ML22130A030

From kanterella
Jump to navigation Jump to search
Summary of Public Meeting on 2021 Annual Assessment Meeting Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324; and Shearon Harris Nuclear Power Plant, Docket No. 50-400, Meeting Number 20220350
ML22130A030
Person / Time
Site: Harris, Brunswick  Duke Energy icon.png
Issue date: 05/09/2022
From: Adam Wilson
NRC/RGN-II
To: Matthew Endress
Division Reactor Projects II
References
20220350
Download: ML22130A030 (3)


Text

May 9, 2022 MEMORANDUM TO:

Matthew F. Endress, Chief Reactor Projects Branch 4 Division of Reactor Projects FROM:

Adam A. Wilson, Senior Project Engineer

/RA/

Reactor Projects Branch 4 Division of Reactor Projects

SUBJECT:

PUBLIC MEETING

SUMMARY

- 2021 ANNUAL ASSESSMENT MEETING REGARDING BRUNSWICK STEAM ELECTRIC PLANT, DOCKET NOS. 50-325 AND 50-324; AND SHEARON HARRIS NUCLEAR POWER PLANT, DOCKET NO. 50-400, MEETING NUMBER 20220350 On April 27, 2022, the Nuclear Regulatory Commission (NRC) conducted a live virtual meeting concerning the Brunswick Steam Electric Plant and Shearon Harris Nuclear Power Plant. The purpose of the meeting was to provide opportunities for the public to discuss the annual assessment for the period of January 1, 2021, through December 31, 2021.

The public meeting was held remotely through the Microsoft Teams application. Additionally, a call-only telephone bridge line was available. The following documents related to the meeting are available in ADAMS: Meeting Notice (ML22094A062), Assessment Meeting Presentation (ML22091A133).

The meeting was conducted from 1:00 PM to 2:00 PM local time. Known attendees consisted of representatives from the NRC, Duke Energy, and general members of the public. Due to the nature of the meeting, no official list of attendees is included. NRC staff were available for questions several times throughout the presentation and again at the conclusion of the presentation. There was minimal interaction with the public which was consistent with the typical annual assessment meetings conducted near the station. One member of the public was interested in Duke Energys emergency evacuation routes assessment, specifically if the assessment has taken into account the rapid population growth of the community surrounding Shearon Harris Nuclear Power Plant. The NRC staff (Senior Resident Inspector) contacted the individual after the meeting to discuss details regarding evacuation time estimates and the status of the latest study.

M. Endress 2

The meeting was listed in the Public Meeting Feedback System under Meeting Code 20220350 and as of the date of this memo, there were no feedback responses to the meeting.

Docket Nos.: 50-325, 50-324, and 50-400 License Nos.: DPR-71, DPR-62, and NPF-63 CONTACT: Adam A. Wilson, RII/DRP/RPB4 404-997-4574

ML22130A030 OFFICE RII/DRP NAME A. Wilson DATE 5/9/2022