ML20154A987
| ML20154A987 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 09/08/1988 |
| From: | Holahan G Office of Nuclear Reactor Regulation |
| To: | Sylvia B DETROIT EDISON CO. |
| Shared Package | |
| ML20154A993 | List: |
| References | |
| NUDOCS 8809130165 | |
| Download: ML20154A987 (6) | |
See also: IR 05000341/1988020
Text
y
_ - - - - - _ - _ - - - - - - - _ _
' %. .ea
+
[1
.
NUCLEAR REGULATORY COMMISSION
+
o,
UNITED STATES
')
. v.
s,
l
wassimo ton. o. c. mis
s' ...../
September 8, 1988
Docket No. 50-341
Mr. B. Ralph Sylvia, Group Vice President
Nuclear Operations
The Detroit Edison Company
6400 horth Dixie Highway
Newport, MI 48166
Dear Mr. Sylvia:
SUBJECT:
EMERGEhCY OPERATING PROCEDURES INSPECTION
(INSPECTION Rn0RT 50-341/88200)
This letter forwards the report for the emergency operating procedure (EOP)
inspection performed by an NRC inspection team at the Fermi 2 nuclear power
plant during the period of July 5 through July 14, 1968. Members of the NRC
Office of Nuclear Reactor Regulation, Region !!!, and contractors conducted
this inspection. At the coriclusion of the inspection, the team discussed the
findings with you and the members of your staff identified in Appendix A of the
enclosed inspection report.
The purpose of the inspection was to verify that your emergency operating
procecures were technically correct; that their specified actions could be
physically accomplished using existing equipment, controls, and instrumenta-
tion; and that the available procedures coulo be correctly carried out by the
plant staff.
The inspection effort involved a review of your program for E0P developeent, a
valtoation and verification of issued E0Ps and an evaluation of your training
activities for E0Ps.
The inspection team accomplished these tasks through use
of your site specific simulator, walk-throughs of E0Ps with operators,
interviews with key plant staff and review of E0Ps and supporting
documentation.
Two documents are enclosed with this letter: the Executive Sumary of this
i
inspection provides an overview of the inspection team's findings in each area
reviewed; the enclosed inspection report provides a more detailed explanation
of the team's findings. Although no response is required to this letter, the
report includes findings that may result in enforcement action, which would be
the subject of separate corresponcence from the hRC Region !!! Office.
L
Overall, the team concluded that the craft E0Ps which have been prepared for
Fermi 2 represent a significant improvement over the procedures that were in
use 41 the tine of the inspection. Numerous deficiencies and potential areas
for improvement were noted in the presently useo procedures.
The more
lh
I
0
!
S809130165 88090s
DR
ADOCK 05000341
1
. -
- -
.
-
.
__
____
_ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _
_
_-
e
I
Mr. 8. Ralph Sylvia
02
September 8, 1988
significant items, such as diversity of methods for containment venting;
overpressure and overtemperature strategies for protection of the containment
and standby gas treatment system; the staging, inventory, and preventive
maintenance progran for E0P-related equipment; and enhancements to your formal
,
procedure place keeping trethods, should be considered on an expedited basis,
It: accordance with 10 CFR 2.790(a), a copy of this letter and the enclosure
a
j
vill be placed in the hRC Public Document Room.
I
Should you have any questions ccncerning this inspection, please contact me or
!
Mr. Ralph Architzel (302-492-0991).
Sincerely,
1
l
Y
Gary M. Holaha"n, Acting Director
Division of Reactor Projects !!!,
.
IV, V, and Special Frojects
Office of Nuclear Reactor Regulation
Enclosures:
1.
Executive Summary
2.
hRC Inspection Report 5C-333/88200
cc w/ enclosures: See next page
1
,
i
1
!
.I
l
!
I
l
!
I
j
l
!
l
1
!
I
1
._ .
- - -
.
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
. _ _
s
1
Mr. B. Ralph Sylvia
-3-
September 8. 1988
'
cc w/ enclosure:
Mr. Ronald C. Callen
Ms. Lynn Goodman
Adv. Plannine Review Section
Supervisor - Licensing
1
l
MichiganPublicServiceCommission
Detroit Edison Company
6545 Mercantile Way
Fermi Unit 2
P. O. Box 30221
6400 North Dixie Highway
Lansing, Michigan 48909
Newport, Michigan 48166
Joha Flynn Esq.
Senior Attorney
1100 Circle 75 Parkway
Detroit Edison Company
Atlanta, Georgia 30339
2000 Second Avenue
Detroit, Michigan 48226
,
Nuclear Facilities and Environmental
Monitoring Section Office
'
Division of Radiological Health
P. O. Fox 30035
Lansing Michigan 48909
Mr. Thomas Randazzo
Director, Regulatory Affairs
Detroit Edison Company
Femi Unit 2
6400 North Dixie Highway
Newpert, Michigan 48166
Mr. Walt Rogers
U.S. Nuclear Regulatury Comission
Resident Inspector's Office
6450 W. Dixie Highway
hewport, Michigan 48166
Monroe County Office of Civil
Preparedness
963 South Raisinville
Monroe, Michigan 48161
Regional Administrator, Region !!!
,
U.S. Nuclear Regulatory Comissiori
799 Roosevelt Road
Glen Ellyn, Illinois 60137
___
_ _
_ _
_ _ _ ____
__ ______ _____ ___
. _-_____
e
s
i
Mr. B0 Ralph Sylvia
4
September 8, 1988
i
!
l
Distribution:
(w/ encl)
N 50-341'i
DRIS R/F
RSIB R/F
.
I
1.PDR
BEGrines, NRR
CJHaugney, NRR
i
JEKonklin, NRR
'
RArchitzel, NRR
InspectionTeam(5)
!
l
DCrutchfield, NRR
TQuay,NRR
,
MVirgilio, NRR
!
TMurley, NRR
i
JSniezek, NRR
l
SRI, Fermi 0, RI!!
RCooper, RI!!
ACRS(3)
i
OGC (3)
'
Regional Administrators
[
Regional Div. Directors
IS Distribution
I
i
i
!
!
!
!
!
!
r
I
kfO
h
(_
..
i
. . . . . . . . . . . . . . . , . . .f.JD TMWy
OFC
- RSIBiDRI5:hRR
- R5IB:DRIS:NRR :R518:TipWER : AD:DRI5:h
1(A)AD:DRSP35
- LA
-
...........
.............................
.............................
N
- GHolahan
F
NAME
- RArchitzel/vj
- JKo
- CHaughney
'BGrimes
j :MYirgilio
hkTE
Ob)[f)b8
b8h)bb
bS)Sf)b$
bb)hh)hb
bb)hihbb
k, k[88
..
,
!
i
t
-
I
i
l
L
i
i
-
- -
-
-
-
.
- _ _ _ _ - _ _ _ _ _ _ - _ - _ - - _ _ - _ _ _ _ -
.O
4
EXECUTIVE SUMMARY
INSPECTION REPORT 50-341/88200
FERMI 2 NUCLEAR POWER PLANT
'
t
A team of NRC inspectors and contractor personnel inspected the Femi 2
Nuclear Power Plant to evaluate the licensee's program for development and
'
implementation of emergency operating procedures (EOPs) as required by Generic
Letter 82-33. The inspection team performed this evaluation by:
Reviewing the E0P development process as described in the procedure
generation package submitted to the NRC.
l
Comparing the emergency procedure guidelines to the E0Ps and deviation
'
documentation.
Validating the E0Ps using the site specific simulator and through plant
l
walkdowns of E0P appendices.
.
Independently verifying selected E0Ps and appendices for conformance with
the procedure generation package.
Reviewing operator requalification training on the E0Ps.
Fermi 2 was in the final stages of implementing symptomatic-based E0Ps based
,
on Revision 4 of the BWR Owners' Group Emergency Procedure Guidelines.
The
l
team thus inspected draft procedures that were nearly in final form and that
'
had been mostly verified, validated and for which the operator training had
!
been almost completed. A significant conclusion of the team was that the draft
procedures represented an enhanced method to control the plant under emergency
operations as compared with the approved E0Ps. Nonetheless, several problems
-
were identified relative to the draft E0Ps and the implementation process.
Some of these problems are highlighted below; more details are provided in the
i
inspection report. The team did conclude that the draft E0Ps could be bsed to
l
adequately control emergency operating conditions and that early implementation
of the revised E0Ps would be a safety enhancement.
l
The team noted that E0P provisions for containment venting were not
comprehensive.
For example, the licensee had not evaluated all possible paths
l
to vent the contairment or assessed the integrity of the standby gas treatment
!
. systert under the planned release paths.
,
The simulator training that was conducted was not integrated and only mercised
!
mild transients. The licensee stated the reason for the lack of chalienge
'
'
during simulator sessions was simulator limitations in modelling complex
transients. The team did observe excellent control of the simulator during the
conduct of th ee scenarios developed for this inspection.
Several problems were noted with plant material conditions during plant
,
"
walk-downs. These problems included emergency access paths that were blocked,
E0P equipment boxes that were poorly configured for equipment removal, and the
l
need to dress-out for normal access to general areas of the reactor building
due to recent leaks in the reactor water cleanup system.
The team concluded
,
l
,
,
, - - - -
r,
,,-...,7-~~-,-e- , -
,n-._
. ,-- - , - - - - - - ~ ,
.
,-_,--,,
--
--
- - - - - , , - - - -
- - - - - , - - - - - - . - - - - - - - - -
- - - - - - - - - - - - - - - -
- - - - - - - - - - - -
- - - - - -
--
- - - - - - - -
-
- - - - - - - - - - - - - - - - - . - - -
,
1
,
s
i
i
i
that certain material conditions should be evaluated and addressed. These
included the use of tygon tubing to vent the potentially hot and high pressure
,
i
fluid for the control rod drives, the use in the E0Ps of normal power supplies,
'
j
and the lack of inventories, prestaging, and planned preventive maintenance of
E0P tools and equipment.
The team identified a significant deviation from the Owners' Group Guidelines
'
.
in the draft E0Ps that had not been addressed by the licensee.
The E0P entry
)
conditions used technical specification allowable values, versus the actual
i
trip setpoints as specified by the Owner's Group. The licensee revised the
E0Ps during the inspection to use trip setpoints for entry conditions, where
,
[
,
conservative.
,
r
i
In the human-factors area, the team noted that some calculations required
i
during performance of the E0Ps were difficult to perform. There was a marked
l
need to define and enhance procedure place-keeping methods.
The lack of flow
!
charts was considered detrimental.
Such charts would represent a significant
C
j
place-keeping enhancement.
A general revision to the E0P Writer's Guide was
l
considered necessary.
In addition;the procedures needed a general editing
i
'
review to be sure the Writer's Guide editorial directions were followed and the
logic statements were properly formulated,
j
I
The team noted several strengths during the inspection. Overall, the quality,
i
legibility and readability of the draft E0Ps was very good. The licensee had
f
developed an excellent system to control jumpers and safety system defeats.
i
The shif t crew assigned to perform simulated E0P execises handled the emergency
-
operations in an accomplished, professional canner.
(
!
1
l
2
.
$'
!
f
i
t
i
,
i
i
)
i
l
l
l
4
,
t
[
!
I
,
I
!
ES-?
!
I
!
4
,