Deficiency Rept Re Bolts Installed on Seismic Ductwork W/O ASTM A-307 Grade a Marking Requirement.Initially Reported on 840105.Item Evaluated & Considered Not Reportable Per 10CFR50.55(e) & Part 21
ML20079D973
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 01/09/1984
From: Chiangi N
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
MQAH-84-04, MQAH-84-4, NUDOCS 8401170006
Download: ML20079D973 (1)


Text

_.

Cp&L

~

I Carolina Power & Light Company .

P. 0.' Box 165,^New Hill, North Carolina 27562 January 9, 1984 FILE: SH N-2/18 MQAH 84-04 Item 146-Mr. James P. O'Reilly

, United States Nuclear Regulatory Commission Region II j -101 Marietta Street, Northwest Atlanta, Georgia 30303 SHEARON JARRIS NUCLFAR POWER PLANT, UNIT NO. 1 '

-DOCKET NO. 50-400 UNMARKED BOLTS

Dear Mr. O'Reilly:

This is to confirm the January 5, 1984 telephone conversation between

- Mr. N. J. Chiangi (P&L) and Mr. A. Hardin (NRC) . Mr. Hardin was informed that the September 23, 1983 potentially reportable item, pertaining to bolts procured under site contract, received and installed on seismic ductwork without the ASTM A-307 Grade A marking requirement, has been evaluated and considered not to be reportable per the provisions of 10CFR50.55(e) and 10CFR, Part 21.

Thank you for your. consideration in this matter.

NJC/mt- .Yours very truly, L

, cc: Mr. R. C.-DeYoung Mr. G. Maxwell Mr. R. L. Prevatte O. ,

N. J. hiangi - Manager Quality Assurance / Quality Control Harris Plant

+