Submits Description of Spent Fuel Insp Program to Be Incorporated Into Tech Specs.Changes Concern Obtaining Photographic Record of Vertical Faces of Fuel Elements Removed from Core During Each Refueling
ML20094L286
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 07/31/1984
From: Warembourg D
PUBLIC SERVICE CO. OF COLORADO
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
P-84246, TAC-57625, NUDOCS 8408150306
Download: ML20094L286 (2)


Text

1 public service company *e (Cdletmde rI

, 16805 WCR 19 1/2, Platteville, Colorado 80651 ahi

^

July 31,1984 Fort St. Vrain Unit #1 P-84246

%M@EDWM  %

Mr. E. H. Johnson, Chief Reactor Project Branch I g Region IV 3m Nuclear Regulatory Commission j 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011

SUBJECT:

Fort St. Vrain Fuel Element Inspection Program

REFERENCES:

(1) NRC Letter, Johnson to Lee, Dated 5-11-84 (G-84158)

(2) PSC Letter, Warembourg to Johnson, Dated 5-21-84 (P-84153)

Dear Mr. Johnson:

The purpose of this letter is to provide you with a description of.

the spent fuel inspection program which Public Service Company of Colorado intends to propose be incorporated into the Fort St. Vrain Technical Specifications. Although a definite schedule for submitting the amendment request has not been established, the changes are expected to be addressed in the overall Technical Specification upgrade effort which is currently underway and expected to be completed well in advance of the fourth refueling outage.

The surveillance / inspection program description is as follows:

1) Obtain a photographic record of all six vertical faces of at least 90% of the spent fuel elements removed from the core during each refueling using the Fuel Handling Machine 35mm camera or the Cask Video Monitor.

8408150306 840731 gDRADOCK05000 'd O y0

=

Q4~=A ,

2)' ) Evaluate all photographic records for indications of significant abnormalities'which could have: an ef fect :. .'o n -the structural integrity of .the

' elements prior to returning to power operation following the refueling.

3) Promptly inform the Nuclear Regulatory Commission of'any significant abnormalities identified which could- have an effect on the structural integrity of a fuel element.

Such a surveillance / inspection program would be comparable to that conducted during'the-third-_ refueling outage, which was determined to be adequate;by LANL in Reference (1).

If you have any questions, please contact me at (303) 785-2224.

Very- truly yours, awAxA Don Warembourg Manager, Nuclear Production DWW/djm