ML20235L389

From kanterella
Jump to navigation Jump to search
Insp Repts 50-313/87-14 & 50-368/87-14 on 870504-08 & 0608-12.Violations & Deviations Noted.Major Areas Inspected: Implementation & Compliance to 10CFR50,App R Safe Shutdown Requirements
ML20235L389
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 09/30/1987
From: Hunter D, Murphy M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20235L248 List:
References
50-313-87-14, 50-368-87-14, NUDOCS 8710050449
Download: ML20235L389 (58)


See also: IR 05000313/1987014

Text

- - - - _ _ _ __ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -

,

APPENDIX C

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report: 50-313/87-14 Licenses: DPR-51

50-368/87-14 NPF-6

Dockets: 50-313

50-368

Licensee: Arkansas Power & Light Company (AP&L) i

P. O. Box 551

Little Rock, Arkansas 72203

Facility Name: Arkansas Nuclear One (ANO), Units 1 and 2

Inspection At: AN0 Site, Russellville, Arkansas

Inspection Conducted: May 4-8 an'd June 8-12, 1987

f

'

Inspector: / 9y77

M'. E. Murphy, Projett Iffspector, Project Dlte /

Section B, Reactor Projects Branch j

1

Accompanied

By: D. Kubicki, Office of Nuclear Reactor Regulation

G. Dick, Office of Nuclear Reactor Regulation

R. Lee, Office 01 Nuclear Reactor Regulation l

M. Villaran, Brookhaven National Laboratory t

K. Parkinson, Brookhaven National Laborstory I

Approved: [ w et

D. R. Hunter, Chief, Project Section B Date {

Reactor Projects Branch

I

Inspection Summary i

Inspection Conducted May 4-8, 1987 (Report 50-313/87-14)

Areas Inspected: Nonroutine, announced inspection for implementation of and

compliance to the safe shutdown requirements of 10 CFR 50, Appendix R.

Results: Within the areas inspected, one violation was identified (failure to

properly protect structural steel which supports or is framed into fire

barriers, paragraph 3). Two deviations were identified (failure of fire alarm

8710050449 870930 ,

PDR ADOCK 05000313

G PDR

_ _ _ _ _ _ _

______________________;

1

2

fire barriers in accordance with BTP-APCSB 9.5-1, Appendix A, . paragraph 3).

Three unresolved items are identified in paragraphs 3, 8.-a(5), and 10.b(1).

Inspection Conducted June 8-12, 1987 (Report 50-368/87-14)

Areas Inspected: Nonroutine, announced inspection for implementation of and. j

compliance to the safe shutdown requirements of.10 CFR 50, Appendix R. I

Results: Within the areas inspected, one violation was identified (failure to

properly protect structural steel which supports or is framed into fire

barriers, paragraph 3). Two deviations were identified (failure of fire alarm i

system to comply with NFPA Standard No. 720, 1975; and, failure to maintain 1

l fire barriers in accordance with BTP-APCSB 9.5-1, Appendix A, paragraph 3). l

Three unresolved items are identified in paragraphs 3, 8.a(5), and 10.b(1).-

.

I

l

l

l

l

_ _ _ = _ _ - _ - _ _ - - .

,. . . . . . . . . . . . . . .. . . . . . . . . ..

. . . . .. .. _ . . . . . . .. . . . . . . . . . . . . . . . . . . - - . . . . . .

.

. . - . . . . . . .. - - - . - . . . .

1

)

I

l

3 l

q

!

!

DETAILS ]

' i

i

i

1. Persons Contacted I

l

AP&L

  • E. C. Ewing, General Manager, Plant Support l
  • M. M. Coombs, Corporate Fire Protection Specialist  !
  • D. D. Snellings, Manager, Nuclear Programs. 1
  • D. Williams, Senior Engineer J

l *D. Lomax, Team Leader, Appendix R Audit (Plant Licensing' Supervisor)-

  • 0. Howard, Team Leader, Appendix R' Audit (Manager, Special Projects)

D. H. Smith, Senior Engineering Technician )

H. Rideout, Engineer {

  • J. G.'Dobbs, LR. Electrical Engineering Supervisor  ;
  • M. C. Moser, Engineer ;j

W. E.' Rogers, LR Mechanical Engineering Supervisor

M. Huff, LR Mechanical Engineering Supervisor

i

!

M. R. Cumbest, Supervisor, Fire Protection (MSU SSI, New Orleans)

  • M. C. Snow, Licensing Engineer

i

  • P. Michalk, Plant Licensing Engineer  ;

G. D'Aunoy, Unit 2, Operations i

^S. McGregor, Engineering Services Supervisor  !

B. L. Bata, Quality Assurance (QA) Engineer

  • D. R. Brown, Nuclear Quality
  • G. Higgs, Plant Engineering

B. E. Williams, Plant Engineering

"G. Storey, Engineering Services  !

  • R. Rispoli, ANO Fire Protection Specialist

K. Dickerson, Plant Engineer

E. Force, Training

R. Shinkowski, Shift Supervisor

S. Feemster, Senior Radiation Officer

l D. Olsen, Radiation Officer

l B. Flake, Radiation Officer

S. Szabo, Shift Administrative Assistant

  • C, Zimmerman, U-1 Operations Technical' Support Supervisor

B. L. Garrison, U-1 Operations Technical Support

R. Ashcraft, Electrical Maintenance Supervisor

  • J. Johnson, Engineering Technical, Fire Protection

R. Oakley, I&C Engineering Supervisor

  • P. Pittman, Electrical Engineer
  • D Williams, Engineer-I

W. Cottingham, I&C Engineer

P. Crossland, Training

B. McBride, Shift Supervisor

L. McLerran, Control Room Supervisor

R. Pierce, Radiation Officer

l

l

L _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ - __

4

R. Carter,' Radiation Officer

N. Yockey, Shift Administrative' Assistant

  • C. W. Taylor, U-2 Operations Technical Support Supervisor
  • T. Robinson, Fire Protection Specialist
  • D. Provencher, QA Supervisor.
  • J. Taylor-Brown, Quality Control (QC). Superintendent
  • R. Lane, Manager,. Engineering
  • B. Hinton, Operations Technician Engineer ,  !

'*S. M. Quennoz, General Manager, Plant Operations

G. W. Woerner, Mechanical Engineer-

J. Lamb, Fire Prevention and Safety Coordinator

J. Waid, Technical Support Training Supervisor

R. Hargrove, General Employee Trainer

i

IMPELL

l

t

  • E. J. Shelton, Nuclear Programs

Bechtel

i

T. Gilmartin, Electrical Field Engineer l

0. Barnhouse, Electrical Field Engineer  ;

i

  • Denotes those attending the exit interview conducted on June 12, 1987.

The team members also interviewed other AP&L personnel during the

inspection. '

2. List of Documents Reviewed

i

See attachment to this appendix.

3. Fire Protection / Prevention Program Units 1 and 2

This inspection was conducted to determine that the licensee had

established and was implementing a program for fire protection and

prevention in conformance with regulatory requirements and industry guides

and standards.

The NRC inspectors reviewed the documentation constituting the licensee's

approved fire protection program. These documents are referenced in

paragraph 2 of this report. The licensee's program provides for.the

control of combustible materials and housekeeping for reduction of fire

hazards. Administrative controls have been established to handle disarmed

or inoperable fire detection or' suppression systems; provide for

maintenance and surveillance on fire suppression, detection, and

emergency communications equipment; establish personnel fire fighting

qualifications, training, and fire protection staff responsibilities;

provide fire emergency personnel designations as well as plans and

actions; and establish controls for welding, cutting, grinding, and other

l

ignition sources.

_ _ _ _ .

a <

3

5' i

'The NRC inspectors conducted a walkdown of the fire suppression water. j

system and verified that it was operable as: required by Technical j

Specifications.

' '

1

1

A tour of' accessible areas of the' plant was conducted to assess general, 1

area condition, work activities.in progress, and visual condition of fire a

protection systems and equipment. Combustible materials and flammable and  ;

combustible liquid and gas usage.were restricted or properly controlled in j

areas containing safety-related equipment and components. Items checked;

included positions of selected valves,' fire barrier condition,-' hose i

stations, hose' houses, halon' system lineups,-fire lockers, and fire- "'

extinguishers for type, . location, and condition. 'i

There was'no welding, cutting, or use of-open flame ignition.. sources foun'da

in the areas toured.- There were no construction act_ivities'in progress in .

'

.the toured areas. There was'some maintenance work and surveillance

testing noted. General housekeeping conditions were found,to be' goo'd.

-]

Fire protection systems and equipment installed for protection of .

safety-related. areas'were found'to be functional and. tested in accordance l

with the requirements specified in the Technical Specifications- Fire

.

brigade equipment, including. emergency breathing. apparatus,.was found to j

be properly stored and maintained. '

The NRC inspectors'also reviewed fire brigade training and drill records.

The records were iniorder and confirmed that training and drills were .I

being conducted at the specified intervals.- Individual qualifications and  :(

training were found to meet BTP-APCSB19.5-1 requirements. A review of:the'

current roster of_ qualified fire brigade members verified that brigade

composition is'in accordance'with Technical Specification requirements.

.. s

By letter dated August 15, 1984, the-licensee requested approval of a. i

number.of exemptions from'Section III.G of Appendix'R to the: extent that.

it requires protection for structural steel which is . framed. into or

supports a fire' barrier. During the Unit.1 inspection,.the NRC inspectors  :

discovered unprotected steel in an area'not encompassed by the exemption

request. The licensee provided a copy of a fire hazards' analysis for this ,

area. .It was considered inadequate by the staff because it did not:

~

I

consider the potential'for areas of concentrated combustibles which could

produce localized heating sufficient to cause the steel to fail. During

the Unit 2 inspection, the audit team.also discovered additional areas l

containing unprotected steel ~not encompassed by the licensee's August 15,

1984, exemption request. The' licensee produced a revised fire hazards

analysis which was conducted by'a consultant. . (The. methodology utilized

in this-analysis was one'that had previously been accepted by the staff.)

The results of this analysis-indicate that a localized heating problem

exists in Room 111 in Unit 1 and Rooms 2055 and 2084 in. Unit 2. The

licensee is studying options-to mitigate.this problem but'no actual'

modifications have been completed. .Because the steel in these areas is.

supporting a fire barrier and is l unprotected from the ' effects of a fire, o

and because no exemption for this condition is either pending or approved,:

l

!

4 !

]

6

this represents a potential violation of.Section III.G of Appendix R.

(313/8714-01; 368/8714-01) ,

During the licensee's review of the AND Fire Protection Program against

the guidelines of Appendix A to BTP-APCSB 9.5-1, the plant was divided ,

into distinct fire areas and significant fire hazards were isolated by  !

fire-rated walls and floor / ceiling assemblies. These fire barriers were

to be.surveilled under the provisions of the plant Technical

Specifications. The NRC inspectors discovered that certain fire barriers,  !

such as portions of the wall and floor / ceiling surrounding the control J

room were not being surveilled per the Technical Specifications. This j

represents a potential deviation from the licensee's commitment to )

establish and maintain these fire barriers. (313/8714-02; 368/8714-02)

During the review of the ANO Fire Protection Program against the  ;

guidelines of Appendix A to BTP-APCSB 9.5-1, the licensee committed to I

design and install a fire alarm system in accordance with the provisions i

of National Fire Protection Association Standard No. 720, 1975. I

Paragraph 2464 of the standard stipulates, "An audible trouble signal at a i

central supervising station may be common to several signaling line l

circuits. The act of silencing it upon operation in connection with one '

signaling line circuit shall not prevent it from operating immediately

upon the occurrence of trouble on other signaling line circuits."

,

The fire alarm system at AN0-1 and -2 is not designed to annunciate

subsequent trouble alarms after an initial alarm is silenced. This

condition represents a potential deviation from the licensee's commitment ,

_

to conform with NFPA 72.0. (313/8714-03; 368/8714-03)

During the BTP-APCSB 9.5-1, Appendix A review, the licensee submitted to

the staff, for evaluation, a number of fire barrier penetration seal

designs. The staff accepted these asigns as documented in the fire

protection safety evaluations for ANO-1 and -2. Subsequently, the

licensee submitted additional seal designs for staff review. NRR action i

on this issue is pending. During the inspection, the licensee notified

the NRC inspectors that qualification fire tests on three additional seal

designs (not previously reviewed by the staff or pending with NRR) were i

unavailable. The licensee has committed to submit these seal designs to a

standard fire test. Pending transmittal of the test results.and

evaluation by NRR, the adequacy of these seal' designs is considered an

unresolved item. (313/8714-04; 368/8714-04)  :

1

4. Emergency Lighting System, Units 1 and 2

4

The NRC inspectors examined the emergency lighting system required for

( safe shutdown. Section J of Appendix R requires that emergency lighting

I

units with at least an 8-hour battery power supply be provided in all

areas needed for operation of safe shutdown equipment and in access and

egress routes thereto'. The licensee has installed all cf the emergency

lighting units required for the operation of safe shutdown equipment in

L_____._.___________________________.____ _ _ _ _ _ . _ _ _

i

7

the event of a fire that destroys and forces evacuation of the control

room.

During the alternate shutdown procedure walkdown for both units, the team

members observed adequate lighting at work stations and in access. routes

to the components and controllers.

5. Post-Fire Safe Shutdown Capability (Unit 1)

a. Systems Required for Safe Shutdown

The systems are grouped according to the performance goals for PWR

safe shutdown functions to achieve both hot standby and cold

shutdown.

(1) Reactivity Control

Initial reactivity control is provided by operator initiation of

a reactor manual trip from the control room upon notification of

a major fire requiring plant shutdown. The control rods will be

inserted into the reactor core thereby bringing it subcritical.

The reactor may also be tripped from outside the control room by

local trip of the control rod drive system feeder breakers.

Additional boration will be provided during cooldown by j

intermittent operation of-the makeup /high pressure  ;

injection (HPI) pumps taking suction from the borated water  ;

storage tank (BWST). The BWST has a minimum volume'of 362,000 i  !

13,000 gallons of 2470 1 200 ppm boron concentration water per  ;

the ANO-1 Technical Specifications. With. letdown paths ,

isolated, the licensee has determined that supplying borated l

makeup water from the BWST to offset RCS inventory shrinkage

during cooldown will provide sufficient boration to assure

better than a 1 percent shutdown margin during the cooldown and

subsequent Xenon decay.

(2) Reactor Coolant Makeup (Level and. Pressure Control)

For a post-fire safe shutdown, reactor coolant system (RCS)

inventory will be controlled by isolating all . reactor coolant

leakage paths and verifying isolation of these paths. Potential ,

loss pathways include' normal letdown, reactor coolant pump (RCP)

seal bleedoff, RCS high point vents, pressurizer power operated

relief valves, RCS sample valves, and decay heat suction valves.

The reactor coolant pumps will be secured for the duration of

the incident to avaid seal failure which might occur while

attempting to restart the pumps.in an' emergency situation.

The only maLeup thus required will be to offset inventory

shrinkage resulting during the cooldown. Steam generator

overcooling pathways will be controlled to regulate RCS

_ _ _ _ _ _ _ _ -

. . . .. .. .. . . . .. .. .. . .. . .. .. . .. .

.. ..

.

l

8

i

inventory shrinkage by controlling emergency feedwater (EFW)

flow, closing the main steam isolation valves and turbine. bypass  !

valves, tripping and verifying tripped the main turbine, and

'

controlling the atmospheric dump valves.

Isolation of the direct RCS leakage paths and control of the  ;

steam generator overcooling pathways as described above will l

delay the need for makeup for about 1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> following a

post-fire reactor trip.. Borated inventory makeup will then be j

provided as required via the makeup /HPI pumps taking suction I

from the BWST and discharging through the HPI valves as i

described in Section (1) above. The makeup /HPI pumps will be i

started and stopped to maintain inventory (as monitored by j

temperature-compensated pressurizer level) and control RCS ]

pressure. j

l RCS pressure may be more' easily controlled by operation of the

vital' bus powered pressurizer heaters if they are available.

However, the pressurizer heaters 'are.not mandatory for achieving i

and maintaining safe shutdown.

(3) Decay Heat Removal I

Decay heat will be removed from the reactor following a reactor

scram via the steam generators by natural circulation cooldown.

Emergency feedwater is supplied to the steam generators by the

emergency feedwater system to provide makeup for the inventory

discharged as steam from the safety relief valves and the

atmospheric dump valves.

I

The emergency feedwater system consists of one motor-driven

pump (P7B) and one turbine-driven pump (P7A) interconnected to

permit supply of emergency feedwater to either one or both of

the steam generators from either or both of the pumps. The

'

motor-driven pump and its associated components are powered from

the red train, AC engineered safeguards buses. The

turbine-driven pump is powered by steam from the steam

generators and its associated components and controls are

supplied by the green train, battery backed DC buses.

The EFW condensate storage tank (T418) will serve as the normal

water source for the emergency feedwater system. The EFW CST

has a Technical Specification minimum capacity of

107,000 gallons which equates to about a 4 -hour supply for

natural circulation cooldown. The backup source of feedwater is

the service water system. The CST T41 may also be aligned to

the EFW system suction header.

The EFW system automatic operating logic is provided by the

emergency feedwater initiation and control system (EFIC). The

system will auto initiate upon loss of main feedwater, low steam

L______________--.-_ _ _ _ _ _

___ . _ _ _ _ _ . - .-

9

generator level or pressure, loss of all RCPs, or ECCS

actuation.

Steam release from the! steam generators will be controlled by

the atmospheric dump valves and/or the mechanical safety. relief

valves. Controlled operation of the atmospheric dump valves

will be utilized to achieve the desired RCS cooldown rate. '

(4) Process Monitoring

The following process monitoring instrumentation is available in

the control room and on~the safety parameter display

system (SPDS) " Alternate Shutdown" display:

Source Range Flux

Reactor Coolant System Pressure  ;

Reactor Coolant System Hot Leg Temperature j

Reactor Coolant System Cold Leg Temperature i

Steam Generator Level J

Steam Generator Pressure

Pressurizer Level

CST 141B Level  !

'

The SPDS at' ANO is a computer-based system used for monitoring

and display of plant safety parameters developed in accordance

with the requirements of NUREG-0737. The SPDS configuration at

ANO is designed to provide redundant. isolated data acquisition,

processing, and display devices. Two redundant display .

j

terminals are available in the control room and also-in the TSC  ;

for alternate shutdown. Software has been developed to display '

the above parameters as well as provide trending data on an

" Alternate Shutdown" display screen.

In addition, the following local indicators are available:

P7A EFW Pump Discharge Pressure

Decay Heat Pump Discharge Pressure

Decay Heat Pump Suction Temperature

Steam Generator Pressure (at the ADV area) ,

(5) Support Systems

The safe shutdown components and systems described in

Sections (1) through (4) require the operation of several-

critical support systems in order to properly perform.their safe

shutdown function. .The following systems must have one train

operating to support the safe shutdown.

Service Water System

Emergency Diesel Generators

l

- _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - - _

_

,

!

'!

10

Diesel Fuel 011 Transfer System l

!

Emergency (Engineered. Safeguards) AC Power Distribution

System

Uninterruptible DC Power Distribution System  !

I

HVAC for all Essential Areas j

i

Emergency Lighting )

Radio Communication System

SPDS j

l

(6) Cold Shutdown  !

The reactor coolant system temperature and pressure will be )

reduced by natural circulation cooldown using the atmospheric i

dump valves and the emergency feedwater system as described in l

the previous sections. 'Once the reactor coolant system _

1

temperature has been lowered to less than 280 F, the RCS'will be

depressurized to e. approximately 225 psig, and the decay heat

removal (OHR) system.will be initiated. The DHR. system will be

used to reduce RCS temperature to 200 F and maintain cold

shutdown. Some minor repairs at motor control center breaker

cubicles in the form of lifted leads and jumpers for control

circuits and control power fuse replacements may be required.

It should be noted that the licensee was granted an exemption

for ANO-1 from the requirement that the plant be capable of j

achieving cold shutdown within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> without the use of '

offsite power. Without offsite power, the RCPs cannot_be -l

operated; therefore, pressurizer auxiliary spray:is unavailable. '

A very conservative controlled cooldown to DHR' system cut-in

conditions without void formation in the reactor vessel would

take at least 135 hours0.00156 days <br />0.0375 hours <br />2.232143e-4 weeks <br />5.13675e-5 months <br /> per licensee's analysis-with

approximately another 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> to reach cold shutdown.- For the

purposes of this audit, the reference documents pertaining to

this exemption were reviewed for baseline information only,

b. Alternate Shutdown

In_the event of a fire in the main control room (Fire Area G,

Zone 129-F) and/or the cable spreading room (Fire Area G, Zone 97-R)

which results in a functional loss of control room instrumentation

and controls, or requiring evacuation of the control room, the

licensee has provided alternate shutdown capability. The

Procedure 1203.02, " Alternate Shutdown," will implement the safe

shutdown from outside the control room.

_ _ _ _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ .

r

l

,

11

, Initial reactivity control will be provided by manually scramming the

'

reactor just prior to evacuating the control room. The shift

supervisor will direct the remainder of the shutdown from the

Technical Support Center (3rd floor of the administration' building)

using portable radios to communicate with shift personnel deployed

throughout the plant. Monitoring of plant parameters is provided on

either of the two redundant safety parameter display system terminals

in the technical support center (TSC).

l' It should be noted that AN0-1 and -2 share what.is essentially a

common control room, separated by only a glass wall. Both unit-

control rooms share a common ventilation and air conditioning system.

For this reason, a significant Unit 1 control room fire requiring

evacuation would in all likelihood require a Unit 2 control room

evacuation and shutdown of Unit 2 in accordance with

Procedure 2203.30, " Remote Shutdown." See Section 6.b for further

-discussion.

The alternate shutdown procedure directs reactor coolant system level

and pressure control by locally verifying and manually isolating as

required the RCS letdown pathways and steam generator overcooling

pathways. Operators then verify the makeup /fiPI injection pathway and

locally operate the pumps from the switchgear breakers under

direction of the shift supervisor.

RCS pressure may be more easily controlled by local manual operation

of the vital bus powered pressurizer heaters from the motor control

center breakers under supervision of the shift supervisor, if control

circuits have not been faulted by control room / cable spreading room

fire failing the SCR gating circuits. The pressurizer heaters are

not mandatory, however, for achieving and maintaining safe shutdown.

Decay heat removal by natural circulation is. established by first

verifying the operation of the turbine driven EFW Pump P7A. Steam

supply to the turbine and flow path from CST T41B.to the steam

l generators will be verified, and the turbine manually started if it

did not auto start or had tripped. The EFW flow will be locally

'

l controlled manually by throttling the P7A trip / throttle valve as

.

'

directed by the shift supervisor to achieve a stable natural

circulation cooldown. As time and additional manpower permit, the

motor-driven EWF Pump P7B flow path will be verified. When AC power

is restored P7B may provide feedwater to the steam generators in

preference to P7A to eliminate the need for P7A trip / throttle

adjustment.

Steam release from the steam generators will initially be provided by

the mechanical safety relief valves. As additional manpower becomes

available, the atmospheric dump valves will be manually operated

i under the direction of the shift supervisor. If being operated

l

'

locally (manual operation of the air-operated valves), the operator

will be told to reduce steam header. pressure as required to achieve

L

_ - - _ _ _-

i

12

the desired cooldown rate. If the isolation valve control circuit is. .

'

undamaged, the isolation valves may be electrically operated at the

MCCs to control RCS cooldown rate.

6. Procedures (Unit 1)

i

'

The procedures reviewed during this inspection include a post-control room

fire alternate shutdown procedure, a remote shutdown procedure, Technical-

Specification surveillance procedures, fire alarm corrective action

procedures, and plant operating procedures. A sampling of fire preplans

from the fire protection program manual was also reviewed.

)

a. Alternate Shutdown Procedure 1203.02

In the event of a fire in the main' control room and/or the cable  !

spreading room which results in evacuation of the ANO-1 control room, I

l the licensee may shut the reactor down from outside the control room {

in accordance with the Procedure 1203.02, " Alternate Shutdown."

The minimum operating shift complement for Unit I consists of the

following personnel:

Title Control Room Evacuation Assignment

Shift Supervisor 3rd Floor TSC

Shift Admin. Asst. 3rd Floor TSC & plant library

Shift SR0 switchgear, EDG, battery rooms  !

Reactor Operator No.1 Various locations in auxiliary / turbine I

buildings per procedure & shift supervisor's

direction

Reactor Operator No. 2 Upper north / lower south piping penetration

rooms, EFW pump room, various locations per

shift supervisor's direction

i

Waste Control Operator Fire brigade leader, affected unit

Auxiliary Operator Fire brigade member

The first five people above are required to implement the control

room evacuation procedure. The shift supervisor is in charge of the

-

normal operating shift and he continues in that role upon entry into

the procedure. He also serves as emergency director of the emergency

response organization until-the TSC is formally activated. The waste

control operator and auxiliary operator together with other onshift-

personnel will staff the fire brigade. Available additional operators

will be utilized to support the required operators.

L__- _-_ __

g

-

m

-l

13

Once the decision to' evacuate the' control room has'been made, th'e.

reactor will be tripped from the control room driving the control 1

rods in for. initial reactivity control. Severa1 'other immediate

- actions will:be attempted from the main control' room pr.ior to-

evacuation. If unsuccessful, however, all are covered procedurally

!

from outside the control room soon after the evacuation. The

operating shift personnel then proceed to their post-evacuation

assignments as outlined above, to implement their assigned procedure .j

sections, attachments, and checklists. The remainder of the

L alternate safe shutdown will be directed and-monitored by the' shift l ,

supervisor from the TSC, 3rd floor of the administration building -

b. Procedure Walkdown

The alternate shutdown procedure (1203.02, Revision 4)walkdownwas

initiated at 9:23 a.m. (CDT) on May 7, 1987, using five people from

the licensee's operating staff with the proper training and

qualifications to fill the. control room operating shift positions.

Since the procedure is symptom oriented, the following initial .

conditions were presented:

)

Fire in control room of sufficient size to require-

evacuation

Coincident loss of offsite power 4

Botn EFW pumps fail to auto start

Both standby diesel generators failed to auto start  !

All system line-ups as normally found at full power

Two NRC inspectors accompanied the shift supervisor and the shift

administrative astistant to the 3rd floor TSC. They remained there

to observe personnel actions, crew direction and leadership, i

communications, use of the SPDS, interface with and initiation of j

emergency plan implementation procedure, and training and familiarity  ;

with the alternate shutdown procedure. Reactor. Operator Nos.1 and 2-

'

were not accompanied by NRC inspectors during .the walkdown,'so their

actions were' monitored from the TSC as they made their' call-ins to

the shift supervisor.. A third NRC inspector accompanied'the shift

SR0 to observe his actions.at the electrical equipment rooms and

EDGs, observe lighting 'at~ work ' stations and access routes, evaluate

l- communications, and evaluate training and familiarity with the )

procedure. -

The procedure was halted during Step 13, Item No.1, of Shift

Supervisor Section.1A which demonstrated that a stable hot shutdown

could be achieved and a controlled rate of cooldown was to be  ;

commenced. Emergency feedwater flow to.the steam generators via the  !

turbine-driven EFW Pump P7A was established and verified within -

l

__ _

_j

l

14

12 minutes. Both EDGs K4A and K4B were manually started and loaded

within 20 minutes of start of event. The operating staff

demonstrated adequate training and familiarity with the procedure '

.

throughout the walkdown.

The only procedure deficiency identified was the lack of a. clear i

procedural interface between the Unit I and 2 control rooms for the i

situation where a control room fire requires evacuation of one unit's  ;

control room. The.two control rooms share a single ventilation and i

, air conditioning system and are only physically separated by a glass

I

wall. There should be a procedure to provide positive direct a

notification of the other unit's shift supervisor when a control room

fire evacuation in one unit is imminent. The second unit's control

room response to such a notification should also be established by

l procedure.

Other improvements to the alternate shutdown procedure would be:

Provide a procedure step to perform a radio check at the time

that portable radios are picked up by operations personnel at

the alternate shutdown equipment cabinet. This assures that

working communication will exist during the first critical

minutes of the procedure implementation.

Establish a periodic program to check contents of the alternate

shutdown equipment cabinet and file cabinet. This will assure

that all procedures, tools and equipment used to implement the

procedure will be there if they should ever be needed,

c. Fire Alarm Corrective Action Procedures and Fire Preplans

Procedure 1203.12K, " Annunciation K12 Corrective Action," and l

Procedure 1203.09, " Fire Protection System Corrective Action," were l

reviewed to evaluate the train of responses followed by the control

room operator upon receipt of a fire annunciation alarm. The

procedures were found to adequately direct the operators to identify

the origin of an alarm, verify its validity, and respond accordingly.

The fire preplans were readily available in the control room to guide j

the operators in their response.  ;

l

d. Technical Specification Surveillance Procedures

Surveillance test procedures covering a sampling of Technical

Specification surveillance requirements for various post-fire safe

shutdown components and systems were reviewed. These included .

procedures for the Makeup /High Pressure Injection Pumps P36A and l

P36B, the motor-driven Feedwater Pump P7B, and the turbine-driven

auxiliary Feedwater Pump P7A. The past two periodic performances of

Procedures 1104.02, Revision 22, " Makeup and Purification System

Operation," (a quarterly Technical Specification surveillance), and

Procedure 1106.06, Revision 31, " Emergency Feedwater Pump Operation," ,

l

_

. . _ . .. . . . . . . . . . . _ _ . . . . .. . . _ . .

. .

.. .

.. ... .

..

I

15

' Supplement I for P7B and Supplement II for P7A (monthly Technical'

Specification surveillance) were retrieved for inspection of test

results. This review showed the procedures to be adequate and the

performances reviewed were performed on time and documented

adequately.

e. Operator Training on Safe Shutdown Procedures

]

i

In addition to observing the operator's performance during the

'

walkdown of the alternate shutdown procedure, operations technical

support and operator training personnel were interviewed concerning

operator training on Appendix R post-fire safe shutdown procedures  !

and equipment. The training covered Appendix R equipment, Alternate I

Shutdown Procedure 1203.02, and the fire protection program manual,

and fire preplans. The program includes classroom instruction, ,

walkdowns, simulation, and hands-on operating experience. A 2 ycar

requalification cycle is being maintained.

.)

Lesson plans related to Appendix R training were provided for J

inspection. Training records for operating shift personnel were also

'

reviewed. These areas' reviewed were found to be adequate.

,

The licensee is presently revising the Appendix-R rehted training to j

enhance the fire preplan instruction and to integrate plant simulator J

exercises into the safe shutdown / alternate shutdown portions of the

course. These improvements are scheduled to be incorporated by late

1987.

l

7. Protection for Associated Circuits (Unit 1)

Common Bus Concern

Spurious Signals Concern

Common Enclosure Concern

a. Common Bus Concern

, The common bus associated circuit concern is found in circuits,

i either nonsafety-related or safety-related, where there is a common

power source with shutdown equipment and the power source is not

electrically protected from the circuit of concern.

The common bus concern is made up of two items:

Circuit Coordination

High Impedance Fault Analysis

(1) Circuit Coordination

Breaker Coordination is audited by reviewing the time current

curves developed during the licensee's bus coordination study.

l

l

__________o_ _ _ _ - _ _ -

- _ _ _ ._ _ - -

!

=16

I

l

At ANO-1, the following circuits were randomly selected for

review:

Circuit Comment

! 4160 V DG1 Coordination Satisfactory

l

4160 V-BUS A3 Coordination Satisfactory

4160 V DG2 Coordination Satisfactory

l

4160 V BUS A4 Coordination Satisfactory 1

480 V LC B5 Coordination Satisfactory

480 V LC B6 Coordination Satisfactory

480 V MCC B52 Coordination Satisfactory

480 V MCC B62- Coordination Satisfactory

125 VDC PNL 001 Coordination. Satisfactory

125 VDC PNL 002 Coordination Satisfactory

'

125 VDC PNL D11 Coordination Satisfactory l

125 VDC PNL D21 Coordination Satisfactory l

120 VAC PNL RS1 Coordination Satisfactory.

120 VAC PNL RS2 Coordination Satisfactory .I

PNL C539 Coordination Satisfactory

BNL C540 Coordination Satisfactory

The licensee's coordination program was found to be i

satisfactory. )

1

To ensure that the existing satisfactory circuit coordination is

not compromised by future design changes, the licensee has an

established procedure for modification design review,

Procedure 216, Revision-1, dated April 30, 1987, " Guidelines for

Evaluation of Safe Shutdown Capability and Control of Safe

Shutdown Capability Assessment," which provides for reviewing

modification design for Appendix R concerns.

The licensee performs relay testing and maintenance at 18-month

intervals (each refueling outage). Circuit breakers are. tested

and maintained at intervals of up to 60 months. Breaker-and

relay maintenance and testing are currently scheduled manually. 2

The licensee is in the process of converting to an automated  !

maintenance scheduling system.

Maintenance records for the following randomly selected circuit

breakers or protective relays were reviewed to verify that

maintenance and testing are being performed at the specified

frequency:

Maintenance Required Comp

Component Title Procedure Frequency Date

BKR A-409 A-4 bus Feeder 1307.07 Refueling 11/12/82

10/29/84

10/02/86

L__ ___---_1---_------

- _

l

!

17

l

BKR B-633 Reector Bldg. 1403.81^ 234 Weeks 01/23/83

Cooling Fan 11/26/84

BKR B-723 Reactor 1403.82 234 Weeks 12/15/84

Pressurizer 11/20/86

Heatera

BKR B-512 B-5 Mair, 1403.83 306 Weeks' 12/19/82'

Breaker  ;

I

WA302/A- Service Water 1403.150 Refueling' 12/03/84 -l

150/151/M Pump P4A "A" 12/10/86

Phase Relay

I i

E11/A-187 DG1 "A" Phase 1403.151 Refueling 10/26/84 i

DG1 Differential 11/12/86 l

Relay a

The reviewed records documeated compliance with established , ,

maintenance procedures.

'

'j

Control of fuse replacement is required to ensure maintenance of

coordination for circuits protacted by fuses. The licensee's  ;

controls for fuse replacement include the following: '

I *

Procedure 1403.85, " Motor Control Center Preventive

Maintenance"

.)

Plant Drawings / Prints -

Technical. Manuals , j

,

1

.

1

Job Orders

l {

Material Controls. I

The licensee's fuse replacement control, were found to~be i

satisfactory. )

(2) High Impedance Fault Analys_is ,

The high impedance fault concern is found in the case where

multiple high impedance faults exist as loads -on a safe shutdown-

power supply and cause the loss of the safe shutdown power

supply prior to clearing the high impedance faults.

The licensee's analysis for high impedance faults, EE-87-014,

January 21, 1987, ANO-1 and -2, " Position on Multiple High

Impedance Faults," determined that protection for simultaneous

high impedance faults was provided by the following:

l

l

L___________

l

l

18

4.16 KV safety buses are equipped with ground fault relays.

'

The 4.16 KV and 480 V distribution systems are grounded.

High impedance faults would rapidly propagate into low

impedance faults and cause coordinated circuit breaker

tripping.

In the event that a required electrical bus.is lost due to

high impedance faults,.the licensee's procedures provide

for manually tripping all breakers on the faulted bus and-

reenergizing required safe shutdown loads.

w ., i

The' licensee's analysis and protection for high impedance faults l

were :found to be satisfactory. j

The licensee's protection for the' associated circuit coinmon bus

concern was found to be satisfactory.  ;

b. Spurious Signals

i

The spurious signal concern is made up of two items:

i

The false motor, cor trol, and instrument readings such as  !

,

occurred at the 197S Brown's Ferry fire. These could be caused

l by fire-initiated grounds, short or open circuits.

Spurious operation of safety related or nonsafety related I

components that would adversely affect shutdown capability

(e.g., RHR/RCS isolation valves).

,i

(1) High/ Low Pressure Interfaces l

The licensee has identified the following high/ low pressure

interfaces and methods for controlling the interfaces:  ;

Interface Method of Control Status

l- ERV & Associated Block valve CV 1000 has a transfer

Block Valve switch at MCC 861. Separation of cables

is maintained outside of containment.  !

Decay Heat Drop Procedure 1102.02, Revision 36, I

Line Valves December 16, 1986, Plant'Startup  ;

Step 6.4.9.C, opens CV-1050 breaker 1

after shutting the valve.

Letdown Valves The cables to CV-1214, CV-1216, and  !

CV-1221 are routed separately outside of

l the Control Room. .The alternate

shutdown procedure deenergizes MCC B51

to assure that the interface is isolated.

l

.

j

_ _ _ _ - - >

- _ - _ _ _

.

19

High Point Vents .The design flow 1 capacity at the high

point vent path is_less than the

definition of a LOCA.

'The licensee's protection for. fire induced spurious operation of

high/ low pressure' interfaces was found to be satisfactory.

(2) Current Transformer Secondaries

The licensee's current transformer (CT) analysis, EE-86-0002,

January 10, 1986, ANO-1, "Possible Appendix R Concerns Due to

Open CT Circuits," determined that the CT saturation

characteristics will. limit potential and energy in CT

secondaries such that secondary fires could not be induced by

open CT secondaries.

The licensee's protection for current transformer open secondary

concerns was found to be satisfactory.

(3) Isolation of Fire Instigated Spurious Signals

The licensee has provided isolation for fire instigated spurious

signals by various methods, including:

Administrative controls '

Rerouting of cables

Wrapping cables

Isolation / Transfer switches (redundant fuses used)

Fuses

Signal isolators

During the inspection, all forms of isolation listed above were

observed.

The licensee's methods of fire-instigated spurious signal

isolation were found to be satisfactory.

c. Common Enclosure

The common enclosure associated circuit. concern is found when

redundant circuits are routed together in a ' raceway or enclosure and

they are not electrically protected, or fire can destroy both

circuits due to inadequate fire protection means.

Licensee representatives state that:

Redundant safe shutdown cables are never routed in common

enclosure.

l

L

.

1

1

20 '

b

j

,

'*

Nonsafety-related. cables routed in common enclosure with I

redundant safety-related cables are never routed between 'l

redundant trains.

All circuits are electrically protected.

During the' inspection, no exceptions to the above statements were

noted.

I The licensee's protection for the common enclosure associated circuit

concern was found to be satisfactory. j

l

d. Cable Routing l

'

Documentation (cable routing) review and physical in plant inspection

were performed on the following: i

Component Type Cable

Primary Makeup Pumps P36A/B/C Power

Fuel Oil Transfer Pumps P16A/B Power

The cabling for th'e redundant' fuel oil transfer pumps has less than

20 feet of horizontal separation in several areas of the plant. The

licensee has provided alternate shutdown capability using Unit 2 fuel ,

oil transfer pumps. I

i The cabling for the redundant primary makeup pumps has been provided

separation by 3-hour fire barriers or has been fire wrapped.

'

l

1

, The licensee's separation analysis for components requiring manual  ;

I operations in Fire Area B was questioned by'the electrical. inspector  ;

and the NRR representative. Licensee representatives had stated that l

redundant cables for manually-operated components in Fire Area B were- i

not completely walked down to verify separation in accordance with

Section III G.2 separation requirements. The licensee's basis for

not fully walking down Fire Area B cable routings was that credit was

being taken for manual operation so that the cables were not

required.

During the inspection, the licensee failed to provide marked up

drawings of cable routings for selected components. The licensee's

documentation to support providing the requested information was

available; however, the licensee did not have personnel resources.

available to produce the requested information during the inspection.

Cable separation / routing was found to be an unresolved item pending

documentation review and physical in plant inspection (to be '

l accomplished during the inspection of Unit 2 in June 1987, see

paragraph 13.b) of the following:

l

_ - _ _ - _ - - - _ _ _ - - _ _ _ _ _ _ . _ - - _

.-

1

1

I

.)

21

.j

.i

Components Type Cables  ;

.

CV1407 and CV1408 (BWST) Power and Control

s

CV1219 and CV1220 (HPSI) Power and Control

PSV1000 and CV1000 (PZR.PORV) Power and Control

1

CV1228 and CV2618 (SG ATMOS and associated j

block valves)' Power and Control j

P4A/B/C (Service Water Pumps) Power and Control-

LT1001 and LT1002 (PZR Level) Instrumentation j

PT1042 and PT1041 (RCS Press) Instrumentation

TE1144 and TE1147 (RCS Temp) Instrumentation

!

LT2620 and LT2624 (SG Level) Instrumentation

NE501 and NE502 (Source Range) Instrumentation l

l

LT4204 and LT4205 (CST Level) Instrumentation ,

l

, Redundant Components in Fire Area B Power and Control I

requiring manual operation

i

e. Modification Review

The licensee's process for controlling the design and installation of ,

modifications was reviewed for proper review and approval, including

10 CFR 50.59 aspects. The following Appendix R modifications were

reviewed:

Tech Safety

Testing Training Spec Question

Modification Description _Compl Compl Review Review

,

DCP 84-1061 EDG Room Exhaust 05/31/85 01/20/86 11/17/84 11/17/84

Fans Control

Isolation

i

DCP 83-1008 Disconnect 05/01/85 11/06/84 09/26/84 09/26/84

l Switches "B"

Makeup Pump

DCP 83-1012 CV-1000 03/25/85 10/15/84 09/12/84 09/12/84

Modification

l

_ - _ - _ _ _ _ _

I

22

DCP 82-2079 EDG Cross 07/18/83 09/20/82 10/30/82_ 10/30/82

Connect

The control of modification design is governed by Procedure 202,

Revision 10, dated November 7, 1986, " Design Process," which provides

for design review for Appendix R concerns. The administration of

modifications for Appendix R concerns'was found to be satisfactory.

f. Control of Cables

The licensee controls / tracks cables using Procedure 216, Revision 1,

dated April 30, 1987,." Guideline'for. Evaluation of Safe Shutdown

Capability and Control of Safe Shutdown Capability Assessment." This

procedure provides the following forms for maintaining the-cable data

base:

Form Description

216 F2 Used to add new shutdown components and their related

cables to the data base.

216 F3 Used to add new shutdown cables and associated cable

data.

The licensee's control of cables was found to be satisfactory.

8. Post-Fire Safe Shutdown (Unit 2)

a. Systems Required for Safe Shutdown

The systems required for safe shutdown are grouped according to the

performance goals for PWR safe shutdown functions to achieve both hot

l standby and cold shutdown.

(1) Reactivity Control

Upon notification of a major fire, initial. reactivity control is

, provided by inserting the control element assemblies via

l

operator initiation of a reactor manual trip from the main

i_ control room. The reactor may also be tripped from outside the

control room by locally opening reactor protection system

i breakers or tripping the reactor protection system

i

motor generator sets.

1

Additional boration will be provided throughout the cooldown by

intermittent operation of the coolant charging pumps (CCPs)

taking suction from the boric acid makeup (BAM) tanks. The BAM

tanks (2T6A and 2T68) are required by Technical Specifications

to contain a minimum of 8121 gallons (65 percent capacity) each

at a baron concentration of no less than 8750 ppm. With the

letdown paths isolated, the licensee has determined that

- - - _

,

]

23 l

I,

injection of boric acid from the BAMTs via a CCP for a 3

cumulative run time.of 84 minutes will assure that a '

-5.5 percent shutdown margin will be maintained during the

cooldown. In the event that suction from the BAM tanks isn't

available, the refueling water tank (464,900 gallon minimum

Technical Specification volume of at least 1731 ppm boron

concentration) may be used as a boric acid source. Boron

injection from the. refueling water tank will ensure that the

reactor will remain subcritical with at least a -1 percent 3

shutdown. margin.

(2) Reactor Coolant Makeup (Level and Pressure Control)

For a post-fire safe shutdown, reactor coolant system (RCS) 1'

inventory will:be controlied first by isolating all reactor

coolant leakage paths and' verifying isolation of these paths.

Potential loss pathways include normal letdown, reactor vessel

head vents, reactor coolant pump (RCP). seal bleedoff, RCS

high point vents, and pressurizer vent /LTOP relief isolation

valves.

The only makeup thus required will be to offset inventory

shrinkage resulting during the cooldown. Steam generator l

overcooling pathways will be controlled to regulate RCS

inventory shrinkage by tripping the main feedwater pumps

controlling emergency feedwater (EFW) flow, closing the main

steam isolation valves and turbine bypass valves, tripping and

i

verifying tripped the main turbine, and controlling the l

l

atmospheric dump valves.

'

Isolation of the direct RCS leakage paths and control of the

steam generator overcooling pathways as described above will

limit most of the variations in pressurizer level to inventory

shrinkage due to cooldown. Borated' inventory makeup will be

,

'

provided as required via the CCP taking suction from the BAM

tanks or refueling water tanks. The coolant charging pumps will

be started and stopped to maintain inventory (as monitored by.

temperature-compensated pressurizer level) and control RCS

l

pressure.

RCS pressure may be more easily controlled by operation of the

vital bus powered pressurizer heaters if they are available.

l However, the pressurizer heaters are not mandatory for achieving

and maintaining safe shutdown.

(3) Decay Heat Removal

Decay heat will be removed from the reactor following a reactor.

scram via the steam' generators by natural circulation cooldown.

Emergency feedwater is supplied to the "B" steam generator

(2E24B) by the emergency feedwater system to provide makeup for

- _ - - _ _ _ _ _ _ _ _ - -

__ _- _ -

,

1

i

24' j

the inventury discharged as steam from the safety relief valves I

and.the atmospheric dump valves. Emergency feedater may also  ;

be supplied to the "A" steam generator (2E24A); however, the-

instrumentation monitoring this component is not protected.to

the requirements of 10 CFR 50, Appendix R. Only one steam

generator is required to perform a natural circulation cooldown.

The emergency feedwater system consists of one motor-driven j

pump (2P78) and one turbine-driven pump ~(2P7A) interconnected to 'I

permit supply of emergency feedwater to either one or both of l

the steam generators from either or both of the pumps. The-

motor-driven pump and its associated components are powered. from

the red train, AC engineered safeguards buses. The

i turbine-driven pump.is powered by steam from the steam

l

generators and its associated components and controls are  !

supplied by the green train, battery-backed DC buses.

l

The condensate storage tanks (2T41A and 2T41B), with maximum

capacity of 200,000 gallons each, will serve as the normal water

sources for the emergency feedwater system. The on-line CST has

a Technical Specification minimum capacity of 160,000 gallons,

which equates to about a 12-hour supply for natural circulation

cooldown. The backup source of feedwater is the service water

system.

The EFW system automatic operating logic is provided by the i

emergency feed activation system (EFAS). The system will auto

initiate upon loss of main feedwater, low steam generator level,

or low steam generator pressure.

Steam release from the steam generators will be controlled by

, the atmospheric dump valves and/or the mechanical safety relief

I

valves. Controlled operation of the atmospheric dump valves

will be utilized to achieve the desired RCS cooldown rate.

(4) Process Monitoring

The following process conitoring instrumentation is available in

the control room and on the SPDS " Alternate. Shutdown" display:

Source Range Flux

Pressurizer Pressure

Reactor Coolant System B Hot Leg Temperature

Reactor Coolant System D Cold Leg Temperature

B Steam Generator Level

B Steam Generator Pressure

Pressurizer Level

Pressurizer Temperature

The safety parameter display system (SPDS) at ANO is a

computer-based system used for monitoring and display of plant

___ _ _ -

- _- -

)

i

l

25

i

i

safety parameters developed in accordance with the requirements {

of NUREG-0737. The SPDS configuration at AND is designed to J

provide redundant isolated data acquisition, processing, and i

display devices. Two redundant display terminals are available

in the control room and also in the TSC for alternate shutdown. )

Software has been developed to display the above parameters as J

well as provide trending data on.an." Alternate Shutdown". display

'

screen.

In addition, the following local indicators are available:

~1

2P7A EFW Pump Discharge Pressure j

Shutdown Cooling Heat Exchanger (2E35A) Inlet Temperature  !

I

Shutdown Cooling Heat Exchanger (2E35B) Inlet Temperature

Steam Generator Pressure (at the ADV area)

CST 2T41A Level i

CST 2T41B Level )

!

(5) Support Systems 1

1

The safe shutdown components and systems require the operation l

of several cr.itical support systems in order to properly perform 1

their safe shutdown function. The-following systens must have f

one train operating to support the safe shutdown: j

Service Water System l

l

Emergency Diesel Generators

Diesel Fuel Oil Transfer. System j

Emergency (Engineered Safeguards) AC Power Distribution

System

,

Uninterruptible DC Power Distribution System

l HVAC for all Essential Areas

Emergency Lighting

Radio Communication System

SPDS

At the time of the ANO-2 inspection, the licensee had not yet

provided an analysis to support the decision not to provide-  !

ventilation for either the ANO-1 electrical equipment /switchgear

rooms (Rooms 95-0, 99-N,100-N,104-5, and 110-L on

elevation 368-378 ft. of the auxiliary building) or the ANO-2

electrical equipment /switchgear rooms (Rooms 2091-BB, 2097-X,

2099-W, 2100-Z, 2101-AA, and 2108-S on elevation 368-378 ft. of-

- _ _ _ _ _

i

l

1

26

I

the auxiliary building) protected in accordance with 10 CFR 50,.

Appendix R requirements. These items will remain unresolved

until adequate analysis of the ventilation requirements has been

provided. (313/8714-05; 368/8714-05)

(6) Cold Shutdown i

The RCS temperature'and pressure.will be reduced by natural

circulation cooldown using the atmospheric dump valves and the j

emergency feedwater system.as described ~in the previous l

sections. Once the RCS temperature has been lowered to between

270 F and 275 F, the RCS will be depressurized to below

275 psia, and the shutdown cooling system will be placed'into

operation. The shutdown cooling system will then be used to

reduce the RCS temperature to 200 F and maintain cold shutdown. .l

1

'

b. Alternate Shutdown

.

l

.The licensee has provided alternate shutdown capability for fire-

.

occurring in any of the following areas which results in a functional

loss of control room instrumentation and controls, or. requiring

evacuation of the control room:

2098-L, Cable Spreading Room l

2199-G, Control Room Unit II

2150-C, Core Protection Calculator Room ,

2136-I, HP Office

2137-I, Upper South Electrical Penetration Room

2119-H, Control Room Printer Room (Old Shift Supervisor Office)

i

The Procedure 2203.14, Revision 4, " Alternate Shutdown," will  ;

implement the safe shutdown from outside the control room.  ;

1

Initial reactivity control will be provided by manually scramming the

reactor jusf prior to evacuating the control room. LThe shift

supervisor will direct the remainder of the shutdown from the TSC j

(3rd floor of the Administration Building) using portable radios to

communicate with shift personnel deployed throughout the plant.

Monitoring of piant parameters is provided on either of the two

redundant safety parameter display system terminals in the TSC.

It should be noted that ANO-1 and -2 share what is essentially a

common control room, separated by only a glass wall. Both unit

control rooms share a common ventilation and air conditioning system. i

for this reason, a significant Unit 2 control room fire requiring

evacuation would in all likelihood require a Unit 1 control room

evacuation and shutdown of Unit 1 in accordance with

Procedure 1203.29, " Remote Shutdown."

The alternate shutdown procedure directs RCS level and pressure

control by locally verifying and manually isolating as required, the

_ -_ - -

27

~

RCS letdown pathways and steam generator. overcooling pathways. .

Operators then verify the coolant charging pump. injection. pathway and-

4

-locally operate the pumps from the switchgear. breakers under

direction of the shift supervisor. i

Although pressurizer heaters are not relied upon for.'saf' e shutdown'

capability, RCS pressure may be more ' easily controlled by local'

manual' operation of the ESF. bus-powered pressurizer proportional

heaters from the local heater SCR Control Panels 2C117 and 2C118.

The proportional heaters may be operated either full on or_ full off

under the direction of the shift supervisor.- The backup pressurizer

heaters may also be controlled similarly from their. load center

supply breakers if offsite power.is available, q

Decay heat removal by natural _ circulation is established by first

verifying the operation of the turbine-driven EFW Pump 2P7A.. Steam.

supply to the turbine and flow path from the CSTs 2T41A and -B to the

"B" steam generator will be verified, and the~ turbine manually l started'

if it did not auto start or had tripped. The EFW flow will'be

locally controlled manually by throttling the 2P7A trip / throttle

valve as directed by the shift supervisor to achieve a stable natural'

circulation cooldown. As time and additional manpower. permit, the

motor-driven EFW Pump 2P7B flow path will be verified. When AC power

is restored, 2P78 may provide feedwater to the steam generators in -

preference to 2P7A to eliminate the need for 2P7A trip / throttle

adjustment.-

Steam release from the steam generators will initially be provided by

the mechanical safety relief valves. As additional manpower becomes

available, the atmospheric dump valves will be manually operated

under the direction'of the shift supervisor. If bein

locally (manual operation of the air operated valves)g operated-

, the operator

will be told to reduce steam header pressure as required'to achieve

the desired cooldown rate. If the isolation valve control circuit is

undamaged, the isolation valves may be electrically operated at the

MCC3 to control RCS cooldown rate.

c. Area Compliance With Appendix R,Section III.G.2

10 CFR 50, Appendix R, Section III.G.2, specifies that where

redundant trains of systems necessary to achieve and maintain hot

shutdown' conditions'are located within the same fire area, one of the

following means of ' ensuring -that one of the redundant trains is free

of' fire damage shall be provided:

(1) separation of cables and equipment and' associated nonsafety

circuits of redundant trains by a fire barrier having a'3-hour.-

rating,

(2) separation of cables and equipment and associated nonsafety

circuits of redundant trains by a horizontal distance of more

I

l

28 l

1

than 20 feet with no intervening combustible or fire hazards.

In addition, fire detectors and an automatic fire suppression  !

system shall be installed in the fire area, or ]

(3) enclosure of cable and equipment and associated nonsafety i

circuits of one redundant train in a fire barrier having a i

1-hour rating. In addition, fire detectors and an automatic

fire suppression system shall be installed in the fire area.

(a) Fire Area B, Fire Zone 2091-88, North Electrical Equipment

Room

Fire Zone 2091-BB was selected because it contained

redundant associated circuit components and cabling for the t

pressurizer vent and relief valves high/ low pressure {

interface. The following conditions were found to exisc:

There is less than 20 feet of horizontal separation

between the DC motor starters for 2CV-4698-1, ECCS

vent valve, and 2CV-4740-2, pressurizer LTOP relief

isolation. )

j

Fire detection is provided. l

Automatic fire suppression is not provided.

An exemption from the fixed fire suppression

requirement of Section III.G.3 has been granted by SER

dated March 28, 1983. (An alternate capability has

been provided for the fuel oil transfer pumps in this

zone)

Fire Area B, Fire Zone 2091-BB, north electrical equipment

room, was found to be not in compliance with Appendix R,

Section III.G.2.  !

(b) Fire Area JJ, Fire Zone 2109-U, Corridor and Motor Control

Center

Fire Zone 2109-U was selected because it contained

>

redundant associated circuit cabling for the pressurizer

LTOP relief valves high/ low pressure interface, the  ;

shutdown cooling suction valves high/ low pressure

interface, and the RCS letdown valves high/ low pressure  ;

interface. The following conditions were found to exist:

Less than 20 feet of horizontal separation exists for

the following redundant cables:

- Pressurizer LTOP Relief Isolation 2CV-4731-2,

Power Cable G2861L2A and Control Cable G2861L2C,

_ _ _ _ _ _ - _ _ _

i

l

I

29 1

.and Pressurizer LTOP Relief Isolation 2CV-4730-1,

Power Cable R2851E4A.

l

-

Pressurizer LTOP Relief Isolation 2CV-4740-2,  !

Power Cables G2026A,'-B, -C, and -F, and Control

Cable G2D26A3J; and Pressurizer LTOP Relief-

Isolation 2CV-4741-1, Power Cable R2B51K2A.

-

Shutdown Cooling Suction Valve 2CV-5084-1, Power

Cable R2851G28.and Control Cable R2851G2E,~and

Shutdown Cooling Suction Valve 2CV-5086-2, Power

Cables G2B62E5L, -M, and -N.

-

RCS Letdown Flow Valve 2CV-4823-2, Control

'

Cable G2S017C, RCS Letdown to Regenerative Heat

Exchanger Valve 2CV-4820-2, Power Cable G2B61L3B

and Control Cable G2861L3C, and RCS Letdown i

Containment Isolation Valve 2CV-4821-1, Power -!

Cable R2B51M1B and Control Cable R2B51M10.

Fire detection is provided.

Automatic fire suppression is provided.

An exemption from the 20-foot horizontal separation.

requirement of Section III.G.2 has been granted by SER

dated March 28, 1983, for electrical distribution

Panels 2RS3 and 2RS4.

Fire Area JJ, Fire Zono 2109-U, corridor and monitor I

control center, was found to be not in compliance with

Appendix R,Section III.G.2.

(c) Fire Area EE, Fire Zone 2111-T, Lower South Electrical

Penetration Room

Fire Zone 2111-T was selected because it contained

redundant associated circuit cabling for the pressurizer

.

LTOP relief valves high/ low pressure interface and the

shutdown cooling suction valves high/ low pressure

interface. The following conditions were found to exist:

Less than 20 feet of horizontal separation exists for

the following redundant cables:  !

-

Pressurizer LTOP Relief Isolation 2CV-4731-2,

Power Cable G2B61L2A and Control Cable G2B61L2C;

and Pressurizer LTOP Relief Isolation 2CV-4730-1,

Power Cable R2851E4A.

l

- _ _ - _ _ - _ _ _ _ .

30

!

- Shutdown Cooling Suction Valve 2CV-5084-1, Power i

Cable R2B51G2B and Control Cable R2B51G2E; and

Shutdown Cooling Suction. Valve 2CV-5086-2, Power

Cables G2B62E5L, -M, and -N.

Fire detection is provided.

Automatic fire suppression is provided.

,

Fire Area EE, Fire Zone 2111-T, lower south electrical

penetration room, was found to be not in compliance with  !

Appendix R,Section III.G.2.

Th'e licensee's non-compliance with 10 CFR 50, Appendix R, l

Section III.G.2 is summarized in the following table. . i

These items are considered as unresolved pending resolution 1

between the licensee and NRR. (Seealsoparagraph11.b.(1)) j

l

1

1

l

4

I

.

\

-_-_-_- _

. _ .

. _ _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ _ _ - _ _ - _ _ _ _ _

l

31

TABLE 9.c

SECTION III.G.2 NON-COMPLIANCE SUMMARY TABLE i

l

Fire Fire Redundant Component Type Cable .Non-

Area Zone Component Description Cable Number Compliance

B 209188 2CV469B-1 ECCS Vent Valve DC Motor Starter <20 ft Sep

2CV4740-2 LTOP Isolation DC Motor Starter

JJ 21090 2CV4731-2 LTOP Isolation Power G2861L2A <20 ft.Sep

l

Control G2861L2C

2CV4730-1 LTOP Isolation Power R2851E4A

JJ 21090 2CV4740-2 LTOP Isolation Power G2026A3A <20 ft Sep

Power G2026A3B l

l

'

Power G2026A3C ,

Power G2D26A3F  ;

'

l Control G2026A3J

l

2CV4741-1 LTOP Isolation Power R2851K2A

JJ 21090 2CV5084-1 SDC Suction Power R2851G2B <20 ft Sep

Control R2B51G2E

2CV5086-2 SDC Suction Power G2862E5L

Power G2862E5M i

l Power' G2862E5N

JJ 2109U 2CV4823-2 Letdown Flow Control. G25017C <20 ft Sep

2CV4820-2 Letdown RHX' Power G2B61L3B

Control G2861L3C

2CV4821-1 Letdown Isol. Power R2B51M1B

1

Control R2B51M1C

EE 211fT 2CV4731-2 LTOP Isolation Power . G2861L2A <20 ft Sep

Control G2B61L2C

2CV4730-1 LTOP Isolation Power R2851E4A

EE 2111T 2CV5084-1 SDC Suction Power R2851G2B <20 ft Sep

Control R2B51G2E

2CV5086-2 SDC Suction Power G2B62E5L

Power G2B62E5M

Power G2862E5N

1

!

1

i

'  !

i

32

9. Procedures (Unit 2)

1

The procedures reviewed during this inspection include a post-control l

room-fire alternate shutdown procedure, a remote shutdown procedure, l

Technical Specification surveillance procedures, fire alarm corrective i

action procedures, plant operating procedures, an emergency plan

'

implementing procedure, and an emergency operating procedure. j

a. Alternate Shutdown Procedure 2203.14, Revision 4

In the event of a fire in any of the areas which results in.

evacuation of the ANO-2 control room, the licensee may shut the i

reactor down from outside the control room in accordance with the 4

Procedure 2203.14, Revision 4, " Alternate Shutdown."

The minimum operating shift complement for Unit 2 consists.of the .

following personnel: l

itle Control Room Evacuation Assignment

Shift Supervisor 3rd floor technical support center

Shift Administrative 3rd floor technical support center & plant

Assistant library

Shift SR0/ Control Switchgear, EDG, battery rooms

Room Superviror  ;

Reactor Operator EFW pump room, various locations per

No. 1 procedure and shift supervisor's direction

Reactor Operator Various locations in auxiliary / turbine  !

No. 2 buildings per procedure and shift

supervisor's direction

Waste Control Fire brigade leader, affected unit 1

Operator

Auxiliary Operator Fire brigade member

The first five people above are required to implement the control

'

room evacuation procedure. The shift supervisor is'in charge of the

normal operating shift and he continues in that role upon entry into

the procedure. He also serves as emergency director of the emergency

' response organization until the TSC is formally activated. The waste

control operator and auxiliary operator together with other onshift

personnel will staff the fire brigade. Available additional

operators will be utilized to support the required operators.

Once the decision to evacuate the control room has been made, the

reactor will be tripped from the control room driving in the control

_-_

q

l

!

33 i

j

element assemblies for. initial reactivity control. Several other

immediate actions will be attempted from the main control room prior

to evacuation. If unsuccessful, however, all are covered I

procedurally from outside the control room soon after the evacuation, l

with the exception of MSIV's closure. The licensee agreed to ravise 1

the procedure to include the latter action.

Following the control room evacuation, the operating shift personnel

then proceed to their post-evacuation assignments as. outlined above, J

to implement'their assigned procedure sections, attachments, and i

checklists. The remainder of the alternate safe shutdown will be i

l directed and. monitored by the shift supervisor from the technical .)

support center, 3rd floor of the administration building. ]

l i

b. Procedure Walkdown I

The alternate shutdown procedure (2203.14, Revision 4) walkdown was

initiated at 2:05 p.m. on June 11, 1987, using five people from the ,

licensee's operating staff with the proper training and 1

qualifications to fill the control room operating shift positions.

Since the procedure is symptom oriented, the following initial

conditions were presented:

Fire in control room of sufficient. size to require evacuation ,

I

'

Coincident loss of offsite power  !

Both EFW pumps fail to auto start l

Both standby diesel generators failed to auto start I

All system lineups as normally found at full power

Two NRC inspectors accompanied the shift supervisor and the shift

i administrative assistant to the 3rd floor TSC. They remained there

l to observe personnel actions, crew direction and leadership,

communications, use of the SPDS, interface with and initiation with

l

and initiation of emergency plan implementation procedure,.and

training and familiarity with the alternate shutdown procedure. Two

other NRC inspectors each accompanied the shift SR0/ control room

supervisor and the Reactor Operator No. I to observe their actions at

the electrical e,uipment rooms and EDGs, at the EFW pump rooms,

observe lighting at work stations and access routes, evaluate

communications, and evaluate training'and familiarity with the

procedure. Reactor Operator No. 2 was not accompanied by an NRC

inspector during the procedure walkdown, so his actions were

monitored from the TSC as he made his call-ins to the shift

supervisor.

The procedure was halted during Step 12 of Shift Supervisor

Section I, which demonstrated that stable hot standby natural

circulation conditions could be achieved and a controlled rate of ,

cooldown was to be commenced. Emergency feedwater flow to the

"B" steam generator via the turbine-driven EFW Pump P7A was

established and associated valve lineups verified within 23 minutes.

_ _ - _ -

m

!

34

l

a

Both emergency Diesel Generators.2K4A and 2K4B were, manually started

and loaded within 18 minutes of start of event. Motor. control'

centers supplying power to the ECCS vent valve (2CV-4698-1) and ,

pressurit er LTOP relief valves (2CV-4731-2, .2CV-4740-2, 'andi .I

2CV-4741-1)weredeenergizedwithin6' minutes..The'operatingstaff'

'

demonstrated adequate training and familiarity with the' procedure

throughout the walkdown.

The only procedural deficiencies identified;were:

(1) Immediate Action No. 6 in Section I.of the' procedure directs

closure of main steam isolation Valves 2CV-1010-1 and 2CV-1060-2

prior to. control room evacuation.- Credit'is given for only one~

manual action prior to evacuation;t typically ~ this is. the reactor d

i manual trip. . The' procedure should be revised to. direct MSIV i

closure from outside the control room if-Irr. mediate Action No. 6

is unsuccessful. -(All other immediate action steps are covered'

later on.in the procedure.) The licensee' agreed to incorporate-

such a revision.

(2) Step 11 in the Shift Supervisor Followup Actions,Section I

directs the tracking of cumulative Coolant : Charging Pump run

time to determine' the amount of boric acid added to the RCS.

The procedures should provide a table to record and track ~ the

run times and should indicate who is to record this information.

The licensee agreed to incorporate such a revision. q

Another improvement to the alternate shutdown procedure would be to

include a note alerting the shift supervisor that he may also use l

"A" steam generator to remove decay heat during cooldown; however, i

the instrumentation monitoring this component is not protected to the H

requirements of 10 CFR 50, Appendix R. If the "A" steam generator .

instrumentation is unavailable, he must make- a judgement as to -  !

whether to supply EFW to the "A" steam generator as directed by the ,,

procedure in Step 9 of Reactor Operator No'. 2 Followup Duties

(Section I). Only one steam generator is required for safe shutdown..

It should be noted that the procedural deficiencies and -improvements 3

indicated for the' Alternate Shutdown Procedure 1203.02, Revision 4 '

t

during the AN0-1 inspection in May 1987 were reviewed and. l

incorporated as applicable into the ANO-2 Alternate Shutdown- i

Procedure 2203.14 Revision 4, prior to the ANO-2' inspection in-

June 1987. These included interface direction between Units 1 and 2  ;

control rooms for a control room / cable spreading room fire, equipment 1

checklists for operators at the alternate shutdown equipment locker,

and a radio check step prior to dispatching operators 'to their

alternate shutdown duty locations.. The licensee should be commended

on his responsiveness in incorporating these improvements. ,

l

- -_ _ _- -_

35

i

c. Fire Alarm Corrective Action Procedures and Fire Preplans

i

Procedure 2203.12K, Revision 13. " Annunciation K12 Corrective Action,"

.

and Procedure 2203.09, Revision 5, " Fire Protection System 4

Annunciation Corrective Action," were reviewed to evaluate the train

of responses followed by the control room operator upon receipt of a.

fire annunciation alarm. The procedures were found to adequately

direct the operators to identify the origin of an alarm, verify its

validity, and respond accordingly. The fire preplans were readily

available in the control room to guide the operators in their

response,

d. Technical Specification Surveillance Procedures

Surveillance test procedures covering a sampling of Technical ,

Specification surveillance requirements for various post-fire safe  !

shutdown components and systems were reviewed. These included

procedures for valve lineup verification of several safe shutdown

systems, the motor-driven emergency feedwater Pump 2P7B, and the

turbine-driven emergency feedwater Pump 2P7A. The past two

performances of monthly Technical Specification Surveillance

Procedures 2102.01, Revision 22, " Plant Pre-Heatup and Pre-Critical-

Checklist," Attachment E - Category.E Valve Position Verification; l

,

and 2106.06, Revision 21, " Emergency Feedwater System Operations,". i

l Supplement I for 2P7A and Supplement II for 2P7B, were retrieved for i

'

inspection of test results. This review showed the procedures to be

adequate and the performances reviewed were performed on time and i

documented adequately. j

l

e. 0_perator Training on Safe Shutdown Procedures-- l

In addition to observing the operator's performance during the

walkdown of the alternate shutdown procedure, operatioris technical

support and operator training personnel were interviewed concerning

operator training on Appendix R post-fire safe shutdown procedures

and equipment. The training covered Appendix R equipment, Alternate

Shutdown Procedure 2203.14, and the fire protection program manual

and fire preplans. The program includes classroom instruction,

walkdowns, and hands-on operating experience. An annual

requalification cycle will be maintained in accordance with

10 CFR 55, May 26, 1987, edition.

The licensee is presently revising the Appendix R-related training to

enhance the fire pre-plan instruction and to integrate plant-

simulator exercises into the safe shutdown / alternate shutdown

portions of the course. The mechanical systems specialist observed

the performance of one crew on an unannounced alternate shutdown

exercise on the simulator. The personnel involved demonstrated good

knowledge of the plant and the required procedures and responded

adequately to the scenario presented to them. All six shift crews

( _ _ _ _ _ _ _ _ - -

,

,

'

] ;

I

1

36 3

l

1

,

will have completed an alternate shutdown' exercise on the plant

simulator within the next few veeks. J

l

.A general lesson plan utilized to administer Appendix R was provided-

for inspection. Training records for' operating shift personnel were

also reviewed. These areas reviewed were found to be acequate.

10. Protection for Associated Circuits (Unit 2). ,

1

Common Bus Concern

Spurious Signals Concern-

Common Enclosure Concern

a. Common Bus Concern .

The common bus associated circuit concern is found in circuits,.

either nonsafety-related or safety-related, where there is a common  ;

power source with shutdown equipment and the power source is not I

electrically protected from the circuit of concern,

1

The common bus concern is made up of two items: I

Circuit Coordination

High Impedance Fault Analysis

(1) Circuit Coordination

Breaker coordination is audited by reviewing the time current

curves developed during the licensee's bus coordination study.

At ANO, Unit 2, the following circuits were randomly selected 1

for review:  ;

Circuit Comment

Bus 2A3 Coordination satisfactory

Bus 2A4 Coordination satisfactory

,

Bus 2B5 Coordination satisfactory

Coordination satisfactory

'

'

Bus 2B6

MCC 2B51 Coordination satisfactory ,

MCC 2B61 Coordination satisfactory '

MCC 2B53 Coordination satisfactory

l MCC 2B63 Coordination satisfactory

2001 Coordination satisfactory

2002 Coordination satisfactory

2RS1 Coordination satisfactory

2RS2 Coordination satisfactory

2RS3 Coordination satisfactory

2RS4 Coordination satisfactory

2RA1 Coordination satisfactory

2RA2 Coordination satisfactory

4

l

_ _ _ _ ___m.__________ ~__

.__. .

H

37 )

2023 Coordination satisfactory i

2024 Coordination satisfactory j

The licensee's circuit coordination program was found to be

satisfactory, i

To ensure that the existing satisfactory circuit coordination is _

not compromised by future design changes, the licensee has an

established procedure for modification design review, 1

Procedure 216,, dated April 30, 1987,." Guidelines for Evaluation- i

of Safe Shutdawn Capability and Control of Safe Shutdown: 1

Capability Assessment.," which prevides for reviewing ~ 1

modification design far Appendix R concerns'.'

The licensee performs relay testing and maintenance at 10-month

intervals (each refueling outage). Circuit breakers are tested

and maintained at intervals of 60 months. Breaker and relay '

)

maintenance and testing.are currently scheduled manually. The

licensee is .in the precess of converting to' an automated

maintenance schedulirs system. ,

1

Maintenance recordslcr the following randomly selected circuit

breakers or protectiva relays were reviewed to verify that

maintenance and'tcsting are being performed at the specified .)

frequency

Required Completion l

Component. Title Frequency Date

BKR 2A113 Startup Number 3 156 Weeks 07/02/86

Feeder BKR

BKR 2A303 Service Water Pump 78 Weeks 07/07/86 I

2P-4B BKR

BKR 2H13 Startup Number 156 Weeks 06/21/86 i'

Feeder BKR

BKR 28-832 2B85 Supply BKR- 208 Weeks '08/07/86 i

The reviewed records documented compliance with established

maintenance procedures.

Control of fuse replacement is required to ensure maintenance of

coordination for circuits protected by fuses. The licensee's ,

controls for fuse replacement include the following: '

Procedure 1403.85, " Motor Control Center Preventive

Maintenance"

Plant Drawings / Prints

- _ _ _ _ _ - _ - _ _ _

,

!

38 j

i

. i

'

Technical. Manuals j

Job Orders-

!

Materials Controls  !

The licensee's fuse replacement controls were found to be

satisfactory.

'

l

1

(2) High Impedance Fault Analysis

The high impedance' fault concern is found in the case where

multiple high. impedance faults exist.as. loads on a safe shutdown j

power supply and cause the loss of the safe shutdown power  :

supply prior to' clearing the.high' impedance faults.

l The licensee's analysis .for high impedance faults, EE-87-014, i

( dated January 21, 1987, ANO, Units 1 and 2 position on multiple j

high impedance faults, determined that protection for i

simultaneous high ' impedance faults was~ provided by the

following- {

The 4.16 KV safety buses are equipped with ground fault -

relays.

The 4.16 KV and 480 V distribution systems.are grounded.

High impedance faults would rapidly propagate into low l

impedance faults and cause coordinated circuit breaker'

tripping. ]

I

i

In the event that a required electrical bus is lost due to I

high impedance faults', the licensee's procedures provide i

for manually tripping all breakers on the faulted bus and )

reenergizing required safe shutdown loads. ,

The licensee's analysis and protection for high impedance faults

were found to be satisfactory.

The licensee's protection for the associated. circuit common bus f

concern was found to be satisfactory.

i

b. Spurious Signals i

The spurious signal concern is made up of two items: I

The false motor, control, and instrument readings such as

occurred at the 1975 Brown's Ferry fire. These could be caused

by fire initiated grounds, short or open circuits.

l

!

l

a___-____--_-__-----_-____-_---_--__-__- _ _ - - - _ _ _ _ . _ - - _ _ _ - _ _ - _ _ - _ _ _ _ _ _ _ _ - _ - _ - _ - _ - _ - - -

39

Spurious operation of safety-related or nonsafety-related

components that would adversely affect shutdown capability

(e.g. , RHR/RCS isolation valves).

(1) High/ Low Pressure Interfaces

The licensee has identified the following high/ low pressure

interfaces and methods for controlling the interfaces:

Interface Method of Control Status

l High Point Vents Flow path capacity via 2SV-4636-1,

I. 2SV-4636-3, 2SV-4668-1, 2SV-4668-2,

'2SV-4669-1, and 2SV-4670-2 is less than

the definition of a LOCA.

Pressurizer Vent SER dated May 13, 1983, considered that

Valves 2CV-4698-1 spurious operation of this interface was

l and 2CV-4740-2 unlikely. The basis for this conclusion

l was that.for both valves to open, four

I

circuits would have to be spuriously

completed in two locations.

Documentation (schematics) review and

in plant inspection determined that only

l

'

two shorts, one in the control circuit

of each valve, were required to cause

spurious operation of the high/ low

pressure interface. The' interface is

,

i

susceptible to spurious operation for I

control room and cable spreading room  ;

fire-induced short circuits. Addition- -i

l ally, since the power. circuits for these y

valves do not have adequate separation- ~

as described in. paragraph 4.3, high/ low

pressure interface protection is not

provided in the north electrical l

equipment room,

RCS Letdown Flow SER dated May 13, 1983, determined that

Valve 2CV4823-2, this interface was not a concern. The i

RCS Letdown to basis for this determination was that

Regenerative Heat the letdown lines are flow restricted

Exchanger Valve lines protected by reliefs and would

2CV4820-2, and RCS require the failure of at least three

Letdown Containment valves to challenge the relief.

Isolation Valve

2CV4821-1 Documentation (schematics) review and

in plant inspection determined that

single shorts in the control circuit of

each valve were required to cause

,

-- _ - . _ - _ - _ - _ _ - _ . _ _ _ - - _ _ _ _ -

q

.4

L

40

.)

<

spurious operation of the high/ low

pressure interface. The interface is .,

susceptible to spurious operation for a

control room and cable. spreading room

~

fire-induced short. circuits. Addition- l

i ally, since the power and control  !

circuits for these valves do not have

'

)

adequate separation as described in i

paragraph 4.3, high/ low pressure I

interface protection is not provided in '

the corridor and motor control center zone

and lower south electrical penetration

room.

LTOP Relief Isolation. -This high/ low pressure interface is

Valves 2CV4731-2.and controlled by tagging 2CV4730-1 circuit

2CV4730-1 breaker'open after shutting the valve I

during plant startup.~ 'This method of

control is effective for control room  !

and cable spreading room fires. However,

power and control cables for the valves

do not have adequate separation as

described in paragraph 4.3 in the

corridor and motor control. center zone and

the lower south electrical penetration

room, causing the interface to be

unprotected for shorts and hot shorts in

these areas.

LTOP Relief Isolation This high/ low pressure interface is

Valves 2CV4741-1 and controlled by tagging 2CV4741-1 circuit

2CV4740-2 breaker open after shutting the valve

during plant startup. -This method of I

control is effective for control room

and cable spreading' room fires. However,

power and control cables for the valves

do not have adequate separation as

described in paragraph 4.3 in the

corridor and motor control center zone,

causing the interface to be unprotected ,

for shorts and hot shorts in this area. '

Pending resolution of these items between the licensee and NRR.

This will be considered an unresolved item. (368/8714-06)

(2) Current Transformer Secondaries

'

The licensee's current transformer (CT) Analysis EE-86-002,

dated January 10, 1986, ANO, Unit 1, Possible Appendix R

Concerns Due to Open CT Circuits, also applicable to Unit 2,

determined that the CT saturation characteristics limited

L______________.___ _ _ _ . _ _ _

41 .

potential and energy in CT secondaries such that secondary fires

could not be induced by open CT secondaries.

The licensee's protection for current transformer ypen secondary

concerns was found to be satisfactory.

(3) Isolation of Fire Instigated Spurious Signals

The licensee has provided isolation for fire-instigated spurious

ignals by various methods, including:

administrative controls,

rerouting of cables,

'

wrapping cables,

isolation / transfer switches (redundant fuses used),

"

fuses,

signal isolators, and

manual component operation.

During the inspection, all forms of isolation listed above were

observed.

The licensee's methods of fire instigated spurious signal

isolation were found to be satisfactory.

c. Common Enclosure

The common enclosure associated circuit concern is found when

l redundant circuits are routed'together in a raceway or enclosure and

l they are not electrically protected, or fire can destroy both

circuits due to inadequate fire protection means.

Licensee representatives stated that:

, Redundant safe shutdown cables are never routed in common

I

enclosure.

Nonsafety-related cables routed in common enclosure with

redundant safety-related cables-are never routed between

redundant trains.

All circuits are electrically protected.

During the inspection, the following randomly selected nonsafe

shutdown cables routed in common enclosure with safe shutdown cabies

were verified to be electrically protected:

Component Cable Number Location Protection

2CV8831-1 R2853A4A Raceway EB156 Circuit _ Breaker 2853A4

2CV1074-1 R2853C1C Raceway EB156 Circuit Breaker 2B53C1

_ _ _ - -

-_- - _ - _ _ _ _ _ _ - _. _.

--.

42

2VUCM-68-1 R2853K4A Raceway EB156 Circuit Breaker 2B53K4

2FS-8678-2 G2863C3E Raceway EC275 Control Power Fuse

2RE-8271-2 G2S110L Raceway EC275 Circuit Breaker R2RS1-13

2C184 G25124C Raceway EC275 Control Power Fuse

The licensee's protection for the common enclosure associated circuit

~

concern was found to be satisfactory.

11. Communications (Units 1 and 2)

The licensee has identified three communications systems available for

safe shutdown: por.able hand-held radios, the plant dial telephone

system, and the Gaitronics system. The primary means of communications

during alternate shutdown are the portable hand-held radios available in

the control room and the alternate shutdown radio cabinet. Plug-in

headsets are provided for the radios for ease of use and improved

background noise rejection. During the Alternate Shutdown procedure

walkdown hand-held radios with headsets were used for communications and

were found to be adequate.

The AP&L radio / communications group performs an annual frequency check and

functional check of all the radios. The repeater for the portable. radio

is powered by the security diesel and located on top of the Administration l

Building. A recent security upgrade of the in plant radio system to

provide a coaxial antenna for improved reception throughout the plant

incorporated the requirements for the Appendix R alternate shutdown

equipment locations into its design. The system has been thoroughly

tested to verify its performance in those areas where the portable radios

are required to provide safe shutdown communications.

Additionally, the plant dial telephone system (PAX) and plant announcing  ;

system (GAITRONICS) may be available to support safe shutdown

communications. The licensee does not take credit for these systems.

12. Other Electrical Evaluation (Units 1 and 2)

a. Cable Routing

Documentation (cable routing) review and physical in plant inspection '!

were performed on the following:

Component Type Cable

2P36A,B,C Power

2CV-4920-1 Power and Control

2CV-4873-1 Power and Control

2CV-4921-1 Power and Control

2CV-4950-2 Power and Control

2CV-4741-1 . Power and Control

2CV-4740-2 Power and Control

2CV-4731-2 Power and Control ,

. _ - - -

~

)

4

l

43

2CV-4730-1 Power and Control i

2P60A,B Power

'2P4A,B,C Power

2P16A,B Power  :

2VEF24A,B,C.D Power- i

2RA1,2' Power  ;

I 2021,22,23,24 Power

l SPDS Power i

2CV-1038-2 .

Control  ;

2CV-1026-2 Control '

2CV-1025-1 Control

'2CV-1037-1 Control  ;

2CV-1036-2 Control  :

2CV-1076-2 Control i

2CV-1075-1 Control 1

2CV-1039-1 Control

2CV-0798-1 Control

2CV-0714-1- Control

2PT-4624-1 Instrumentation. ]

2PT-4624-2 Instrumentation

2TE-4614-1 Instrutnentation

2TE-4714-2A Instrumentation  ;

2TE-4611-3B ' Instrumentation -l

2TE-4716 Instrumentation

2LT-4627-1 Instrumentation

2LT-4627-2 Instrumentation

2PT-1141-1 Instrumentation

2PT-1141-2 Instrumentation '

2LT-1179-1 Instrumentation

2LT-1179-2 Instrumentation

2JE-9000-1 Instrumentation i

2JE-9003-2 Instrumentation j

Except for the components discussed in paragraph 8.c, the routing of

the cables for the above components was found to be in compliance

with Appendix R,Section III.G separation requirements.  !

The licensee controls / tracks cables using Procedure 216, Revision 1,

dated April 30, 1987, " Guideline for Evaluation of Safe Shutdown

,

Capability and Control of Safe Shutdown Capability Assessment." This

l procedure provides the following forms for maintaining the cable data

j base:

Form Description

216 F2 Used to add new shutdown components.and their related

cables to the data base. '

I

I

216 F3 Use to add new shutdown cables and~ associated cable

data.

i

l

I

.-.._.-_______-..____._.___-_-a

44 j

'i

I

The licensee's control-of cables was found to'be satisfactory.

'J

-

b. Review of Unit 1 Cable Routing Open Item

During the May 1987, Unit 1, Appendix R inspection,-cable ,

i separation / routing was found to be an unresolved. item pending 1

l. documentation review and physical in plant inspection. The following

circuits were inspected during the week of the June 1987 Appendix R

inspection for Unit 2 to clear the Unit I cable routing unresolved

item:

Components Type Cables-

CV1407 and CV1408 (BWST) Power and Control j

j

CV1219 and CV1220 (HPSI) Power and Control-

PSV1000 and CV1000 (PZR PORV) Power and Control

CV1228 and CV2618 (SG ATMOS) Power and Control  :

l (and associated block valves) j

P4A/B/C (Service Water Pumps) Power and Control l

LT1001 and LT1002 (PZR Level) Instrumentation

i

PT1042 and PT1041 (RCS Press) Instrumentation i

TE1144 and TE1147 (TCS Temp) Instrumentation-

'

LT2620 and LT2624 (SG Level) Instrumentation

NE 501 and NE 502 (Source Range)- Instrumentation i

i

LT4204 and LT4205 (CST Level) Instrumentation i

Redundant Components in Fire Power and Control 4

Area B requiring manual operation

Documentation review and physical in plant inspection for Unit 1

cable separation / routing was completed satisfactorily. This closes

the unresolved item from the May 1987, ANO-1 inspection (see

paragraph 7.d).

c. Modification Review

The licensee's process for controlling the design and installation of ,

modifications was reviewed for proper review and approval, including  !

10 CFR 50.49 aspects.

l

t

1

!

j

45

1

The control of modification design is governed by Procedure 202,

Revision 10, dated November 7, 1986, " Design Process," which provides

for design review for Appendix R concerns.

The administration of modifications for Appendix R concerns was .found

to be satisfactory. >

13. Unresolved Item

.

.

1

An unresolved item is a matter about which more information is r.equired in

order to determine whether it is.an acceptable item, a violation,, or a

deviation. Three unresolved items are discussed in paragraphs 3, 8.a(5),  !

and 10.b(1) of this report. l

j

'

14. Exit Interview

An exit interview was conducted on June 12, 1987, with those personnel

denoted in paragraph 1 of this report. lAt this meeting, the scope of the

inspection and the findings were summarized.

I

!

'l

l

l

<

,

_ _ _ _ _ _ _ _ _ _ _ _ _ _

_ -

.,, .

>

'

21 $

0.

AlTACHMENT TO ,

,

NRC-INSPECTION REPORT

50-313/87-14; 50-368/87-14' '

APPENDIX C .l

DOCUMENTS REVIEWED

r ,

A. Letters, Reports, and Procedures j

I

Date Number Rev. Title j

t

08/30/85 Letter -

J.T. Enos (AP&L) to J.F. Stolz ]

'(NRC) & E.J. Butcher'(NRC), Results

of Reanalysis Against.NRC Clarifi-

cation / Interpretation of Appendix R' )

to 10 CFR 50 Supplemental Informa- l

tion j

02/23/83 Letter -

J.R. Marshall (AP&L) to J.F. Stolz

(NRC) & R.A. Clark (NRC), Hot.to- i

Cold Shutdown Scenario for Loss of i

Offsite Power-Exemption Request l

Details from Appendix R compliance '

submittals

05/11/83 Letter -

J.F. Stolz (NRC) to J.M. Griffen

(AP&L) concerning exemption to

Appendix R to 10 CFR 50, 4

Section III L.I for ANO-1 l

l

l 02/25/83 Memorandum -

L.S. Rubenstein (NRR) to

G.C. Lainas (NRR) .SER Supplement

for Appendix R to 10 CFR 50,

Sections III G. and III L. and ANO,

Units 1 and 2 l

l

11/15/82 Memorandum -

L.S. Rubenstein (NRR) to  !

G.C. Lainas (NRR), SER'for  ;

Appendix R to 10 CFR 50,

, Sections III G. and III L. - ANO, j

l Units 1 and 2

03/22/83 Letter -

R.A. Clark (NRC) and J.F. Stolz

(NRC)~to J.M.'Griffen'(AP&L)

concerning Exemptions to certain

requirements of Appendix R to ,

10 CFR 50 for ANO-1 and -2

05/04/87 1203.02 24 Alternate Shutdown

02/15/86 1102.10 27 Plant Shutdown and Cooldown

03/14/86 1203.13 6 Natural Circulation Cooldown ,

i

L--_________________________________________________________

,

2

12/16/86 1102.02 36 Plant Startup

FSAR Amend 4 Final Safety Analysis Report -

ANO-1

03/86 FPPM 2 Fire Protection Program Manual

05/21/74 Tech Spec Amend 106 Technical Specifications-

11/06/86 1000,06A 2 Remote Shutdown

'0/18/84 Memo ANO Unit 1 Training Scope of. Licensed'

84 11379 Requalification Cycle 4 8/28/84 to

9/28/84

11/13/84 Memo ANO Unit-1 Training Scope of Licensed

84 12620 Requalification Training Cycle 5

10/02/84 to 11/02/84

06/19/85 Memo ANO Unit 1 Operations Training ANO-

85 08359' Alternate Shutdown Procedure

Training

09/27/85 Memo ANO AND Cycle 4 Requalification

85 12245 Training Alternate Shutdown

10/03/85 Memo AN0 AN0 Cycle 4 Requalification-

85 12399 Training Alternate Shutdown

10/11/85 Memo AN0 AND Cycle 4 Requalification

85 12559 Training Alternate Shutdown  !

10/21/85 Memo AN0 AN0 Cycle 4 Requalification

85 12862 Training Alternate Shutdown

10/28/85 Memo AN0 ANO Cycle 4 Requalification

85 13013 Training Alternate Shutdown

11/05/85 Memo ANO AND Cycle 4 Requalification

85 13243 Training Alternate Shutdown

08/31- AA-99999-002 Training Attendance Records:

09/28/84 10 CFR, Appendix R-Related DCPs

10/05/84- AA-21003-004 Training Attendance Records:

01/24/85 AA-21001-008 Alternate Shutdown Procedure

07/26- AA-21003-004 0 Training Attendance Records:

10/31/85 Alternate Shutdown Procedure

l _ _ .- . __- -___ __ - _ - - -

R

3

i

i

l

11/07- AA-21001-008 Training Attendance Records: {

12/02/85 10 CFR 50, Appendix R-Required J

Equipment i

11/08- AA-21002-028 0 Training Attendance Records: Fire

, 12/13/85 Protection Manual

10/31/85 AA-51002-028 2 Plant Systems Training

09/29/83 AA-51001-008 1 Shift Administration l

01/02/87 1203.12K 20 Annunciator K12 Corrective Action

01/13/86 1203.09 Fire Protection System Annuncie. tor

Corrective Action +

12/05/84 1104.02 22 Makeup and Purification System

Operation

03/26/87 1106.06 31 Emergency Feedwater Pump 3peration

05/06/87 87E-0011-01 Calculation: Makeup Pump Room

Temperature with No Cooling Fan

10/15/85 85E-00081-01 Calculation: Decay Heat Vault

Temperature & Rate of Heat Rise

Assessment During Normal Decay Heat

Operation without Cooling

03/31/87 85E-00070-01 Calculation for Cooldown Without ,

Pressurizer Heaters  !

l

06/06/86 Memo Appendix R Treatment of HPI  !

NEL-066-25 Auxiliary Lube Oil Pumps (P64s)

03/31/87 85E-00071-01 Calculation: Evaluation of Time

Available for Manual Initiation of

EFW following Loss of All Feedwater

01/21/87 EE-87-014 ANO Units 1 & 2 Position On

Multiple High Impedance Faults

01/10/86 EE-86-002 A'N0 Unit 1 Possible Appendix R

Concerns Due to Open CT Circuits

12/05/84 1307,07 1 Testing & Maintenance of Metal Clad

Switchgear & Breakers

05/08/86 1403.81 1 Type K-225 Low Voltage Breakers

05/08/86 1403.82 1 Type K-600 Low Voltage Breakers

s

i

_______.__________________________s

'

.

4

!

l

05/08/86 1403.83 1 Type K-1600 Low Voltage Breakers-

05/29/86 1403.150 5. Relay Calibration for WA3 Bus

05/29/86 1403.151 1 Relay Calibration for DG1 Diesel

Generator

11/07/86 202 10 Design Process Procedure

04/30/87 216 1 Guideline for Evaluation of Safe

Shutdown Capability and Control.of 1

Safe Shutdown Capability Assessment

02/27/87 123 1 Forms Control'

)

1

02/02/87 J0#00728878 Fuse F10 in 20108 Replacement "

10/31/84 DCP 84-1061 Control Isolation for EDG Room

Exhaust Fans )

06/15/84 DCP 83-1012 CV-1000 Modification

08/20/82 GCP 82-2079 Install EDG Cross Connect Emergency '

Diesel Fuel Storage Building

06/21/84 DCP 83-1008 Provide Disconnect Switches for "B"

Swing Makeup Pump Appendix R  ;

08/18/82 OCAN088204 ANO Units 1 & 2 Additional' l

Information Concerning Reactor

Coolant System High Point' Vents

06/02/87 1107.01 27 Electrical System Operations

08/18/82 OCAN088204 Additional Information Concerning

AP&L Letter Coolant System High Point Vents

05/13/83 05831245 ANO Units 1 and 2 Fire Protection

SER

10/27/83 2307.30 PC-2 Testing'and Maintenance of Metal <

Clad Switchgear and Breakers Type '

AM-7.2-500-6H 1200 & 2000 Amperes

12/12/84 1403.82 PC-1 Type K-600 Low Voltage Breakers

10/27/83 2307.27 PC-1 Testing and Maintenance of Metal

Clad Switchgear & Breakers Type

AM-4.16-250-8H.1200 Amperes

,

i

_ - _ - _ - _ _ _ _ _ _ _ _ - - - - - - -

}

5

,

04/30/86 2403.65 2 Relay Calibration for 2B Load

Centers

02/11/87 2101.02 26 Plant Startup

03/21/86 1403.85 2 Motor Control Center Preventive l

Maintenance

01/21/87 EE-87-014 ANO Units-1 & 2 Position'on

' Multiple High Impedance Faults

04/30/87 216 2 Guidelines for Evaluation of Safe l

Shutdown Capability and Control of 1

Safe Shutdown Capability Assessment ']

01/06/84 0CNA018401 ANO. Units 1 & 2 Fire Protection j

Safety Evaluation Report l

03/22/83 OCNA038328 ANO Units 1 & 2 Fire Protection

Safety Evaluation Report

01/14/87 2203.14 4 Alternate Shutdown  ;

06/26/86 2102.10 17 Plant Shutdown and'Cooldown  ;

i

01/17/86 2203.13 4 Natural Circulation Cooldown

05/03/85 2203.30 1 Remote Shutdown

SAR Amend 4 Safety Analysis Report - ANO-2

12/11/86 Tech Spec Amend 81 Technical Specifications

08/12/86 AA-22003-004 Training Attendance Report:

Alternate Shutdown Procedure and

Walkthrough

08/17/86 AA-22003-004 Training Attendance Report:

Alternate Shutdown Procedure and '

Wal kthrough

08/26/86 AA-22003-004 Training Attendance Report:

Alternate Shutdown Procedure and

Walkthrough

09/05/86 AA-22003-004 Training Attendance-Report:  ;

Alternate Shutdown Procedure and  !

Walkthrough

_ _ - - -____ -- -- - _ _ _ -

l

i

k

6  ;

I

09/09/86 AA-22003-004 Training Attendance Report:

Alternate Shutdown Procedure and'

Walkthrough

09/16/86 AA-22003-003 Training Attendance Report:

Alternate Shutdown Procedure A0P .

'

2203.14

I

04/29/87 2203.09 5 Fire Protection System Annunciator d

Corrective Action

10/11/85 2102.04 11 Power Operation

03/23/87 2106.06 21 Emergency Feedwater System .]

,

Operations

]

l 10/29/86 AA-62002-008 2 Shift Administration

l 09/20/86 2203.12K 13 Annunciator 2K11 Corrective Action

l

WP870089 ANO Unit 2 Emergency Operating

l Procedure Technical Guidelines-

05/18/87 Memo Ventilation Requirements for

NEL-057-25 Electrical Equipment Room, ANO-1

& -2, Appendix R

09/21/77 Letter D.A. Rueter (AP&L) to D.K. Davis

and'J.F. Stolz (NRC)i ANO, Units 1

& 2, Docket Nos. 50-313 & 50-368,

License No. DPR-51 Fire Protection

08/30/77 Letter D.A. Rueter (AP&L) to J.F. Stolz &

D.K. Davis (NRC): ANO, Units 1 &

l 2, Docket Nos.- 50-313 & 50-368,

1

Fire Hazards Analysis & Miscellan-

eous Fire Protection Submittals

10/15/85 85E-00095-01 Calculation: Room 2091 Temperature

Assessment After Fire, Appendix R

Fire Evaluation

WP870173 4 Basis Document for Alternate

Shutdown Abnormal Operating

Procedure 2203.14, Revision 4, ANO

Unit 2

01/07/87 85E-00071-02 Calculation: Evaluation of Time

Available for Manual Initiation of

EFW following Loss of All_ Feedwater

L-------------------_---_--------_----------._--.------.----- - - - -__---__--__--------z

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ _ _ _ _ _ _ _

.

7

85E-0087-1 2 Safe Shutdown Capability Assessment

(ANO, Unit 2)-

02/11/86 85E-0122 0 Evaluation of'ANO Radio System

Suitability for Alternate Shutdown

l Communications

l B. Drawings - Mechanical

Date Number Rev. Title

01/17/86 M-202 50 Piping & Instrument' Diagram Main

Steam

01/29/87 M-204 Sht Piping & Instrument Diagram

3 of 4 10 Emergency Feedwater

M-204 Piping & Instrument Diagram

Sht 5 0 Emergency Feedwater Storage

01/28/87 M-206 Sht Piping & Instrument Diagram Steam

1 of 2 Peal Generator Secondary System

11/05/86 M-209 35 Piping & Instrument Diagram Cond'r.

Vacuum, Circ. Water & Intake l

Structure Equipment

03/02/87 M-210 44 Piping.& Instrument Diagram Service q

Water j

i

12/10/86 M-217 49 Piping & Instrument Diagram )

Emergency Diesel Generator & Fuel

Oil System

12/04/86 M-230 Sht Piping & Instrument Diagram Reactor

1 of 2 53 Cooling System

12/04/86 M-230 Sht Piping & Instrument Diagram Reactor

2 of 2 53 Cooling System

01/10/87 M-231 Sht Piping & Instrument Diagram Makeup

1 of 2 47 & Purification System

01/06/87 M-231 Sht Piping & Instrument Diagram Makeup.

2 of 2 7 & Purification System

12/13/86 M-232 35 Piping & Instrument Diagram Decay

Heat Removal System

- _ _ - _ _ _ - _ _ - _ _ - _ - _ _ - _ _ _ - _ __

--

-

i

)

l

l

8

1

i

i

11/24/86 M-263 Piping &. Instrument Diagram HVAC  ;

Sht 3 'O Auxiliary Building Miscellaneous  !

Rooms

01/06/87 M-2202'Sht. Piping & Instrument Diagram Main .i

2 of 2 39 Steam 1

01/12/87 M-2204 Sht Piping & Instrument Diagram ,

4 of 4 24 Emergency Feedwater

01/06/87 M-2206 Sht Piping & Instrument Diagram Steam

1 of 2 75 Generator Secondary System

l

l 05/21/87 M-2210 Sht Piping & Instrument Diagram Service l

l

1 of 3 32 Water System

10/18/87 M-2210 Sht Piping & Instrument Diagram Service

2 of 3 Water System

07/07/87 M-2210 Sht Piping & Instrument Diagram Service

3 of 3 36 Water System

01/17/87 M-2212 34 Piping & Instrument Diagram Makeup

Water Demineralization System j

l

03/04/87 M-2230 44 Piping & Instrument Diagram Reactor  !

Coolant System

i 01/15/87 M-2231 Sht Piping & Instrument Diagram

1 of 2 54 Chemical & Volume Control System

I

01/15/87 M-2231 41 Piping & Instrument Diagram Safety

Injection System j

01/06/86 M-2232 54 Piping & Instrument Diagram Safety

Injection System )

01/07/87 M-2236 52 Piping & Instrument Diagram

Containment Spray System

01/03/87 M-2263 1 Piping & Instrument Diagram Air

Flow Diagram HVAC Auxiliary

Building - Miscellaneous Rooms

C. Drawings - Electrical

Date Number Rev. Title

12/21/84 2A309-1 0 SWGR 2A3 '

12/21/84 2A309-2 0 AN02-4.16 KV Ground Fault Relays

l

_ _ _ _ - _ _ - -

-

i

  • 1

9

<-

12/21/84 2A310-1 0 AN02-4.16 KV SWGR Breaker 2A309  ;

12/21/84 2A408-1 0 AN02-4.16 KV SWGR Breaker 2A408  !

12/21/84 2A409-1 0 AN02-4.16 KV SWGR Breaker 2A409

12/21/84 2A409-2 0 AN02-4.16 KV Ground Fault Relays .

12/21/84 28512-1 0 AN02-480 Volt Load Center -

Coordination on Main Breaker 28512

12/21/84 2B612-1 0 AN02-480 Volt Load Center -

Coordination on Main Breaker 2B612

09/27/85 E2006 15 Low Voltage Safety Systems Power j

Supplies Single Line Diagram -l

11/18/84 2B521-2 0 AN02-480 Volt Load Center MCC

Breaker 2B521 J

11/18/84 28621-2 0 AN02-480 Volt Load Center MCC

Breaker 2B621

12/21/84 2001-1 0 AN02-125 VOC Breaker 72-0100

Coordination

12/21/84 2002-2 0 AN02-125 VOC Breaker 72-0211

Coordination

08/05/85 2RS1-1 1 AN02-120 VAC Panel 2RS 1

Coordination

08/05/85 2RS1-2 1 AN02-120 VAC Panel 2RS-1

Coordinatico

08/05/85 2RS2-1 1 AN02-120 VAC Panel 2RS-2

Coordination

08/05/85 2RS2-2 1 AN02-120 VAC Panel 2RS-2

Coordination

08/05/85 2RS3-1 1 AN02-120 VAC Panel 2RS-3

Coordination

08/05/85 2RS3-2 1 AN02-120 VAC Panel 2RS-3

Coordination

08/05/85 2RS4-1 1 AN02-120 VAC Panel 2RS-4

Coordination-

__ _ _- - _

.10 j

08/05/85 2RS4-2 1 AN02-120 VAC Panel 2RS-4

Coordination

12/29/86 E-2566' 4 . Schematic Diagram Pressurizer Vent

Valve

09/04/86 E-2302 Schematic Diagram Pressurizer

Sht 2 Po2 Relief Valves

09/04/86 E-2303 Schematic Diagram Pressurizer

Sh 1 Po2 Relief Valves

12/21/84 2001-0122-1 0 AN02-125 VOC Breaker 72-0122

12/21/84 2001-0133-1 0 AN02-125 VDC Breaker 72-0133

04/23/87 E-2891 31 Conduit & Tray Layout Containment

Penetration Area 24 Partial Plans

05/13/87 E-2867 58 Conduit & Tray Layout Containment

Auxiliary Building Area 24

03/20/85 E-2209 14 Schema' tic Diagram Shutdown Cooling .

Return Header Isolation Valve L

2CV5084-1 & 2CV5086-2

12/10/85 E-2252 6 Schematic Diagram Letdown

Containment Isolation Valve

2CV4823-2

l 09/04/86 E-2233 P1 Schematic Diagram Regenerative Heat

7

Exchanger Inlet 2CV4821-1

10/08/84 A308-1 0 ANO-1, 4.16 KV DG1 Breaker

.J

10/08/83 A309-1 0 ANO-1, 4.16 KV Breaker A309

10/08/84 A408-1 0 ANO-1, 4.16 KV DG2 Breaker 1

10/08/83 A409-1 0 ANO-1, 4.16 KV Breaker A409 .

!

09/07/84 A309-2 0 ANO-1, 4.16 KV Breaker A309 1

1

09/07/84 A409-2 0 AN0-1, 4.16 KV Breaker A409

11/20/84 BS12-1 1 ANO-1, 480 Volt Load Center BS

11/20/84 B612-1 1 ANO-1, 480 Volt Load-Center B6

10/26/84 RS-1 0 ANO-1, 120 VAC RPS & ESF Panel RS1

i

_ - - . . _ _ _ - -

11

10/26/84 RS-2 0 ANO-1, 120 VAC RPS & ESF~ Panel RS2

10/29/84 001-1 0 AND-1, 125 VDC Load Center D01

10/29/84 002-2 0 ANO-1, 125 VOC Load Center 002

'06/19/86 8532-2 0 ANO-1, 480 Volt MCC Breaker B532

Downstream Coordination

11/24/84 B614-2 0 ANO-1, 480 Volt MCC Breaker 8614

Downstream Coordination

11/04/86 E-1 15 Station Single Line Diagram

11/13/86 E-5 12 Single Line Meter & Relay Diagram

4160 Volt System Engineered.

Safeguard

11/03/86 E-8 12 Single Line Meter & Relay Diagram

480 Volt Load Centers Engineered-

Safeguard & Main Supply

'

09/17/85 E-9 22 Single Line Diagram 480 Volt Motor

Control Centers 871, B24, B72, B44

12/12/86 E-15 29 Single Line Diagram 480 Volt Motor

Control Centers B51 & B52

12/11/86 E-16 19 Single Line Diagram 480 Volt Motor

Control Centers 855 & B56

09/29/86 E-17 20 Single Line Meter & Replay Diagram

125 VDC System

01/25/87 E-18 Pul Single Line Diagram 480 Volt Mctor

Control Centers B61 & B62

12/12/86 E-19 .23 Single Line Diagram 480 Volt Motor

Control Centers B53 & B63

07/24/86 E-22 37 ENGINEERED SAFEGUARD & 125 Volt DC

Power Distribution Panels

12/05/86 E-24 3 Single Line Diagram 125 Volt.DC

Motor' Control Center D15 & D25

12/29/83 E-203 6 Schematic Diagram Pressurizer

Proportional Heater Control

04/20/75 M2012-14 12 Electrical Schematic Generator ,

Control Panel J

l

____ a

- _ _ _.

12

'10/01/86 E-667 43 Conduit & Tray Layout Auxiliary

Building Area 4 Plan Sh 1

09/23/86 E-667 6 Conduit & Tray Layout Auxiliary

Building Area 4 Plan Sh 2

03/09/87 E-667 9 Conduit & Tray Layout Auxiliary

Building Area 4 Plan Sh 3

12/29/86 E-667 10 Conduit & Tray Layout Auxiliary

Building Area 4 Plan Sh 4

,

03/13/86 E-661 42 Conduit & Tray Layout Auxiliary

'

Building Sh 1

03/05/87 E-258 0 Wiring' Block Diagram Emergency

Feedwater: Initiation & Control

(EFIC) Sh 1A

03/05/87 E-258 0 Wiring Block Diagram Emergency

Feedwater Initiation & Control

(EFIC) Sh 1B

,

09/04/86 E-84 3 Schematic Diagram Typical 480 Volt

Motor Control Centers FVR Starters,.

Interposing Relays Sh 5

01/10/87 E-199 P2

3 Schematic Diagram Reactor Coolant

System MOVs-

l 02/18/86 E-260 0 Wiring Block Diagram Reactor

Nuclear Instrumentation Source

Range Detector Sh 6

02/18/86 E-260 0 Wiring Block Diagram Reactor

Nuclear Instrumentation Source

Range Detector Sh 7

01/12/87 E-262 3 Wiring Block Diagram Plant

Auxiliary Control System Reactor

Coolant Sh 1A

09/03/86 E-331 Po2 Schematic Diagram Miscellaneous

Instrumentation Shs 40 & 41

05/04/82 E-2232 P131 Schematic Diagram Letdown Line Stop~

MOV 2CV4820-2

10/14/82 E-2703 P121 Schematic Diagram Instrumentation ,

Sh 1 Pressurizer Pressure Protection-

1

,

13'

i

10/10/8a E-2703- 13 Schematic Diagram Instrumentation

Sh 2 Pressurizer Pressure Protection

l \

l 'l

i

1

l

1

'

.

!

l

'l

!

l

,

i

3

l

l

l

l

1

J

!

,

.

m_. ___-_ --__.____-.-_____m_m._m___ ,