05/21/2007 Summary of Clarification Telephone Call with Progress Energy Regarding Pilot Plant (Shearon Harris) Transition to National Fire Protection Association Standard 805
ML071650065
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 07/27/2007
From: Lain P W
NRC/NRR/ADES/DRA/FPB
To: Weerakkody S D
NRC/NRR/ADES/DRA/FPB
Lain P, NRR/DRA, 415-2346
Shared Package
ML071650197 List:
References
Download: ML071650065 (10)


Text

July 27, 2007MEMORANDUM TO: Sunil D. Weerakkody, ChiefFire Protection Branch Division of Risk Assessment Office of Nuclear Reactor RegulationFROM: Paul W. Lain, Senior Fire Protection Engineer /RA/Fire Protection Branch Division of Risk Assessment Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF MAY 21, 2007, CLARIFICATION TELEPHONE CALLREGARDING PILOT PLANT (SHEARON HARRIS) TRANSITION TO NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805On May 21, 2007, the U.S. Nuclear Regulatory Commission (NRC) staff from Headquartersparticipated in a telephone call with Progress Energy to discuss Shearon Harris Nuclear Power Plant transition to the National Fire Protection Association Standard NFPA 805. The subjects of the discussion were the analyses, procedures, and methodology for performing fire safe shutdown analyses, circuit analysis, non-power operational modes analysis, and NFPA 805 Chapter 4 Fire Area Transitions.Progress Energy recorded the NRC comments, answered some of them, and retained theremaining ones for subsequent disposition. All of the comments will be discussed at the next observation visit and will be documented in the associated trip report.Enclosed are a list of the teleconference participants (Enclosure 1) and the NRC staffclarification questions (Enclosure 2). The publically available documents discussed during the telephone call are available in the Agencywide Documents Access and Management System (ADAMS) Accession No. ML071650197.

Enclosures:

As statedCONTACT: Paul Lain, NRR/DRA 301-415-2346 MEMORANDUM TO: Sunil D. Weerakkody, ChiefFire Protection Branch Division of Risk Assessment Office of Nuclear Reactor RegulationFROM: Paul W. Lain, Senior Fire Protection Engineer Fire Protection Branch Division of Risk Assessment Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF MAY 21, 2007, CLARIFICATION TELEPHONE CALLREGARDING PILOT PLANT (SHEARON HARRIS) TRANSITION TO NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805On May 21, 2007, the U.S. Nuclear Regulatory Commission (NRC) staff from Headquartersparticipated in a telephone call with Progress Energy to discuss Shearon Harris Nuclear Power Plant transition to the National Fire Protection Association Standard NFPA 805. The subjects of the discussion were the analyses, procedures, and methodology for performing fire safe shutdown analyses, circuit analysis, non-power operational modes analysis, and NFPA 805 Chapter 4 Fire Area Transitions.Progress Energy recorded the NRC comments, answered some of them, and retained theremaining ones for subsequent disposition. All of the comments will be discussed at the next observation visit and will be documented in the associated trip report.Enclosed are a list of the teleconference participants (Enclosure 1) and the NRC staffclarification questions (Enclosure 2). The publically available documents discussed during the telephone call are available in the Agencywide Documents Access and Management System (ADAMS) Accession No. ML071650197.

Enclosures:

As statedDISTRIBUTION: DRA R/FPLainTDinhEMcCannSLaurRGallucciJSHyslopHBarrettSWeerakkody JCircleSWilliamsCPayneWRogers

ADAMS Accession # (Package): ML071650197 ADAMS Accession # (Cover memo with encl.): ML071650065 ADAMS Accession # (FPIP-0126): ML071630512 ADAMS Accession # (FPIP-0106): ML071630505 ADAMS Accession # (EGR-NGGC-0102): ML071630478 ADAMS Accession # (Table B-2) : ML 071630517 ADAMS Accession # (FPIP-0127): ML071210335 NRC-001 OFFICEAFPB/FPEBC:AFPB/FPENAMEPLainSWeerakoddyDATE7/ 27 /077/ 27 /07OFFICIAL RECORD COPY CLARIFICATION TELEPHONE CALL REGARDING PILOT PLANT (SHEARON HARRIS) TRANSITION TO NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805List of ParticipantsU.S. Nuclear Regulatory Commission StaffE. McCannP. Lain R. Gallucci T. Dinh H. Barrett JS. HyslopPacific Northwest National LaboratoryT. Blackburn*

Progress EnergyR. Rishel*T. Maness*

R. Rhodes*

S. Hardy*

J. Ertman**participated via telephoneENCLOSURE 1 NRC Questions for the May 21 st Clarification Conference CallFPIP-0126 (Non-Power Operational Modes Transition Review)General question: Assuming OMP-003 is the governing procedure for Outage RiskManagement during Shutdown at Harris, how is this modified to include the effects of fire?

Should this be discussed in detail in FPIP-0126, assuming it is not done so specifically in OMP-003? If this is done specifically in OMP-003, we would need to review. (RG)3.6: Consider using definitions from ASME RA-Sb-2005 (RG) 9.6.1: Why is the "pinch point" search limited only to areas that might damage ALL creditedpaths? Should not damage to ANY credited path be identified as well, since outage management "risk" usually considers various degrees of redundancy loss, not just total loss?

(RG)9.6.6: Related to the above, this seems to indicate that compliance strategies will only beinstituted when ALL redundancy is lost, not just partial loss. Plant conditions can be >Green with only partial loss, and do not these usually require some sort of compensatory measures?

(RG) How is "increased potential for fire" addressed in OMP-003? (RG)

Based on the above, we need to review OMP-003, at least the outage management "risk"evaluation portion. (RG)9.7.3 Document outage activities which may lead to failure of KSF, including length of timecondition in effect, type of outage activity, amount of combustibles added (if appropriate), etc.

For example, bringing in a load of combustibles for some outage maintenance activity would include documentation on the amount of combustibles, length of time they were there, type of combustible, etc. (JSH)FPIP-0106 (Validate Fire Area SSD Strategies)3.1: Consider using definitions from ASME RA-Sb-2005 (RG)3.13: Recovery action definition: This definition identifies a recovery action as an action takenaway from the primary control station, where the primary control station is not necessarily in the control room. If this primary control station is outside the control room due to fire damage, why shouldn't an action at this primary control station be considered a recovery action? (JSH)9.1.7: Independent events: An earthquake inducing a fire is accounted for in fire PRA (i.e. theStandard) as well as licensing basis (i.e. SSD earthquake hose stations). Don't see why itshould be excluded here. (JSH)9.1.10: Why the single spurious restriction? Is not the purpose of transitioning to NFPA 805the establishment of a new licensing basis that includes multiple spurious? [Since this ENCLOSURE 2 2"deficiency" is rectified in Section 9.6, consider mentioning that here.] (RG)9.1.12: Statement made that "consideration should also be given to the possibility that totalfailure of the electrical component may not be the worst case failure." Does this mean that the failure mode of spurious operation will be taken for the analysis, if it is the worst case failure?

(JSH)9.2: According to 9.2, a manual action is a sufficient strategy for being the sole mitigationmeans for safe shutdown. 9.2.9 says that "Recent NRC positions on manual actions shall be considered when evaluating......" Shouldn't it say that "Rec ent NRC positions on manualactions shall be followed when evaluating....... (JSH)9.2: Saw no discussion about red box vs. blue box. Section 9.2 should go into the colored boxthat represents the licensing basis. (JSH)9.2.9: The NRC references for manual actions need to be updated to include NUREG-1852. Inaddition, manual action feasibility AND RELIABILITY must be addressed. Likewise, referenced EGR-NGGC-0102 may need updating to the latest NRC guidance on manual actions.

(RG)9.3: Again, multiple and potentially concurrent spurious, not just single and only sequential,should be considered. [Since this "deficiency" is rectified in Section 9.6, consider mentioningthat here.] (RG)9.6: Is intercable multiple spurious restricted to two components while intracable has no suchrestriction? What is the basis - RIS 2004-003, Rev. 1? Presumably, this restriction does NOT carry over into the Fire PSA. (RG)EGR-NGGC-0102 (SSD/FP Review)9.2.1, Note: The appropriate reference for manual actions taken as compensatory is RIS 2006-10. (RG)Attachment 3: This needs to be updated to the latest NRC guidance, including NUREG-1852(draft for review in August 2006, final to be issued soon) and RIS 2006-10. Also, both feasibility AND RELIABILITY need to be considered. (RG)Att. 3, 2.1: Historically, manual actions have never been part of III.G.1 compliance (ADAMS #ML050140123, below). Change this statement. (RG)It was stated that in fire areas for which alternative safe shutdown has not been provided, anexemption for Section III.G.2. of Appendix R is required if the separation features of Section III.G.2 are not provided. This statement was challenged with the line of reasoning that if SectionIII.G.1.a. of Appendix' R is satisfied,Section III.G.2 need not be satisfied. ELD [now OGC]provided the following resolution to this question: Interpretation Three of Appendix R (which defines the term "free of fire damage" in Section III.G.1.a) was provided to clarify SectionIII.G.1(a), during the exemption process, for licensees attempting to Justify the lack of I1I.G.2.

separation features for redundant trains within a single fire area. It was never intended that "other methods proposed by licensees" would be reviewed and approved at the Appendix R validation inspection.

3Att. 3, 4.2: Brigade members may NOT be credited later in the timeline unless all Brigade dutieshave been completed and the Brigade members have replacements on the Brigade, thereby freeing them for only manual action operations in case of subsequent fire (i.e., they would no longer be considered Brigade members at that time - no collateral duties). (RG)Att. 3, Table 4-1: References to "within/after the first hour or before/after the fire isextinguished" should include the caveat "whichever is later." (RG)Att. 3, 4.7: This should also include intermittent communication, or communication after anaction is completed to verify its completion. The communication need not be "continuous" only.

(RG)Att. 3, Table 5-1: While it is true that the likelihood of two spurious FOR THE SAME CABLETYPE AND FIRE SIZE is less than that for one, the likelihood for multiples is not necessarily "low." The distinction between priority Medium and Low with regard to spurious should be based on the likelihoods of the specific types of spurious, not just the number. E.g., one spurious in a conduited cable may be less likely than two in a non-conduited cable (0.15 vs.

0.36, without CPT, as per NUREG/CR-6850, Table 10-2 or 10-4, M/C Intracable). (RG)Att. 3, 5.3: Why are multiple spurious "not expected to occur concurrently unless...?" Sinceeach circuit tends to affect a different component, would not fire-induced failures in "circuits" (plural) normally be expected to affect multiple components? (RG)Att. 3, 5.3.2, Event Timeline: Tsp can occur before Tal or may actually constitute Tal. Likewise,Tglst can occur before Tor. Are these, as well as other possible permutations considered?

(RG)Att. 3, 5.3.2: "The deter mination that the time to perform an operator action is acceptable will bebased on successfully reaching Tgr prior to reaching Tun." This should be conditioned on inclusion of uncertainties, etc., in the timeline. such that acceptability includes an appropriate time margin between Tgr and Tun, not just that Tgr < Tun. (RG)Attachment 4: This needs to address considerations beyond those of RIS 2004-03, Rev. 0 (and even beyond Rev. 1), since the RIS is only inspection guidance and not limiting.

NUREG/CR-6850 would be a better governing document. It also needs updating to reflect caveated NRC endorsement of NEI 00-01. (RG)Table B-2 (Nuclear Safety Capability Assessment)Why is this Table keyed to NEI 00-01 instead of NEI 04-02, or some other National FireProtection Association Standard 805(NFPA-805)-related guidance? (RG)3.5.1.1: The risk-informed inspection process will focus NOT ONLY on failures with relativelyhigh probabilities, BUT ALSO on failures with special consequences, even if low probability, such as ISLOCA via high/low-pressure interface spurious opening. (RG)3.5.1.5[A]: The multiple spurious review should not be restricted to the guidelines of RIS 2004-03, but should include considerations from NUREG/CR-6850. (RG) 43.5.1.5[C]: Same comment as above [A]. (RG)Table B-3 (Fire Zone 12-A-BAL)Since it references CMEB 9.5-1, Section C.5.c as the pre-transition regulatory basis and NFPA805 Section 4.2.3.2 as the post-transition regulatory basis, it appears that Fire Area 12-A-BAL is transitioning from an alternative shutdown area to the NFPA 805 equivalent of a III.G.1 area. Is this a correct interpretation? (PF)It appears that the concept of the section on performance goals is to discuss specific systemsbeing credited to accomplish a performance goal when there is a choice of systems that could be used. An example of this is using the normal charging path for RCS inventory control. The table does not mention equipment used to accomplish a function when there is only one way of accomplishing the function. For example, RCS pressure boundary isolation, which is a sub-goal of inventory control is not mentioned because there it is not a matter of choice of systems, but rather just a function that must be accomplished. From the other hand, RCP seal integrity is a sub-goal of inventory control, where there is a choice of methods to use, namely seal injection or thermal barrier cooling, but these are not mentioned. So please clarify the underlying principle which determines the level of detail needed for the B-3 table. In this example if one wanted to get this kind of detail where will it reside in the documentation?

PF)NEI guidance document for the B-3 table has a column headed exemptions/deviations, but theexample does not appear to have such a column. The exemption/deviation column appears to be desirable from the viewpoint of reviewing a transition submittal and as program record. Is the licensing action section intended to be a substitute for the exemptions column? (PF)Performance Goal Section: It appears that there is very little equipment that can be damagedin fire area 12-A-BAL because virtually every function lists two trains in the method of accomplishment column. Is this a correct interpretation? When the table says CSIP A or CSIP B is the method does that mean that both trains are analyzed to be undamaged and the procedures give the operator a choice of which one to use? (PF)The B-3 table does not discuss area wide automatic suppression or detection in terms of arequirement for the area. Does this information reside in another part of the documentation?

(PF)The B-3 table for fire area 12-A-CR, control room, does not list a post-transition regulatorybasis. Is this just an oversight? (PF)* The questions by Paul Fillion (PF) listed above pertain to the April 19, 2007, clarificationtelephone call (ADAMS Accession No. ML071590154). Table B-3 is withheld from public availability under 10 CFR 2.390(d)(1) as Sensitive Unclassified Non-Safeguards Information.

5Clarification questions by Edward McCannProcedureSectionCommentEGR-NGGC-0102GeneralManual actions to be in accordance with NUREG 18529.2.5.1This section stated "These coordination studies analyzed thelargest feeder protective device on each common power supply. Once coordination of this feeder with the upstream protective device(s) was established, it was assumed that all other feeder protective devices on the same common power supply were coordinated." How do you know that the other breaker coordination curves all have the same shape, coordination curves may not be similar and one would not know if one does not check it?GeneralThe idea that III.G.1 compliance means "free of fire effects" istoo simplistic and leads to misconceptions.

For III.G.1 thereare two alternative ways to be free of fire effects and that is either from the Control Room or at the Emergency Control Stations. Being free of fire effects at the emergency control station, which is a dedicated (shutdown panels) or alternate (manual actions) method to shutdown, III.G.3 and III.L applysince the provisions III.G.2 could not be satisfied. If III.G.2 could have been satisfied, one would be free of fire effects from the control room.Attachment 3Section 3.0Item 3: NRC will not revise Appendix R or NUREG 800 formanual actions.General Will concurrent or in rapid succession multiple spuriousoperations be analyzed during the transition to NFPA 805? Attachment 4Section 2.0*Make definitions in accordance with RG 1.189 Rev 1.

  • Required safe shutdown circuits definition: RG 1.189uses words like "required to operate" or "systemsrequired to achieve and maintain post-fire safe-shutdown conditions" rather than credited. May want to change to: "circuits that support a component/system that is required to operate for safe shutdown after a fire" or something similar.
  • Ensure other procedures like FPIP-0104 and 0105 usesimilar definitions.Attachment 4Section 3.3Item 3 needs to be updated for NEI 00-01 NRC approval.Attachment 4Section 3.3Will thermoset intercable faults be analyzed during thetransition to NFPA 805?

6Attachment 4Section 5.3*This criteria uses "unrecoverable plant condition" as acondition to follow to incorporate new FICF while Appendix R uses III.L requirements. Why is this discrepancy acceptable?

  • Will multiple concurrent spurious operations beanalyzed during the transition to NFPA 805?Attachment 4Table 1*Item 1: Open circuits can cause spurious operationsand these will in general not clear without an action. How are you capturing these spurious operations?
  • Item 4: Will three phase proper polarity faults forpower cables to MOVs be analyzed during thetransition to NFPA 805?
  • Item 5 and 8C: Multiple concurrent Intercable andintractable hot shorts will need to be considered forhigh risk scenarios for ungrounded DC circuits. This is a possible backfit issue for Appendix R/NUREG 800 plants but must be considered if high risk. Will concurrent intercable and intractable hot shorts for ungrounded DC circuits be analyzed during the transition to NFPA 805?*Item 6: Will multiple high impedance faults beanalyzed during the transition to NFPA 805?
  • Item 7B and 8B: Will multiple concurrent spuriousoperations for these scenarios be analyzed during thetransition to NFPA 805?*Item 9 and 10: Will multiple concurrent spuriousoperations for intercable faults between thermoset and thermoplastic cables be analyzed during the transition to NFPA 805?Table B-2GeneralSimilar comments apply here as in EGR-NGGC-0102 above.3.5.1.1 Page 47Will cable to cable (intercable) faults between thermoset andthermoplastic cables be analyzed during the transition to NFPA 805? Will you bring forward this Prior NRC Approval for cable for cable faults during the transition to NFPA 805?3.5.1.5Page 51RIS 2004-03 risk informed inspection guidance applies foryour plants but it does constitute compliance. All cable failure modes need to be considered during the transition to NFPA 805 and these failure modes must not be limited by the RIS.

Will you consider all failure modes during the transition to NFPA 805? What does not applicable mean for the applicability of RIS?FPIP-0106Attachment 3Will you ensure that the IN 92-18 issue is addressed outsideof the Control Room including inside the MCC and at the valve during the transition to NFPA 805?

7 Legend:RG: Ray GallucciJSH: JS. Hyslop PF: Paul Fillion KSF: Key safety feature SSD: Safe-shutdown OGC: Office of the General Counsel NEI: Nuclear Energy Institute ISLOCA: Interfacing-systems loss-of-coolant accident RIS: Regulatory Issue Summary RCS: Reactor coolant system RCP: Reactor coolant pump CSIP: Containment safety initiatives program MCC: Motor control center