ML20213F810

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept,Item 233,re Electrical Separation. Initially Reported on 860822.Addl Time Necessary to Submit Final Rept.Final Rept Expected on 861210
ML20213F810
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 11/10/1986
From: Watson R
CAROLINA POWER & LIGHT CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
CON-NRC-499 233, HO-860372-(), HO-860372-(0), NUDOCS 8611170192
Download: ML20213F810 (1)


Text

CP&L Carolina Power &,Lyht Company a1: 7g

~.u.

~

HARRIS NUCLEAR PROJECT P.O. Box 165 ggy New Hill, NC 27562 File Number:

S9F/10-13510E Letter Number: HO-860372 (0)

Dr. J. Nelson Crace NRC-499 United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, Georgia 30323 CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT 1986-900,000 KW - UNIT 1 ELECTRICAL SEPARATION ITEM 233

Dear Dr. Grace:

On August 22, 1986, CP&L notified the NRC (Mr. P. Fredrickson) of a reportable item per the provisions of 10CFR50.55(e) on the subject of Electrical Separation. An interim report was submitted to the NRC on September 19, 1986, which described CP&L's planned action to resolve this matter. A projected date of November 10, 1986, for completing the described actions was forwarded to the NRC by letter (HO-860356 (0)) dated October 3,1986.

This letter is to inform you that additional time is required to submit the final report since CP&L is currently in the process of verifying the completed corrective action. It is currently projected that a final report will be submitted by December 10, 1986.

Thank you for your consideration in this matter.

Yours very truly, Zaa/M co qoo

/

R. A. Watson Vice President Harris Nuclear Project MW/Imj cc: Messrs.