Brunswick Annual Assessment Meeting 2019 Reactor Oversight Process Nuclear Regulatory Commission - Region 2 ML20099D128

Agenda Introductions - Brunswick Resident Inspectors and Regional Staff Responsible for Oversight Strategic Plan Goals Annual Assessment Summary Findings Performance Indicators NRC Plans for 2020 NRC COVID-19 Response Questions/Answers

Introductions

Resident Inspectors Galen Smith - Senior Resident Inspector Jeffery Steward - Resident Inspector Regional Personnel Stewart Bailey - Branch Chief Phil Niebaum - Senior Project Engineer Jeffrey Hamman - Senior Project Engineer Donna Jackson - Project Engineer

The NRCs Resident Inspectors

The NRCs Resident Inspectors SJ1 NP1 NRC Strategic Plan Goals Safety Strategic Goal - Ensure the safe use of radioactive materials.

Security Strategic Goal - Ensure the secure use of radioactive materials.

Slide 6 SJ1 Phil, I revised these two bullets to be more in line with the 2018-2022 NRC Strategic Plan.

Steward, Jeffery, 3/12/2020 NP1 Im fine with that, but is a departure from the tmeplate.

Niebaum, Phil, 3/13/2020

NRC Annual Assessment Summary Brunswick Duke Energy/Brunswick operated the plant safely and in a manner that preserved the public health and safety and protected the environment.

Brunswick was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2019.

NRC Inspection Activities Brunswick for 2019 Approx. 6575 hours0.0761 days <br />1.826 hours <br />0.0109 weeks <br />0.0025 months <br /> of inspection and related activities Two resident inspectors on site - residents walk through the plant every day and document an inspection report each quarter 95001 Supplemental Inspection for White PI 3 major team inspections Force-on-Force/Security Inspection Problem Identification & Resolution Design Basis Assurance Inspection

Brunswick PIs and Findings January 1 through December 31, 2019 1 White Performance Indicator - RCS Leakage 10 Green / Severity Level IV inspection findings

NRC Inspection Findings Brunswick Unit 1 Reactor Coolant System Leak Due to Reference Leg Failure Failure to Maintain the Effectiveness of the Emergency Plan Inadequate Procedure Resulted in Inoperable Safety Relief Valves

Significance Threshold Performance Indicators Green Baseline Inspection White Requires additional NRC oversight Yellow Requires more NRC oversight Red Requires most NRC oversight Inspection Findings Green Very low safety or security significance White Low to moderate safety or security significance Yellow Substantial safety or security significance Red High safety or security significance

NRC Inspection Plans for 2020 NRC plans baseline inspections at Brunswick for the remainder of 2020. This includes:

Triennial Fire Protection Inspection Evaluation of Changes, Tests, and Experiments Inspection Emergency Preparedness Exercise

NRC Response to COVID-19 Mission Critical Functions Monitoring plant activities through inspections and oversight.

Maintaining emergency response capabilities with Regional IRCs and HQ.

Risk-informing "eyes on" inspections through residents and regional inspections.

NRC Response to COVID-19 Additional Actions Established a COVID-19 Task Force When on site, residents are social distancing as much as possible Dedicated Continuity of Operations Plan available Coordinating actions with industry on best practices to minimize impacts.

Getting in Touch with the NRC Website - www.nrc.gov Questions/Information -

OPA2.Resource@nrc.gov or 404-997-4417 Allegations 800-695-7403 Employment - 301-415-7400 or www.usajobs.gov

NRC Social Media

  • GovDelivery:

https://service.govdelivery.com/accounts/USNRC/subscriber/new

Questions?

Nuclear Regulatory Commission Region 2 April 29, 2020