessment Meeting2021-04-12012 April 2021 and Shearon Harris Nuclear Plant 2020 Annual Assessment Meeting PMNS20210274, Stations Annual Assessment Meeting2021-03-31031 March 2021 Stations Annual Assessment Meeting PMNS20210279, Pre-application Meeting with Duke Energy Carolinas to Discuss Relief Request Related to Code Case N-853 for Oconee Nuclear Station2021-03-19019 March 2021 Pre-application Meeting with Duke Energy Carolinas to Discuss Relief Request Related to Code Case N-853 for Oconee Nuclear Station ML21041A4532021-02-17017 February 2021 Brunswick/Nrc Pre-submittal Meeting: LAR to Adopt TSTF-505, Rev. 2 (Risk-Informed Completion Times) Presentation PMNS20210152, Presubmittal Meeting with Duke Energy Progress, Llc. to Discuss a Future Relief Request Concerning Containment Metallic Liners and Moisture Barriers Inspection Requirements for the H. B. Robinson Steam Electric Plant, Unit No. 22021-02-11011 February 2021 Presubmittal Meeting with Duke Energy Progress, Llc. to Discuss a Future Relief Request Concerning Containment Metallic Liners and Moisture Barriers Inspection Requirements for the H. B. Robinson Steam Electric Plant, Unit No. 2 ML21041A4822021-02-10010 February 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Proposed License Amendment Request to Adopt TSTF-505 ML21022A2292021-01-22022 January 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Proposed Standby Liquid Control System License Amendment Request ML21011A1472021-01-11011 January 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Inservice Testing of Safety Relief Valves Relief Request ML21007A1942021-01-0707 January 2021 Closed Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Underground Service Water Pipe Coating Relief Valves Relief Request PMNS20201404, Pre-Submittal Meeting for Subsequent License Renewal Application for Oconee Nuclear Station, Units 1, 2, and 3 - Safety2020-12-22022 December 2020 Pre-Submittal Meeting for Subsequent License Renewal Application for Oconee Nuclear Station, Units 1, 2, and 3 - Safety ML20329A3812020-12-0707 December 2020 Regulatory Audit Summary Regarding License Amendment Request to Adopt Risk Informed Completion Times Technical Specification Task Force-505, Rev. 2, Provide Risk-Informed Completion Times (EPID L-2019-LLA-0218 PMNS20201206, Subsequent License Renewal Environmental Pre-Application Meeting2020-10-26026 October 2020 Subsequent License Renewal Environmental Pre-Application Meeting PMNS20201240, Closed Meeting with Duke Energy to Update the U.S. Nuclear Regulatory Commission Staff Security Plan Changes2020-10-22022 October 2020 Closed Meeting with Duke Energy to Update the U.S. Nuclear Regulatory Commission Staff Security Plan Changes 2024-07-23
[Table view] Category:Meeting Briefing Package/Handouts
MONTHYEARML24302A0702024-10-28028 October 2024 Duke Energy Presubmittal Meeting on Adoption of Westinghouse Analysis PAD5/FSLOCA/AXIOM (EPID L-2024-LRM-0121) on October 28, 2024 RA-24-0203, Regulatory Conference Supporting Information2024-07-31031 July 2024 Regulatory Conference Supporting Information ML24143A0612024-05-22022 May 2024 NRC Presentation Slides for Topical Reports to Support SLR (5-22-24 Public Meeting) V2 ML24100A8062024-04-0909 April 2024 Duke Energy Sites Annual Assessment Meeting Presentation Slides April 23, 2024 ML23341A1522023-12-0707 December 2023 December 11, 2023 Public Meeting - RIPE Exemption Request - Licensee Slides ML22336A0382022-12-0808 December 2022 Presentation Slides December 8, 2022, pre-submittal Meeting to Discuss Proposed License Amendment Request Regarding TS 3.7.11, Control Room Area Chilled Water System (Cracws) ML22325A3142022-11-30030 November 2022 November 30, 2022, Pre-Submittal Presentation Slides TSTF-505 and 10 CFR 50.69 (L-2022-LRM-0084) ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22153A3842022-06-0606 June 2022 Duke Energy Presentation Material for June 6, 2022 Public Meeting on GSI-191 Closeout ML22130A0102022-04-28028 April 2022 Duke Presentation for April 28, 2022 Public Meeting - Containment Liner ML22130A0092022-04-28028 April 2022 Duke Presentation for April 28, 2022 Public Meeting - Bolting Integrity ML22091A1332022-04-0101 April 2022 Bru Har Combined 2021 Assessment Meeting Slides ML22067A1992022-03-0303 March 2022 Annual Assessment Meeting Presentation ML22007A2592022-02-0202 February 2022 Presubmittal Licensee Presentation for TS 3.5.3 PIV Testing LAR ML22063A1142022-01-17017 January 2022 Duke Presentation for Public Meeting on February 17, 2022 ML21336A1422021-12-0707 December 2021 December 7, 2021, Pre-submittal Presentation Slides Regarding Embedded Flaw Repair Relief Request - Revised ML21327A2112021-11-23023 November 2021 December 7, 2021, Pre-submittal Presentation Regarding Embedded Flaw Repair Relief Request ML21236A2862021-08-30030 August 2021 License Amendment Request for Revision 1 of DPC-NE-1007-P, Conditional Exemption of the End-of-Cycle (EOC) Moderator Temperature Coefficient (Mtc) Measurement Methodology ML21235A0452021-08-25025 August 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Presentation ML21167A0852021-06-24024 June 2021 Licensee Presentation for Robinson Pre-submittal Meeting TSTF-577 ML21174A3212021-06-24024 June 2021 Licensee Presentation for Robinson Presubmittal Meeting TSTF 577, Rev. 1 ML21105A7522021-04-15015 April 2021 2020 Robinson - EOC Presentation Slides ML21116A2542021-04-15015 April 2021 C2R24 Relief Request Pre-Submittal Slides Call 1 ML21102A0632021-04-14014 April 2021 ONS Slides for Pre-Application Meeting to Discuss Proposed Relief Request Related to Code Case N-853 ML21089A1732021-03-30030 March 2021 EOC Slides Final ML21081A1242021-03-22022 March 2021 EOC Slides Final ML21041A4532021-02-17017 February 2021 Brunswick/Nrc Pre-submittal Meeting: LAR to Adopt TSTF-505, Rev. 2 (Risk-Informed Completion Times) Presentation ML21011A0822021-01-12012 January 2021 Pre-Submittal Meeting January 12, 2021, Revision to VRR-01, Full Stroke Testing of Safety/Relief Valves - Presentation Material ML20300A0902020-10-27027 October 2020 Subsequent License Renewal Environmental Pre-Application Meeting - NRC Presentation ML20300A0872020-10-27027 October 2020 Subsequent License Renewal Application NRC Environmental Pre-Application Meeting - Duke Energy Presentation ML20100G6342020-04-0909 April 2020 Revised- Bru 2019 Annual Assessment Meeting Slides ML20034F2842020-02-0303 February 2020 Implementation of TSTF-564 - NRC Conference Call - February 5, 2020 ML19318F2912019-11-18018 November 2019 Duke Energy Presentation for the Pre-submittal Meeting on November 18, 2019, Regarding the RPV Stud Examination Relief Request ML19302E0512019-11-0606 November 2019 High Energy Line Break License Amendment Public Meeting ML19214A0562019-08-0707 August 2019 Presentation: Duke Energy Presubmittal Meeting - August 7, 2019 ML19207A0172019-07-30030 July 2019 Summary of Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding High Energy Line Break Licensing Basis ML19077A3672019-03-14014 March 2019 March 14, 2019 Pre-submittal Meeting TS DNBR Safety Limit Change LAR Meeting Slides ML18351A1342018-12-20020 December 2018 December 20, 2018 Pre-submittal Meeting Slides for Escw Risk-Informed LAR ML18333A1822018-11-0808 November 2018 Pre-Submittal Meeting - November 8, 2018 - License Amendment Request for Shearon Harris Nuclear Power Plant Emergency Plan Revision ML18255A0142018-09-12012 September 2018 BWROG Presentation Slides for Public Meeting Sept 12 2018 ML18255A0102018-09-12012 September 2018 NRC Slides for Target Rock Public Meeting ML18227B3212018-09-0505 September 2018 Tornado License Amendment Pre-Application Meeting Slides ML18239A3682018-08-27027 August 2018 License Amendment Request Pre-Submittal Conference Call August 29, 2018 ML18157A0322018-06-0606 June 2018 Nw System LAR Presubmittal Meeting ML18144A0632018-05-24024 May 2018 Summary of Meeting Concerning Annual Assessment of H.B. Robinson Steam Electric Plant Unit 2 for Period of January 1, 2017 - December 31, 2017 ML18134A2292018-05-14014 May 2018 Summary of April 26, 2018, Public Teleconference with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment and 3 Regarding Technical Specification 3.8.1 ML18089A0532018-03-30030 March 2018 Summary of Public Meeting with McGuire Nuclear Station ML17331A6272017-11-29029 November 2017 Duke Energy Pre-Submittal Meeting Presentation, Brunswick, Harris, and Robinson License Amendment Requests Regarding 10 CFR 50.69 ML17297B7892017-10-26026 October 2017 Meeting Slide for Partially Closed Pre-submittal Public Meeting with Duke Energy for License Amendment Request to Adopt Areva'S XM-11 Fuel Methodology for Brunswick Steam Electric Plant ML17278A1342017-10-0404 October 2017 Duke Presentation for Public Meeting 09-20-17 2024-07-31
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24302A0702024-10-28028 October 2024 Duke Energy Presubmittal Meeting on Adoption of Westinghouse Analysis PAD5/FSLOCA/AXIOM (EPID L-2024-LRM-0121) on October 28, 2024 RA-24-0203, Regulatory Conference Supporting Information2024-07-31031 July 2024 Regulatory Conference Supporting Information ML24134A0242024-05-22022 May 2024 Duke Presentation Slides Robinson-2 5-22-24 (Trs) ML24136A2482024-05-22022 May 2024 NRC Presentation Slides for Topical Reports to Support SLR (5-22-24 Public Meeting) ML24143A0612024-05-22022 May 2024 NRC Presentation Slides for Topical Reports to Support SLR (5-22-24 Public Meeting) V2 ML24100A8062024-04-0909 April 2024 Duke Energy Sites Annual Assessment Meeting Presentation Slides April 23, 2024 ML24046A1602024-02-16016 February 2024 February 2024 Dseis Public Meeting - In-person Meeting Slides ML24046A1612024-02-16016 February 2024 February 2024 Dseis Public Meeting - Virtual Meeting Slides ML23341A1522023-12-0707 December 2023 December 11, 2023 Public Meeting - RIPE Exemption Request - Licensee Slides ML23114A0672023-04-26026 April 2023 April 26 2023 Public Meeting - RIPE LAR - Licensee Slides ML23087A2972023-04-17017 April 2023 Annual Assessment Meeting Presentation ML23087A2922023-04-12012 April 2023 2022 Annual Assessment Meeting ML22336A0382022-12-0808 December 2022 Presentation Slides December 8, 2022, pre-submittal Meeting to Discuss Proposed License Amendment Request Regarding TS 3.7.11, Control Room Area Chilled Water System (Cracws) ML22325A3142022-11-30030 November 2022 November 30, 2022, Pre-Submittal Presentation Slides TSTF-505 and 10 CFR 50.69 (L-2022-LRM-0084) ML22301A1662022-09-29029 September 2022 Presentation 4 - Recent Biennial PI&R Team Inspection Insights ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22257A2392022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22153A3842022-06-0606 June 2022 Duke Energy Presentation Material for June 6, 2022 Public Meeting on GSI-191 Closeout ML22151A2652022-05-31031 May 2022 Presubmittal Licensee Presentation for 3.3.2 ESFAS Proposed LAR ML22130A0092022-04-28028 April 2022 Duke Presentation for April 28, 2022 Public Meeting - Bolting Integrity ML22130A0102022-04-28028 April 2022 Duke Presentation for April 28, 2022 Public Meeting - Containment Liner ML22109A2122022-04-20020 April 2022 Duke Energy Pre-Submittal Public April 20, 2022, Meeting Presentation ML22091A1332022-04-0101 April 2022 Bru Har Combined 2021 Assessment Meeting Slides ML22083A1072022-03-30030 March 2022 Presubmittal Licensee Presentation for SR 3.8.1.16 Proposed License Amendment Request (EPID L-2022-LRM-0021) (Slides) ML22075A2012022-03-0707 March 2022 Duke 03/07/2022 Presentation - Bolting Integrity ML22067A1992022-03-0303 March 2022 Annual Assessment Meeting Presentation ML22301A1672022-02-0505 February 2022 Presentation 5 - Oconee Trip and Notification of Unusual Event on February 5, 2022 ML22007A2592022-02-0202 February 2022 Presubmittal Licensee Presentation for TS 3.5.3 PIV Testing LAR ML22063A1142022-01-17017 January 2022 Duke Presentation for Public Meeting on February 17, 2022 ML21336A1422021-12-0707 December 2021 December 7, 2021, Pre-submittal Presentation Slides Regarding Embedded Flaw Repair Relief Request - Revised ML21322A3262021-11-29029 November 2021 Duke Energy November 29, 2021 Pre-Submittal Public Meeting Slides for EOF Relocation Licensing Amendment Request ML21327A2112021-11-23023 November 2021 December 7, 2021, Pre-submittal Presentation Regarding Embedded Flaw Repair Relief Request ML21236A2862021-08-30030 August 2021 License Amendment Request for Revision 1 of DPC-NE-1007-P, Conditional Exemption of the End-of-Cycle (EOC) Moderator Temperature Coefficient (Mtc) Measurement Methodology ML21235A0452021-08-25025 August 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Presentation ML21174A3212021-06-24024 June 2021 Licensee Presentation for Robinson Presubmittal Meeting TSTF 577, Rev. 1 ML21167A0852021-06-24024 June 2021 Licensee Presentation for Robinson Pre-submittal Meeting TSTF-577 ML21116A0662021-04-22022 April 2021 C2R24 Relief Request Pre-Submittal Slides Call 2 ML21116A2542021-04-15015 April 2021 C2R24 Relief Request Pre-Submittal Slides Call 1 ML21105A7522021-04-15015 April 2021 2020 Robinson - EOC Presentation Slides ML21102A0632021-04-14014 April 2021 ONS Slides for Pre-Application Meeting to Discuss Proposed Relief Request Related to Code Case N-853 ML21090A1162021-03-31031 March 2021 Combined 2020 Aam Presentation ML21089A1732021-03-30030 March 2021 EOC Slides Final ML21081A1242021-03-22022 March 2021 EOC Slides Final ML21053A0472021-02-25025 February 2021 Duke Energy Pre-Submittal Meeting - February 25, 2021 - H. B. Robinson 3rd Interval Containment ISI Relief Request ML21041A4532021-02-17017 February 2021 Brunswick/Nrc Pre-submittal Meeting: LAR to Adopt TSTF-505, Rev. 2 (Risk-Informed Completion Times) Presentation ML21033A7022021-02-0303 February 2021 Pre-submitting for Planned LAR for Standby Liquid Control Tank Volume Increase ML21034A5552021-01-26026 January 2021 SLRA - NRC Presubmittal Meeting Slides ML21034A5562021-01-26026 January 2021 SLRA - Duke Presubmittal Meeting Slides ML21011A0822021-01-12012 January 2021 Pre-Submittal Meeting January 12, 2021, Revision to VRR-01, Full Stroke Testing of Safety/Relief Valves - Presentation Material ML20300A0902020-10-27027 October 2020 Subsequent License Renewal Environmental Pre-Application Meeting - NRC Presentation 2024-07-31
[Table view] |
Text
2023 ANNUAL ASSESSMENT
CATAWBA MCGUIRE OCONEE BRUNSWICK
Reactor Oversight Process Nuclear Regulatory Commission Region II
HARRIS ROBINSON
If unable to hear audio, dial 301-576-2978, passcode: 250834548#
PURPOSE
Discuss licensee Address findings and Information Meeting with performance in 2023 Performance Indicators a Q&A Session
If unable to hear audio, dial 301-576-2978, passcode: 250834548#
2 AGENDA
- Review Reactor Oversight Process
- Annual Assessment Summary
- Brunswick Steam Electric Plant
- Shearon Harris Nuclear Power Plant
- H.B. Robinson Steam Electric Plant
- NRC available for public questions
If unable to hear audio, dial 301-576-2978, passcode: 250834548#
3
Introductions
Eric Stamm - Branch Chief for Catawba, McGuire, & Oconee
Matthew Fannon - Branch Chief for Brunswick & Harris
Ryan Taylor - Acting Branch Chief for Robinson
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 4 NRC Mission Statement
The NRC licenses and regulates the nation's civilian use of radioactive materials to provide reasonable assurance of adequate protection of public health and safety and to promote the common defense and security and to protect the environment
If unable to hear audio, dial 301-576-2978, passcode: 250834548#5 NRC REACTOR OVERSIGHT PROCESS
1 2 NRC NRC 3
4
Implemented in each Involves inspection and Executed by regional and of the NRCs four assessment activities resident inspectors regions
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 6 Reactor Oversight Framework
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 7 Reactor Oversight Inputs and Oversight
INCREASING SAFET Y SIGNIFICANCE
GREEN WHITE Y E L LOW RED Performance Performance within an Performance outside Related cornerstone Signals a significant Indicators expected level; expected range; objectives are being met; reduction in safety Cornerstone objectives Cornerstone objectives Minimal reduction in the margin in the area are met are still being met safety margin measured Findings Very low safety or security Low to moderate safety Substantial safety or High safety or security significance or security significance security significance significance
Oversight Baseline Inspection Requires additional NRC Requires more NRC Requires most NRC oversight oversight oversight
INCREASING NRC OVERSIGHT
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 8 RESIDENT INSPECTOR PROGRAM
- Resident inspectors live in the communities they serve
- Perform inspections at nuclear power plants
- Provide daily oversight of plant activities
If unable to hear audio, dial 301-576-2978, passcode: 250834548#
9 9 NRC Annual Assessment Summary
CATAWBA NUCLEAR STATION
If unable to hear audio, dial 301-576-2978, passcode: 250834548#10 Catawba Nuclear Station:
Introductions
- Catawba Nuclear Station Resident Inspectors
- David Rivard - Senior Resident Inspector
- Anny Wang - Resident Inspector
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 11 Catawba Nuclear Station:
Annual Assessment Summary
Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment
All findings associated with Catawba Nuclear Station in 2023 were Green 3 - Green non-cited violations
All Performance Indicators were Green
If unable to hear audio, dial 301-576-2978, passcode: 250834548#12 Catawba Nuclear Station:
Annual Assessment Summary
Catawba Units 1 and 2 remained in the Licensee Response Column of the NRCs ROP Action Matrix in all quarters of 2023
NRC plans to conduct routine baseline inspections at the Catawba Nuclear Station for 2023
If unable to hear audio, dial 301-576-2978, passcode: 250834548#13 NRC Annual Assessment Summary
MCGUIRE NUCLEAR STATION
If unable to hear audio, dial 301-576-2978, passcode: 250834548#14 McGuire Nuclear Station:
Introductions
- McGuire Nuclear Station Resident Inspectors
- Frank Young - Resident Inspector
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 15 McGuire Nuclear Station:
Annual Assessment Summary
- Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment
- All findings associated with McGuire Nuclear Station in 2023 were Green
- 4 - Green non-cited violations
- All Performance Indicators were Green
If unable to hear audio, dial 301-576-2978, passcode: 250834548#16 McGuire Nuclear Station:
Annual Assessment Summary
- McGuire Units 1 and 2 remained in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2023
- NRC plans to conduct routine baseline inspections at the McGuire Nuclear Station for 2024
If unable to hear audio, dial 301-576-2978, passcode: 250834548#17 NRC Annual Assessment Summary
OCONEE NUCLEAR STATION
If unable to hear audio, dial 301-576-2978, passcode: 250834548#18 Oconee Nuclear Station:
Introductions
- Oconee Nuclear Station Resident Inspectors
- Nick Smalley - Senior Resident Inspector
- Evan Robinson - Resident Inspector
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 19 Oconee Nuclear Station:
Annual Assessment Summary
- Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment
- All findings associated with Oconee Nuclear Station in 2023 were Green
- 10 - Green non-cited violations
- 1 - Green notice of violation
- 3 - traditional enforcement violations
- All Performance Indicators were Green
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 20 NRC Annual Assessment Summary OCONEE NUCLEAR STATION
- Oconee Units 1, 2, and 3 remained in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2023
- NRC plans to conduct routine baseline inspections at the Oconee Nuclear Station for 2024
If unable to hear audio, dial 301-576-2978, passcode: 250834548#
21 NRC Annual Assessment Summary
BRUNSWICK STEAM ELECTRIC PLANT
If unable to hear audio, dial 301-576-2978, passcode: 250834548#22 Brunswick Steam Electric Plant:
Introductions
- Brunswick Steam Electric Plant Resident Inspectors
- Coleman Curran - Resident Inspector
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 23 Brunswick Steam Electric Plant:
Annual Assessment Summary
- Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment
- All findings associated with Brunswick Steam Electric Plant in 2023 were Green
- 3 - Green non-cited violations
- All Performance Indicators were Green
If unable to hear audio, dial 301-576-2978, passcode: 250834548#24 Brunswick Steam Electric Plant:
Annual Assessment Summary
- Brunswick Steam Electric Plant Units 1 and 2 remained in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2023
- NRC plans to conduct routine baseline inspections at the Brunswick Steam Electric Plant for 2024
If unable to hear audio, dial 301-576-2978, passcode: 250834548#25 NRC Annual Assessment Summary
SHEARON HARRIS NUCLEAR POWER PLANT
If unable to hear audio, dial 301-576-2978, passcode: 250834548#26 Shearon Harris Nuclear Power Plant:
Introductions
- Shearon Harris Nuclear Power Plant Resident Inspectors
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 27 Shearon Harris Nuclear Power Plant:
Annual Assessment Summary
- Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment
- One Greater than Green violation was identified in 2023
- The remaining findings associated with Shearon Harris Nuclear Power Plant in 2023 were Green
- 6 - Green non-cited violations
- All Performance Indicators were Green
If unable to hear audio, dial 301-576-2978, passcode: 250834548#28 Shearon Harris Nuclear Power Plant:
Annual Assessment Summary
- Shearon Harris Nuclear Power Plant Unit 1 transitioned into the Regulatory Response Column of the NRCs ROP Action Matrix due to a Greater-than -green finding identified in the security cornerstone in the 2nd quarter of 2023
- On December 7, 2023, the NRC completed a supplemental inspection in accordance with Inspection Procedure 95001 and determined that completed or planned corrective actions were sufficient to address the performance issue that led to the Greater than Green finding
- NRC plans to conduct routine baseline inspections at the Shearon Harris Nuclear Power Plant for 2024
If unable to hear audio, dial 301-576-2978, passcode: 250834548#29 NRC Annual Assessment Summary
H.B. ROBINSON STEAM ELECTRIC PLANT
If unable to hear audio, dial 301-576-2978, passcode: 250834548#30 H.B. Robinson Steam Electric Plant:
Introductions
- H.B. Robinson Steam Electric Plant Resident Inspectors
- Vanna Gaffney - Resident Inspector
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 31 H.B. Robinson Steam Electric Plant:
Annual Assessment Summary
- Duke Energy operated the plant safely and in a manner that preserved the public health and safety and protected the environment
- All findings associated with H.B. Robinson Steam Electric Plant in 2023 were Green
- 5 - Green non-cited violations
- All Performance Indicators were Green
If unable to hear audio, dial 301-576-2978, passcode: 250834548#32 H.B. Robinson Steam Electric Plant:
Annual Assessment Summary
- H.B. Robinson Steam Electric Plant Unit 2 was in the Licensee Response Column of the NRCs ROP Action Matrix for the entire 2023 assessment period
- NRC plans to conduct routine baseline inspections at the H.B.
Robinson Steam Electric Plant for 2024
If unable to hear audio, dial 301-576-2978, passcode: 250834548#33 CONTACT THE NRC
Web: https://www.nrc.gov
Report an Emergency - 301-816-5100
Safety Concern or Allegations - 1-800- 695-7403 l allegation@nrc.gov
Questions/Information - OPA2.Resource@nrc.gov or 404-997-4417
If unable to hear audio, dial 301-576-2978, passcode: 250834548# 34 CONTACT THE RESIDENT INSPECTORS
Catawba NRC resident inspectors Brunswick NRC resident inspectors (404) 997-5134 (404) 997-5121 (404) 997-5131 (404) 997-5123 McGuire NRC resident inspectors Harris NRC resident inspectors (404) 997-5171 (404) 997-5151 (404) 997-5173 (404) 997-5153 Oconee NRC resident inspectors Robinson NRC resident inspectors (404) 997-5211 (404) 997-5221 (404) 997-5213 (404) 997-5223 (404) 997-5214
If unable to hear audio, dial 301-576-2978, passcode: 250834548#
35 NRC ON SOCIAL MEDIA
Twitter: https://twitter.com/nrcgov Facebook: https://www.facebook.com/nrcgov/
Instagram: https://www.instagram.com/nrcgov/
YouTube: https://www.youtube.com/user/NRCgov Flickr: https://www.flickr.com/photos/nrcgov/sets LinkedIn: https://www.linkedin.com/company/u-s--nuclear -regulatory-commission/
GovDelivery: https://service.govdelivery.com/accounts/USNRC/subscriber/new
If unable to hear audio, dial 301-576-2978, passcode: 250834548#
36 GENERAL QUESTIONS
Questions From Teams: Please raise your hand, and we will call on you For those on the Phone: Press *6 to unmute
If unable to hear audio, dial 301-576-2978, passcode: 250834548#37