04/21-22/2009, Notice of Meeting with Progress Energy Carolinas, Inc., and Duke Energy Carolinas, LLC, to Discuss Topics Involving the License Amendment Requests to Transition the Shearon, Unit 1 and the Oconee, Units 1, 2 and 3
ML090990018
Person / Time
Site: Oconee, Harris  Duke Energy icon.png
Issue date: 04/10/2009
From: Vaaler M
Plant Licensing Branch II
To: Boyce T, Melanie Wong
Plant Licensing Branch II, Plant Licensing Branch II
Vaaler, Marlayna, NRR/DORL 415-1998
References
TAC MD8807, TAC MD8832, TAC MD8833, TAC MD8834
Download: ML090990018 (6)


Text

April 10, 2009 MEMORANDUM TO: Melanie C. Wong, Chief Plant Licensing Branch II-1 Division of Operating Reactor Licensing Thomas H. Boyce, Chief

/RA/

Plant Licensing Branch II-2 Division of Operating Reactor Licensing FROM:

Marlayna Vaaler, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing

SUBJECT:

FORTHCOMING MEETING WITH PROGRESS ENERGY CAROLINAS, INC., AND DUKE ENERGY CAROLINAS, LLC, TO DISCUSS TOPICS INVOLVING THE LICENSE AMENDMENT REQUESTS TO TRANSITION THE SHEARON HARRIS NUCLEAR PLANT, UNIT 1 AND THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3, TO THE NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805, PERFORMANCE BASED STANDARD FOR FIRE PROTECTION DATE & TIME:

Tuesday, April 21, 2009, from 10:00 a.m. - 5:00 p.m.

Wednesday, April 22, 2009, from 8:00 a.m. - 12:00 p.m.

LOCATION:

U.S. Nuclear Regulatory Commission One White Flint North 11545 Rockville Pike, Room O-3B4 Rockville, Maryland PURPOSE:

Discuss high level items associated with the Harris and Oconee LARs to transition to NFPA-805. NFPA-805 allows the use of performance-based methods, such as fire modeling, and risk-informed methods, such as Fire Probabilistic Risk Assessment (Fire PRA), to demonstrate compliance with the nuclear safety performance criteria. Regulatory audits were recently conducted at both sites, and several issues generic to both pilots were identified by the staff. This meeting will be an opportunity to further discuss these issues with the pilot plant licensees.

CONTACT:

Marlayna Vaaler, NRR 301-415-3178 Marlayna.Vaaler@nrc.gov

  • Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" (67 FR 36920), May 28, 2002. The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in a meeting (e.g., sign language), or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print), please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

M. Wong and CATEGORY 2*:

This is a Category 2 meeting. The public is invited to participate in this meeting by providing comments and asking questions at designated points identified on the agenda.

Teleconferencing: Interested members of the public unable to travel to the NRC Headquarters may participate by telephone via a toll-free teleconference. For details, please call the NRC meeting contact listed or the toll-free number, 1-800-368-5642, and ask the operator for a connection to the meeting contact. Those interested in participating in this meeting by teleconference should call or email the meeting contact as soon as possible, but no later that April 20, 2009.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC S. Weerakkody (NRR)

M Vaaler (NRR)

A. Klein (NRR)

H. Barrett (NRR)

P. Lain (NRR)

S. Laur (NRR)

M. Stambaugh (NRR)

AFBP and APLA staff as needed UTILITIES J. Ertman D. Goforth D. Corlett Progress Energy and Duke Energy staff/contractors as needed Docket Nos. 50-400, 50-269, 50-270, and 50-287

Enclosure:

Agenda cc w/enclosure: Distribution via ListServ

M. Wong and CATEGORY 2*:

This is a Category 2 meeting. The public is invited to participate in this meeting by providing comments and asking questions at designated points identified on the agenda.

Teleconferencing: Interested members of the public unable to travel to the NRC Headquarters may participate by telephone via a toll-free teleconference. For details, please call the NRC meeting contact listed or the toll-free number, 1-800-368-5642, and ask the operator for a connection to the meeting contact. Those interested in participating in this meeting by teleconference should call or email the meeting contact as soon as possible, but no later that April 20, 2009.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC S. Weerakkody (NRR)

M Vaaler (NRR)

A. Klein (NRR)

H. Barrett (NRR)

P. Lain (NRR)

S. Laur (NRR)

M. Stambaugh (NRR)

AFBP and APLA staff as needed UTILITIES J. Ertman D. Goforth D. Corlett Progress Energy and Duke Energy staff/contractors as needed Docket Nos. 50-400, 50-269, 50-270, and 50-287

Enclosure:

Agenda cc w/enclosure: Distribution via ListServ Accession Number: ML090990018 NRR-001 OFFICE NRR/LPL2-2/PM NRR/LPL2-2/LA NRR/LPL2-2/BC NAME MVaaler RSola TBoyce (MVaaler for)

DATE 04/10/2009 04/10/2009 04/10/2009 OFFICIAL RECORD

Memo to Melanie C. Wong and Thomas H. Boyce from Marlayna Vaaler dated April 10, 2009

SUBJECT:

FORTHCOMING MEETING WITH PROGRESS ENERGY CAROLINAS, INC.,

AND DUKE ENERGY CAROLINAS, LLC, TO DISCUSS TOPICS INVOLVING THE LICENSE AMENDMENT REQUESTS TO TRANSITION THE SHEARON HARRIS NUCLEAR PLANT, UNIT 1 AND THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3, TO THE NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805, PERFORMANCE BASED STANDARD FOR FIRE PROTECTION DISTRIBUTION:

NON-PUBLIC JAdams, EDO, Rgn II LPL2-1 R/F Receptionist OWFN and TWFN (hard copy)

LPL2-2 R/F PMNS RidsNrrDorlLpl2-1 (MWong)

AKlein, NRR RidsNrrDorlLpl2-2 (TBoyce)

Plain, NRR RidsNrrPMJStang HBarrett, NRR RidsPMMVaaler DHarrison, NRR RidsNrrLAMOBrien SLaur, NRR RidsNrrLACSola MGalloway, NRR RidsNrrDorl RGallucci, NRR RidsRgn2MailCenter JCircle, NRR RidsOpaMail SDinsmore, NRR KClark, OPA Rgn II MStambaugh, NRR RidsAcrs_Acnw&mMailCenter MCuningham, NRR RidsOgcMailCenter

CATEGORY 2 MEETING TO DISCUSS THE LICENSE AMENDMENT REQUESTS TO TRANSITION THE SHEARON HARRIS NUCLEAR PLANT, UNIT 1, AND THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3, TO THE NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805, PERFORMANCE BASED STANDARD FOR FIRE PROTECTION APRIL 21 & 22, 2009 AGENDA APRIL 21, 2009 10:00 a.m. - 10:15 a.m.

NRC and Industry Introductory Remarks 10:15 a.m. - 11:30 a.m.

Progress Energy Discussion of the Planned Treatment of Incipient Detection 11:30 a.m. - 11:45 a.m.

Opportunity for Public Comment 11:45 a.m. - 12:30 p.m.

LUNCH 12:30 p.m. - 2:15 p.m.

Continued Discussion of the Planned Treatment of Incipient Detection 2:15 p.m. - 2:30 p.m.

Opportunity for Public Comment 2:30 p.m. - 2:45 p.m.

BREAK 2:45 p.m. - 3:45 p.m.

Pilot Plant Discussion of Fire Modeling Verification and Validation 3:45 p.m. - 4:00 p.m.

Opportunity for Public Comment 4:00 p.m. - 5:00 p.m.

Pilot Plant Discussion on the Impact of Recovery Actions -

Transition of Operator Manual Actions into Recovery Actions 5:00 p.m.

ADJOURN

APRIL 22, 2009 8:00 a.m. - 9:00 a.m.

Continued Discussion on the Impact of Recovery Actions 9:00 a.m. - 9:15 a.m.

Opportunity for Public Comment 9:15 a.m. - 9:30 a.m.

BREAK 9:30 a.m. - 11:00 a.m.

Pilot Plant Discussion of Prior Approval of Fire PRA Methods to be Used in NFPA 805 Change Evaluations Post Transition 11:00 a.m. - 11:15 a.m.

Opportunity for Public Comment 11:15 a.m. - 11:45 a.m.

Discussion of License Amendment Request and NFPA 805 Infrastructure Schedules 11:45 a.m. - 12:00 p.m.

Closing Remarks and Final Opportunity for Public Comment 12:00 p.m.

ADJOURN