Monthly Operating Rept for Jul 1998 for Shearon Harris Nuclear Plant.W/980811 Ltr
ML18016A507
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 07/31/1998
From: Donahue J, Shannon Rogers
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
HNP-98-114, NUDOCS 9808240106
Download: ML18016A507 (7)


Text

CATEGORY 1 REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

DOCKET FACIL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina 05000400 AUTH.NAME .; ~ AUTHOR AFFILIATION ROGERS,S. ,Carolina Power & Light Co.

DONAHUE,J.W. Carolina Power & Light Co.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operatin re t for Jul 1998 for Shearon Harris Nuclear Plan .W/98 r ~

A DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs) T NOTES:Application for permit renewal filed. 05000406K RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-1 PD 1 1 FLANDERS,S 1 1 INTERNAL: ACRS AEOD/SPD/RRAB 1 1 E CENTE OC/DBA/PAD 1 1 EXTERNAL: LITCO BRYCE,J H NOAC 1 1 NRC PDR D

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRZBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 10 ENCL 10

Carolina Power & Ught Campany Harris Nuclear Plant PO Box 165 New Hill NC 27562 AUG 11 1998 United States Nuclear Regulatory Commission Serial: HNP-98-114 ATTENTION: Document Control Desk Washington, DC 20555 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50-400/LICENSE NO. NPF-63 MONTHLYOPERATING REPORT

Dear Sir or Madam:

In accordance with Carolina Power & Light Company's Harris Nuclear Plant Technical Specification 6.9.1.5, the report of operating statistics and shutdown experience for the month of July 1998 is provided.

Sincerely, J. W. Donahue Director of Site Operations t Harris Plant )

SGR Enclosure c: Mr. J. B. Brady - NRC Senior Resident Inspector Mr. S. C. Flanders - NRC Project Manager Mr. L. A. Reyes - NRC Regional Administrator 980824Qi06 'st8073i PDR ADQGK 05000400 State Road 1138 New Hill NC

v ~

United States Nuclear Regu atory Commission Page 2 bc: Mr. T. C. Bell Mr. B. H. Clark Mr. G. W. Davis Ms. D. J. Hamilton Mr. W. J. Hindman Mr. W. D. Johnson Ms. W. C. Langston (PE8cRAS File)

Mr. R. D. Martin Mr. W. S. Orser Ms. S. G. Rogers Mr. J. Scarola Mr. W. G. Wendland (American Nuclear Insurers)

Nuclear Records Licensing File

Enclosure to Serial: HNP-98-114 Sheet 2 of 2 CP&L CO. PLANT PERFORMANCE DATA SYSTEM PAGE 1 RUN DATE 08/05/98 APPENDIX B AVERAGE DAILY POWER LEVEL RPD39-000 RUN TIME 14:18:54 HARRIS UNIT 1 DOCKET NO. 050-400 COMPLETED BY SHEILA ROGERS TELEPHONE (919)362-2573 JULY 1998 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET) (MWE-NET) 849 17 849 854 18 852 854 19 849 849 20 848 852 21 847 855 22 843 854 23 843 848 848 847 25 849 10 850 26 852 855 27 850 12 857 28 851 858 29 846 856 30 846 15 855 849 16 849

J

~ ~

~

~

Enclosure to Serial HNP-98-114 Sheet 1 of 2 CP&L CO. PLANT PERFORMANCE DATA SYSTEM PAGE 1 RUN DATE 08/05/98 OPERATING DATA REPORT RPD36-000 RUN TIME 14:18:55 HARRIS UNIT 1 DOCKET NO. 050-400 COMPLETED BY SHEILA ROGERS OPERATING STATUS TELEPHONE (919)362-2573

1. UNIT NAME: HARRIS UNIT 1
2. REPORTING PERIOD: JULY 98
3. LICENSED THERMAL POWER (MWT): 2775
4. NAMEPLATE RATING (GROSS MWE): 950.9
5. DESIGN ELECTRICAL RATZNG (NET MWE): 900.0
6. MAX DEPENDABLE CAPACITY (GROSS MWE): 920.0
7. MAX DEPENDABLE CAPACITY (NET MWE): 860.0
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED 1F ANY (NET MWE):
10. REASONS FOR RESTRICTION IF ANY:

THIS YR TO CUMUL MONTH DATE ATIVE

11. HOURS IN REPORTING PERIOD 744.00 5087.00 98616.00
12. NUMBER OF HOURS REACTOR CRITICAL 744.00 5087.00 83396.71
13. REACTOR RESERVE SHUTDOWN HRS .00 .00 .00
14. HOURS GENERATOR ON LINE 744.00 5087.00 82580.54
15. UNIT RESERVE SHUTDOWN HOURS .00 .00 .00
16. GROSS THERMAL ENERGY GEN. (MWH) 2059984.62 14029329.96 221864107.14
17. GROSS ELEC. ENERGY GEN (MWH) 673685.00 4664786.00 73846590.00
18. NET ELEC. ENERGY GENERATED (MWH) 632653.00 4381956.00 68907261.00
19. UNIT SERVICE FACTOR 100.00 100.00 83.74
20. UNIT AVAILABILITYFACTOR 100.00 100.00 83.74
21. UNIT CAP. FACTOR (USING MDC NET) 98.88 100.16 81.25
22. UNIT CAP. FACTOR (USING DER NET) 94.48 95.71 77.64
23. UNIT FORCED OUTAGE RATE .00 .00 3.20
24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

Plant Refueling Outage number 8 is planned to begin October 24, 1998 and is scheduled for a duration of 34 days.

25. ZF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
26. UNITS ZN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCZAL OPERATION 1.16 - 9